Changes to GXPs. The following procedure will apply if the Distributor proposes to construct and operate, or agree with a Grid Owner to have constructed and operated, a new GXP, or permanently disconnect the Network from a GXP (a "Proposal"); (a) the Distributor must give the Trader notice of the following: (i) the ICPs, groups of ICPs ,or geographical area(s) that will be affected by the Proposal; and (ii) an estimate of the overall costs of the Proposal and a description of any benefits of the Proposal; (b) the Distributor must consult with the Trader about the Proposal for a reasonable period of time; and (c) if, at the conclusion of the consultation, the Distributor decides to proceed with the Proposal (including the Proposal as changed as a result of the consultation), the Distributor must give the Trader at least 20 Working Days' notice of the date on which the commissioning of a new GXP, or permanent disconnection of the Network from a GXP, is expected to be complete.
Appears in 41 contracts
Samples: Distributor Agreement, Distributor Agreement, Distributor Agreement
Changes to GXPs. The following procedure will apply if the Distributor proposes to construct and operate, or agree with a Grid Owner to have constructed and operated, a new GXP, or permanently disconnect the Network from a GXP (a "Proposal");
(a) ; the Distributor must give the Trader notice of the following:
(i) the ICPs, groups of ICPs ,or geographical area(s) that will be affected by the Proposal; and
(ii) an estimate of the overall costs of the Proposal and a description of any benefits of the Proposal;
(b) ; the Distributor must consult with the Trader about the Proposal for a reasonable period of time; and
(c) and if, at the conclusion of the consultation, the Distributor decides to proceed with the Proposal (including the Proposal as changed as a result of the consultation), the Distributor must give the Trader at least 20 Working Days' notice of the date on which the commissioning of a new GXP, or permanent disconnection of the Network from a GXP, is expected to be complete.
Appears in 2 contracts
Samples: Distributor Agreement, Distributor Agreement
Changes to GXPs. The following procedure will apply if the Distributor proposes to construct and operate, or agree with a Grid Owner to have constructed and operated, a new GXP, or permanently disconnect the Network from a GXP (a "“Proposal"”);
(a) the Distributor must give the Trader notice of the following:
(i) the ICPs, groups of ICPs ,ICPs, or geographical area(s) that will be affected by the Proposal; and
(ii) an estimate of the overall costs of the Proposal and a description of any benefits of the Proposal;
(b) the Distributor must consult with the Trader about the Proposal for a reasonable period of time; and
(c) if, at the conclusion of the consultation, the Distributor decides to proceed with the Proposal (including the Proposal as changed as a result of the consultation), the Distributor must give the Trader at least 20 Working Days' ’ notice of the date on which the commissioning of a new GXP, or permanent disconnection of the Network from a GXP, is expected to be complete.
Appears in 1 contract
Samples: Distribution Agreement
Changes to GXPs. The following procedure will apply if the Distributor proposes to construct and operate, or agree with a Grid Owner to have constructed and operated, a new GXP, or permanently disconnect the Network from a GXP (a "Proposal");
(a) the Distributor must give the Trader notice of the following:
(i) the ICPs, groups of ICPs ,ICPs, or geographical area(s) that will be affected by the Proposal; and
(ii) an estimate of the overall costs of the Proposal and a description of any benefits of the Proposal;
(b) the Distributor must consult with the Trader about the Proposal for a reasonable period of time; and
(c) if, at the conclusion of the consultation, the Distributor decides to proceed with the Proposal (including the Proposal as changed as a result of the consultation), the Distributor must give the Trader at least 20 Working Days' notice of the date on which the commissioning of a new GXP, or permanent disconnection of the Network from a GXP, is expected to be complete.
Appears in 1 contract
Samples: Distributor Agreement
Changes to GXPs. The following procedure will apply if the Distributor proposes to construct and operate, or agree with a Grid Owner to have constructed and operated, a new GXP, or permanently disconnect the Network from a GXP (a "“Proposal"”);
(a) the Distributor must give the Trader notice of the following:
(i) the ICPs, groups of ICPs ,or geographical area(s) that will be affected by the Proposal; and
(ii) an estimate of the overall costs of the Proposal and a description of any benefits of the Proposal;
(b) the Distributor must consult with the Trader about the Proposal for a reasonable period of time; and
(c) if, at the conclusion of the consultation, the Distributor decides to proceed with the Proposal (including the Proposal as changed as a result of the consultation), the Distributor must give the Trader at least 20 Working Days' ’ notice of the date on which the commissioning of a new GXP, or permanent disconnection of the Network from a GXP, is expected to be complete.
Appears in 1 contract
Samples: Distributor Agreement
Changes to GXPs. The following procedure will apply if the Distributor proposes to construct and operate, or agree with a Grid Owner to have constructed and operated, a new GXP, or permanently disconnect the Network from a GXP (a "Proposal");
(a) ; the Distributor must give the Trader notice of the following:
(i) the ICPs, groups of ICPs ,ICPs, or geographical area(s) that will be affected by the Proposal; and
(ii) an estimate of the overall costs of the Proposal and a description of any benefits of the Proposal;
(b) ; the Distributor must consult with the Trader about the Proposal for a reasonable period of time; and
(c) and if, at the conclusion of the consultation, the Distributor decides to proceed with the Proposal (including the Proposal as changed as a result of the consultation), the Distributor must give the Trader at least 20 Working Days' notice of the date on which the commissioning of a new GXP, or permanent disconnection of the Network from a GXP, is expected to be complete.
Appears in 1 contract
Samples: Distributor Agreement