Clarifications and Interpretations. The Project Manager will issue with reasonable promptness such written clarifications or interpretations of this Contract as may be necessary. If the Design-Builder believes that a written clarification or interpretation justifies an increase in the Guaranteed Maximum Price or the Contract Time, the Design-Builder may notify the City as provided in Article 9.
Appears in 4 contracts
Samples: Progressive Design Build Agreement, Progressive Design‐build Agreement, Progressive Design Build Agreement