Changes to the Work. 7.1 Changes to the Work may be accomplished by preparation of and execution of a change order or construction change directive. Change orders or construction change directives will be preceded by a change proposal request initiated by the Architect. The Construction Manager shall provide prices and details within 30 days of receipt of a change proposal request, and the Architect shall forward the completed change proposal request to the Owner within 15 days after receipt of the information provided by the Construction Manager.
7.2 For the purposes of this Agreement, a change order is a written document prepared by the Architect, and executed by the Owner, Construction Manager, and Architect, setting out in detail the specific change in the Work, the dollar amount of any adjustment to the GMP, if any, and any adjustment to the contract time.
7.3 For the purposes of this Agreement, a construction change directive is a written document prepared by the Architect and executed by the Owner, which serves to change the work and provides for any proposed adjustment in the GMP or contract time. A construction change directive shall be used in the event the parties to this Agreement cannot reach an agreement on the terms of a change order.
7.3.1 Upon request of the Owner or the Architect, the Construction Manager shall, without any increase in the GMP, submit to the Architect within 15 days, in such form as the Architect may require, an accurate written estimate of the cost of any proposed Work set forth in the construction change directive.
7.3.2 The estimate shall indicate the quantity and unit cost of each item of materials, and the number of hours of work and hourly rate for each class of labor, as well as the description and amounts of all other cost chargeable under the terms of this subparagraph. Unit labor costs for the installation of each item of materials shall be shown if required by the Architect. The Construction Manager shall promptly revise and resubmit such estimate if the Architect determines that it is not in compliance with the requirement of this Article, or that it contains errors of fact or mathematical errors. If required by the Architect, in order to establish the exact cost of new work added or of previously required work omitted, the Construction Manager shall obtain and furnish to the Architect bona fide proposals from recognized suppliers for furnishing any material included in such Work. Such estimates shall be furnished promptly so as t...
Changes to the Work. The Consultant shall prepare all reasonable changes to Construction Documents as required for the successful completion of the Project as requested by the State, and shall notify the State of additional services, if any, required by the State’s request.
Changes to the Work. Company may at any time, in writing, direct or authorize Contractor to make changes to the Work within the general scope of this Agreement. All such changes must be agreed upon and authorized in writing by each Party before Contractor’s implementation thereof. Company shall not be required to make any payment for any change that is not authorized in writing. If any change is performed by Contractor without such written authorization, Company may take the same actions and exercise the same rights and remedies with respect to such change that it would have with respect to any of the Work as though such change were in fact authorized.
Changes to the Work. The Publisher agrees to allow the Author to makes changes in the Work, at the final proof stage, costing up to an amount of Two Hundred Fifty dollars ($250), other than for corrections of compositor's errors. Should the cost of such alterations exceed this sum, the balance will be charged to the Author's royalty account, provided, also, however, that the Publisher shall promptly furnish to the Author an itemized statement of such additional expenses, and shall make available the corrected proofs for inspection by the Author. The Author agrees to correct and return, no later than ten (10) days after the receipt thereof, proofs provided by the Publisher. The Author agrees to deliver to the Publisher final revised copy satisfactory to the Publisher in content and form.
Changes to the Work. A. When Architect establishes that the method of valuation for Changes in the Work will be net cost plus a percentage fee in accordance with General Conditions, our percentage fee will be:
Changes to the Work. The District may, by written order, make Changes to the Work, issue additional instructions and to add to or delete from the Work. No Change may be made without the prior written approval and direction of the District. Adjustments of the Contract Price or the Contract Time on account of a Change authorized hereunder will only be made by written Change Order duly executed by the Contractor and the District Representative. Adjustments to the Contract Price for authorized Changes shall be limited to the actual costs of labor and materials necessary to complete the Change plus a xxxx-up of fifteen percent (15%) of the actual costs of labor and materials; it being agreed that the xxxx-up represents all compensation due the Contractor for profit, overhead/administrative costs and impacts of an authorized Change.
Changes to the Work. Siemens shall deliver and/or perform the Work in accordance with the Applicable Laws in effect on the Effective Date. No change will be made to the scope of Work unless Xxxxx and Siemens agree in writing to the change and any resulting price, schedule or other contractual modifications associated therewith. If any change to any law, rule, regulation, order, code, standard or requirement impacts Siemens’ obligations or performance under this Agreement, Siemens may request a change order for an equitable adjustment in the price and time of performance.
Changes to the Work. (a) District may, at any time, by written order, make unilateral changes in the Work. Such changes include, but are not limited to, changes:
(1) in the Specifications or Plans;
(2) in the sequence, method, or manner of performance of the Work;
(3) in the District-furnished facilities, equipment, materials, services or site; or
(4) directing acceleration of the Work.
(b) If such changes cause an increase or decrease in Lessor's cost of, or time required for, performance of this Facilities Lease, the District shall order a Change Order. Such Change Orders shall be funded utilizing the District Contingency.
(c) A change pursuant to this Section 15.01 may begin in the form of a CCD and will result in the form of a Change Order which will set forth the additional, deleted or otherwise changed Work to be done or the method by which the change and cost adjustment, if any, will be determined, and the time of completion of the Work. Upon receipt of a written CCD using the form supplied in these Contract Documents, Lessor shall proceed with the ordered Work. If ordered in writing by the Architect and approved by District, Lessor shall proceed with the Work so ordered prior to actual receipt of a Change Order. A Change Order executed by Contractor and approved by both the Architect and District is an executed Contract Change Order as that term is used throughout this Section. Under no circumstances shall a verbal direction constitute a basis for proceeding with a Change Order. A change to the contract that involves adding time or cost, shall be approved if, and only if, the item is related to unforeseen conditions or owner directed changes. Substitutions are considered change orders and, if DSA approval is required, are to be approved by DSA prior to fabrication or use. All associated costs with a Contractor driven substitution will be at the expense of the Lessor, including DSA fees, Architect fees, Engineering fees, etc.
Changes to the Work. Subcontractor may be required by Contractor, without invalidating this Agreement or the applicable Statement of Work, to make changes to the Work within the general scope of the Statement of Work. The Contract Price and schedule shall only be adjusted accordingly by written agreement with the Contractor (a “Change Order”). Upon Contractor’s issuance of a Change Order, Subcontractor shall promptly perform the Work as altered by the Change Order. Subcontractor shall give Contractor written notice, including a complete detailed breakdown, of any request to change the schedule or Contract Price within three (3) days of any Change Order. Subcontractor’s failure to provide such written notice shall waive any such claim to adjust the schedule or Contract Price. If Contractor and Subcontractor do not agree on the amount of a requested change to the Contract Price, it is agreed that the Subcontractor shall be entitled to an amount equal to Subcontractor’s actual costs plus fifteen percent (15%) for reasonable overhead and profits. Subcontractor acknowledges that Contractor’s signing of labor and materials slips shall be for verification purposes only, and shall not be construed as approval of Subcontractor’s request for adjustment.
Changes to the Work. The City and TriMet recognize and acknowledge that there may be changes required to the plans and specifications during construction. • TriMet and the City agree to make timely responses as appropriate and required to keep the work progressing.