Commissioning Tests. 9.1.1. At least 30 (thirty) days prior to the likely date of commissioning of the Facility, Seller shall notify the Independent Engineer and CEB of its intent to subject the Facility to Commissioning Tests. The date and time of each of the tests shall be determined by the Independent Engineer in consultation with Seller and notified to CEB who may designate its representative(s) to witness the Commissioning Tests. Seller shall provide such assistance as the Independent Engineer may reasonably require for witnessing the Tests. In the event that Seller and the Independent Engineer fail to mutually agree on the dates for conducting the tests, Seller shall fix the dates by not less than 10 (ten) days’ written notice to the Independent Engineer and CEB. 9.1.2. All Commissioning Tests shall be conducted in accordance with the testing procedures specified in Schedule H. The Independent Engineer shall observe, monitor and review the results of the tests to determine compliance of the Facility with this Agreement, and if it is reasonably anticipated or determined by the Independent Engineer during the course of any test that the performance of the Facility or any part thereof does not meet the provisions of this Agreement, it shall have the right to suspend or delay such test and require Seller to remedy and rectify the defects or deficiencies. Upon completion of each test, the Independent Engineer shall provide to Seller and CEB copies of all test data including detailed test results. For the avoidance of doubt, it is expressly agreed that the Independent Engineer may, at the cost of Seller, require Seller to carry out or cause to be carried out additional tests, in accordance with Good Industry Practice, for determining the compliance of the Facility with the Specifications and Standards and the Guaranteed Operating Characteristics.

Appears in 5 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Commissioning Tests. 9.1.1. At least 30 (thirty) days prior to the likely date of commissioning of the Facility, Seller shall notify the Independent Engineer and CEB of its intent to subject the Facility to Commissioning Tests. The date and time of each of the tests shall be determined by the Independent Engineer in consultation with Seller and notified to CEB who may designate its representative(s) to witness the Commissioning Tests. Seller shall provide such assistance as the Independent Engineer may reasonably require for witnessing the Tests. In the event that Seller and the Independent Engineer fail to mutually agree on the dates for conducting the tests, Seller shall fix the dates by not less than 10 (ten) days’ days‟ written notice to the Independent Engineer and CEB. 9.1.2. All Commissioning Tests shall be conducted in accordance with the testing procedures specified in Schedule H. The Independent Engineer shall observe, monitor and review the results of the tests to determine compliance of the Facility with this Agreement, and if it is reasonably anticipated or determined by the Independent Engineer during the course of any test that the performance of the Facility or any part thereof does not meet the provisions of this Agreement, it shall have the right to suspend or delay such test and require Seller to remedy and rectify the defects or deficiencies. Upon completion of each test, the Independent Engineer shall provide to Seller and CEB copies of all test data including detailed test results. For the avoidance of doubt, it is expressly agreed that the Independent Engineer may, at the cost of Seller, require Seller to carry out or cause to be carried out additional tests, in accordance with Good Industry Practice, for determining the compliance of the Facility with the Specifications and Standards and the Guaranteed Operating Characteristics.

Appears in 1 contract

Samples: Energy Supply and Purchase Agreement