Claims for Additional Time. 5.11.1 Time is of the essence of this Agreement. The GMP Basis Documents must be submitted no later than the date set forth in Exhibit M and the Project must be Substantially Complete no later than the Substantial Completion Date set forth within the Project Information Section above.
Appears in 10 contracts
Claims for Additional Time. 5.11.1 5.11.1. Time is of the essence of this Agreement. The GMP Basis Documents must be submitted no later than the date set forth in Exhibit M and the Project must be Substantially Complete no later than the Substantial Completion Date set forth within the Project Information Section above.
Appears in 7 contracts
Samples: Design Build Agreement, Agreement, This Agreement
Claims for Additional Time. 5.11.1 5.11.1. Time is of the essence of this Agreement. The GMP Basis Documents must be submitted no later than the date set forth in Exhibit M within the Project Information Section and the Project must be Substantially Complete no later than the Substantial Completion Date set forth within the Project Information Section above.
Appears in 7 contracts
Claims for Additional Time. 5.11.1 Time is of the essence of this Agreement. The GMP Basis Project Documents must be submitted no later than the date set forth in Exhibit M and the Project must be Substantially Complete no later than the Substantial Completion Date set forth within the Project Information Section above.
Appears in 2 contracts
Samples: Design Build Agreement, Agreement
Claims for Additional Time. 5.11.1 Time is of the essence of this Agreement. The GMP Basis Documents Project documents must be submitted no later than the date set forth in Exhibit M and the Project must be Substantially Complete no later than the Substantial Completion Date set forth within the Project Information Section above.
Appears in 2 contracts
Samples: Agreement, Design Build Agreement