Commissioning Tests. 4.2.1 After a Unit has been successfully Synchronized with the Grid System, the Company shall further give at least seven (7) days notice by fax followed by registered mail to the HPSEBL of the exact date(s) on which Commissioning Test(s) will commence. The HPSEBL shall designate its authorized representative to observe these test(s). 4.2.2 The Company shall conduct Commissioning Tests within fifteen (15) days from the Synchronization Date, in the presence of an Independent Engineer appointed by both the Parties and the authorized representative of HPSEBL. The Independent Engineer and the authorized representative of the HPSEBL shall submit a certificate of the Tested Capacity and necessary performance tests of the plant to the Chief Engineer (Commercial), HPSEBL, Shimla or to any other authority as may be designated by the HPSEBL. After successful completion of the Commissioning Tests, trial operation of the Unit(s) shall be carried out by the Company for a period of 15 days to establish the reliability and stability of the Generating Unit(s). The Company shall also furnish a copy of the Tests results and the report regarding trial operation to the HPSEBL.
Appears in 3 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Commissioning Tests. 4.2.1 After a Unit has been successfully Synchronized with the Grid System, the Company shall further give at least atleast seven (7) days notice by fax followed by registered mail to the HPSEBL of the exact date(s) on which Commissioning Test(s) will commence. The HPSEBL shall designate its authorized representative to observe these test(s).
4.2.2 The Company shall conduct Commissioning Tests within fifteen (15) days from the Synchronization Date, in the presence of an Independent Engineer appointed by both the Parties and the authorized representative of HPSEBL. The Independent Engineer and the authorized representative of the HPSEBL shall submit a certificate of the Tested Capacity and necessary performance tests of the plant to the Chief Engineer (Commercial), ) HPSEBL, Shimla or to any other authority as may be designated by the HPSEBL. After successful completion of the Commissioning Tests, trial operation of the Unit(s) shall be carried out by the Company for a period of 15 days to establish the reliability and stability of the Generating Unit(s). The Company shall also furnish a copy of the Tests Test results and the report regarding trial operation to the HPSEBL.
Appears in 2 contracts