Common use of Claims for Additional Time Clause in Contracts

Claims for Additional Time. § 14.1.6.1 If the Design-Builder intends to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 21 contracts

Samples: Agreement, Design Build Construction Agreement, Agreement

AutoNDA by SimpleDocs

Claims for Additional Time. § 14.1.6.1 4.3.7.1 If the Design-Builder intends Contractor wishes to make a Claim for an any increase in the Contract Time, specific written notice as provided herein defined in Paragraph 4.3.3 shall be given. The Design-Builder’s Contractor's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary.

Appears in 16 contracts

Samples: Agreement, Agreement, Agreement

Claims for Additional Time. § 14.1.6.1 15.1.6.1 If the Design-Builder intends Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein in Section 15.1.3 shall be given. The Design-BuilderContractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 5 contracts

Samples: files.josephlombardo.com, www.fountaininngas.org, www.gov.bm

Claims for Additional Time. § 14.1.6.1 A.4.1.7.1 If the Design-Builder intends wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost the time and of probable its effect of delay on the progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 4 contracts

Samples: www.unlv.edu, www.unlv.edu, www.unlv.edu

Claims for Additional Time. § 14.1.6.1 If the Design-Builder intends to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary. If the Design-Builder wishes to make claim of an increase in the Contract Time, the Design-Builder shall give the Manager written notice thereof within fifteen (15) days after occurrence of the event giving rise to such claim.

Appears in 2 contracts

Samples: rfp.hawaiiconvention.com, rfp.hawaiiconvention.com

Claims for Additional Time. § 14.1.6.1 If the Design-Builder intends to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary. If Design-Builder makes any claim for delay, Design-Builder shall specifically set forth how and why the delay in question affected the critical path, including submission of a time impact analysis based upon the most recently submitted schedule.

Appears in 2 contracts

Samples: www.durhamnc.gov, www.ci.gladstone.or.us

Claims for Additional Time. § 14.1.6.1 A.4.1.7.1 If the Design-Builder intends wishes to make a Claim for an increase in the Contract Time, written notice as Time provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on the the progress of the Work. In the case of a continuing delay, only one Claim notice is necessary.necess

Appears in 2 contracts

Samples: cdn.cocodoc.com, homeforward.org

Claims for Additional Time. § 14.1.6.1 If the Design-Builder intends to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 1 contract

Samples: Agreement

Claims for Additional Time. § 14.1.6.1 If the Design-Builder intends to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Within 21 days after giving notice, the Design-Builder’s Claim Builder shall include provide an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 1 contract

Samples: Fox Factory Holding Corp

AutoNDA by SimpleDocs

Claims for Additional Time. § 14.1.6.1 15.1.6.1 If the Design-Builder intends Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein in Section 15.1.3 shall be given. The Design-BuilderContractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 1 contract

Samples: agenda.webbcountytx.gov:8085

Claims for Additional Time. § 14.1.6.1 A.4.1.7.1 If the Design-Builder intends wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary.

Appears in 1 contract

Samples: Badger State Ethanol LLC

Claims for Additional Time. § 14.1.6.1 If the Design-Builder intends to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary. If the Design- Builder wishes to make claim of an increase in the Contract Time, the Design-Builder shall give the Manager written notice thereof within fifteen (15) days after occurrence of the event giving rise to such claim.

Appears in 1 contract

Samples: rfp.hawaiiconvention.com

Claims for Additional Time. § 14.1.6.1 3.8.1 If the Design-Builder intends Construction Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be givenprovided to the Owner’s Project Representative. The Design-Builder’s Claim Construction Contractor shall include an estimate have the burden of cost and of probable demonstrating the effect of the claimed delay on progress of the WorkContract Time, and shall furnish the ARCHITECT with such supporting documents as the ARCHITECT may reasonably require. In the case of a continuing delay, only one Claim is necessary.

Appears in 1 contract

Samples: bids.findrfp.com

Claims for Additional Time. § 14.1.6.1 If the Design-Builder intends to make a Claim for an increase in the Contract Time, written Xxx notice as provided herein shall be given. The Design-Builder’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 1 contract

Samples: resources.finalsite.net

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!