Claims for Additional Time. § 14.1.6.1 If the Design-Builder intends to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary. § 14.1.6.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated, and had an adverse effect on the scheduled construction.
Appears in 13 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
Claims for Additional Time. § 14.1.6.1 15.1.5.1 If the Design-Builder intends Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-BuilderContractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.
§ 14.1.6.2 15.1.5.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated, anticipated and had an adverse effect on the scheduled construction.
Appears in 6 contracts
Samples: Standard Form of Agreement Between Owner and Contractor, Construction Contract, Construction Contract
Claims for Additional Time. § 14.1.6.1 15.1.6.1 If the Design-Builder intends Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein in Section 15.1.3 shall be given. The Design-BuilderContractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.
§ 14.1.6.2 15.1.6.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated, and had an adverse effect on the scheduled construction.
Appears in 5 contracts
Samples: Standard Form of Agreement Between Owner and Contractor, Construction Contract, Standard Form of Agreement Between Owner and Contractor
Claims for Additional Time. § 14.1.6.1 4.3.7.1 If the Design-Builder intends Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Contractor's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary.
§ 14.1.6.2 4.3.7.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated, anticipated and had an adverse effect on the scheduled construction.
Appears in 3 contracts
Samples: Lease Agreement (Immunicon Corp), Construction Contract (Empire Resorts Inc), Standard Form of Agreement Between Owner and Contractor (Corixa Corp)
Claims for Additional Time. § 14.1.6.1 If the Design-Builder intends to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Within 21 days after giving notice, the Design-Builder’s Claim Builder shall include provide an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.
§ 14.1.6.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated, and had an adverse effect on the scheduled construction.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder (Fox Factory Holding Corp)
Claims for Additional Time. § 14.1.6.1 15.1.5.1 If the Design-Builder intends Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Contractor's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.
§ 14.1.6.2 15.1.5.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated, anticipated and had an adverse effect effuct on the scheduled construction.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Contractor (STAMPS.COM Inc)
Claims for Additional Time. § 14.1.6.1 A.4.1.7.1 If the Design-Builder intends wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary.
§ 14.1.6.2 A.4.1.7.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated, anticipated and had an adverse effect on the scheduled construction.
Appears in 1 contract
Claims for Additional Time. § 14.1.6.1 If the Design-Builder intends to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.
§ 14.1.6.2 If exceptional and unusual adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated, and had an adverse effect on the scheduled construction.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
Claims for Additional Time. DRAFT
§ 14.1.6.1 If the Design-Builder intends to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.. The Design- Builder shall provide to Owner a fragnet to the schedule showing the effect of the Claim for an increase in the
§ 14.1.6.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated, and had an adverse effect on the scheduled construction.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder