Changes in the Quantities. 38.1. If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular item by more than 25 percent provided the change is attributed to the Department i.e., either the B.O.Q. is prepared by the department or variation is due to change/ modification ordered by the Department and the same exceeds 1% of initial Contract Price, the Engineer shall adjust the rate to allow for the change, duly considering, (a) Justification for rate adjustment as furnished by the contractor, (b) Economies resulting from increase in quantities by way of reduced plant, equipment, and overhead costs, (c) Entitlement of contractor to compensation events where such events are caused by any additional work 38.2. The Engineer shall not adjust rates from changes in quantities if thereby the Initial Contract Price is exceeded by more than 15 per cent, except with the Prior approval of the Chief Engineer, PWD, ▇▇▇▇▇▇▇▇▇, Guwahati-3, Assam. 38.3. If requested by the Engineer, the Contractor shall provide the Engineer with a detailed cost break down of any rate in the Bill of Quantities.
Changes in the Quantities. 5.1 The contractor is bound to execute all supplemental works that are found essential, incidental and inevitable during execution of main work. 5.2 The rates of all such items shall be Estimated Rates plus or minus overall Tender premium.
Changes in the Quantities. 36.1. The Contractor is bound to carry out the items in the Bill of Quantities itemwise variation upto 25 per cent excess provided that the change does not exceeds 1% of initial Contract Price.
Changes in the Quantities. 41.1 If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular item by more than 25 percent, provided the change not exceeds 1 percent of the Initial Contract Price, the Project Manager shall adjust the rate to allow for the change.
Changes in the Quantities. 38.1.If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular item by more than 25 per cent provided the change exceeds 1 % of initial Contract Price, the Engineer shall adjust the rate to allow for the change, duly considering, (a) Justification for rate adjustment as furnished by the contractor, (b) Economies resulting from increase in quantities by way of reduced plant, equipment, and overhead costs, (c) Entitlement of the contractor to compensation events where such events are caused by any additional work 38.2. The Engineer shall not adjust rates from changes in quantities if thereby the Initial Contract Price is exceeded by more than 15 per cent, except with the Prior approval of the Employer. 38.3. If requested by the Engineer, the Contractor shall provide the Engineer with a detailed cost breakdown of any rate in the Bill of Quantities.
Changes in the Quantities. 38.1. If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular item by more than 25 percent provided the change is attributed to the Department i.e., either the B.O.Q. is prepared by the department or variation is due to change/ modification ordered by the Department and the same exceeds 1% of initial Contract Price, the Engineer shall adjust the rate to allow for the change, duly considering, (a) Justification for rate adjustment as furnished by the contractor, (b) Economies resulting from increase in quantities by way of reduced plant, equipment, and overhead costs, (c) Entitlement of contractor to compensation events where such events are caused by any additional work 38.2. The Engineer shall not adjust rates from changes in quantities if thereby the Initial Contract Price is exceeded by more than 15 per cent, except with the Prior approval of the Managing Director, ASDC for SC Ltd, Dispur, Guwahati-6 38.3. If requested by the Engineer, the Contractor shall provide the Engineer with a detailed cost break down of any rate in the Bill of Quantities.
Changes in the Quantities. 38.1 If the final quantity of the work done differs from the quantity in the ▇▇▇▇ of Quantities for the particular item by more than 25 percent provided the change exceeds 1% of Initial Contract Price, the Engineer shall adjust the rate to allow for the change. 38.2 The Engineer shall not adjust rates from changes in quantities if thereby the Initial Contract Price is exceeded by more than 15 percent, except with the Prior approval of the Employer. 38.3 If requested by the Engineer, the Contractor shall provide the Engineer with a detailed cost breakdown of any rate in the ▇▇▇▇ of Quantities.
Changes in the Quantities. 38.1. If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular item by more than 25 percent provided the change is attributed to the Department i.e., either the B.O.Q. is prepared by the department or variation is due to change/ modification ordered by the Department and the same exceeds 1% of initial Contract Price, the Engineer shall adjust the rate to allow for the change, duly considering, (a) Justification for rate adjustment as furnished by the contractor, (b) Economies resulting from increase in quantities by way of reduced plant, equipment, and overhead costs, (c) Entitlement of contractor to compensation events where such events are caused by any additional work