Compensation for Extension of Project Time. 4.1.1 If the A/E notifies the Owner and Contracting Authority not less than 30 days before the date for completion of the Project identified in the approved Project Schedule, that the time for completion is reasonably expected to be exceeded by more than ten percent through no fault of the A/E, the A/E’s compensation for Services to be rendered during such extended period shall be negotiated to the mutual reasonable satisfaction of the Contracting Authority, Owner, and A/E. 4.1.2 If, through such negotiation, the Contracting Authority and Owner agree that the A/E shall be paid additional compensation, an amendment to that effect shall be executed in accordance with Section 4.3. 4.1.3 That amendment shall be executed before the A/E renders any Services made necessary by the extension of the time of completion, unless otherwise agreed in writing by the Contracting Authority and Owner.
Appears in 12 contracts
Samples: Professional Services, Professional Services, Architect/Engineer Agreement
Compensation for Extension of Project Time. 4.1.1 If the A/E Consultant notifies the Owner and Contracting Authority not less than 30 days before the date for completion of the Project identified set in the approved Project Schedule, that the time for completion is reasonably expected to be exceeded by more than ten percent extended through no fault of the A/EConsultant, and for good cause shown, the A/EConsultant’s compensation for Services to be rendered during such extended period period, shall be negotiated to the mutual reasonable satisfaction of the Contracting Authority, Owner, Owner and A/E.Consultant.
4.1.2 If, through such negotiation, the Contracting Authority and Owner agree agrees, in its sole discretion, that the A/E Consultant shall be paid additional compensation, an amendment to that effect shall be executed in accordance with Section 4.3.
4.1.3 That Such amendment shall be executed before the A/E Consultant renders any Services made necessary by the such extension of the time of completion, unless otherwise agreed in writing by the Contracting Authority and Owner.
Appears in 5 contracts
Samples: Consultant Agreement, Consultant Agreement, Consultant Agreement
Compensation for Extension of Project Time. 4.1.1 If the A/E notifies the Owner and Contracting Authority not less than 30 days before the date for completion of the Project identified set in the approved Project Schedule, that the time for completion is reasonably expected to be exceeded by more than ten 10 percent through no fault of the A/E, the A/E’s compensation for Services to be rendered during such extended period period, shall be negotiated to the mutual reasonable satisfaction of the Contracting Authority, Owner, and A/E.
4.1.2 If, through such negotiation, the Contracting Authority and Owner agree that the A/E shall be paid additional compensation, an amendment to that effect shall be executed in accordance with Section 4.3.
4.1.3 That Such amendment shall be executed before the A/E renders any Services made necessary by the such extension of the time of completion, unless otherwise agreed in writing by the Contracting Authority and Owner.
Appears in 4 contracts
Samples: Professional Services, Professional Services, Professional Services
Compensation for Extension of Project Time. 4.1.1 If the A/E notifies the Owner and the Contracting Authority not less than 30 days before the date for completion of the Project identified set in the approved Project Schedule, that the time for completion is reasonably expected to be exceeded by more than ten 10 percent through no fault of the A/E, the A/E’s compensation for Services to be rendered during such extended period period, shall be negotiated to the mutual reasonable satisfaction of the Contracting Authority, Owner, the Owner and the A/E.
4.1.2 If, through such negotiation, the Contracting Authority and Owner agree that the A/E shall be paid additional compensation, an amendment to that effect shall be executed in accordance with Section 4.3.
4.1.3 That Such amendment shall be executed before the A/E renders any Services made necessary by the such extension of the time of completion, unless otherwise agreed in writing by the Contracting Authority and the Owner.
Appears in 2 contracts
Samples: Professional Services, Architect/Engineer Standard Terms and Conditions
Compensation for Extension of Project Time. 4.1.1 .1 If the A/E notifies the Owner and Contracting Authority Owner, not less than 30 days before prior to the date time for completion of the Project identified in set by the approved Project Schedule, that the such time for completion is reasonably expected to be exceeded by more than ten 10 percent through no fault of the A/E, the A/E’s compensation compensation, if any, for Basic Services to be rendered during such extended period period, shall be negotiated to the mutual reasonable satisfaction of the Contracting Authority, Owner, Owner and the A/E.
4.1.2 .2 If, through such negotiation, the Contracting Authority and Owner agree agrees that the A/E shall be paid additional compensation, an amendment to that effect shall be executed in accordance with Section 4.3subparagraph 9.6.2.
4.1.3 That .3 Such amendment shall be executed before the A/E renders any Services services made necessary by the such extension of the time of completion, unless otherwise agreed in writing by the Contracting Authority and Owner.
Appears in 2 contracts
Samples: Architect/Engineer Agreement, Architect/Engineer Agreement
Compensation for Extension of Project Time. 4.1.1 If the A/E notifies the Owner and Contracting Authority not less than 30 days before the date for completion of the Project identified set in the approved Project Schedule, that the time for completion is reasonably expected to be exceeded by more than ten 10 percent through no fault of the A/E, the A/E’s compensation for Services to be rendered during such extended period period, shall be negotiated to the mutual reasonable satisfaction of the Contracting Authority, Owner, Owner and A/E.
4.1.2 If, through such negotiation, the Contracting Authority and Owner agree that the A/E shall be paid additional compensation, an amendment to that effect shall be executed in accordance with Section 4.3.
4.1.3 That Such amendment shall be executed before the A/E renders any Services made necessary by the such extension of the time of completion, unless otherwise agreed in writing by the Contracting Authority and Owner.
Appears in 1 contract
Samples: Professional Services
Compensation for Extension of Project Time. 4.1.1 If the A/E notifies the Owner and Contracting Authority not less than 30 days before the date for completion of the Project identified setidentified in the approved Project Schedule, that the time for completion is reasonably expected to be exceeded by more than 10 ten percent through no fault of the A/E, the A/E’s compensation for Services to be rendered during such extended period period, shall be negotiated to the mutual reasonable satisfaction of the Contracting Authority, Owner, and A/E.
4.1.2 If, through such negotiation, the Contracting Authority and Owner agree that the A/E shall be paid additional compensation, an amendment to that effect shall be executed in accordance with Section 4.3.
4.1.3 That SuchThat amendment shall be executed before the A/E renders any Services made necessary by the suchthe extension of the time of completion, unless otherwise agreed in writing by the Contracting Authority and Owner.
Appears in 1 contract
Samples: Professional Services