Common use of Claims for Additional Time Clause in Contracts

Claims for Additional Time. 1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 14 contracts

Samples: Contract for Construction, Contract for Construction, Contract for Construction

AutoNDA by SimpleDocs

Claims for Additional Time. 1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 14 contracts

Samples: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

Claims for Additional Time. 1 4.2.7.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary.

Appears in 1 contract

Samples: Construction Contract (National Instruments Corp /De/)

Claims for Additional Time. 1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary.

Appears in 1 contract

Samples: Construction Contract

AutoNDA by SimpleDocs

Claims for Additional Time. 1 § 15.1.5.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 1 contract

Samples: Roof Replacement Agreement

Claims for Additional Time. 1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of the cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 1 contract

Samples: Small Construction Projects Contract