Conditions Precedent to a Service Period. a. A Service Period does not commence unless and until each of the conditions set out in this clause have been satisfied in accordance with clause 6.3(b) or waived in accordance with clause 6.3(c). b. The conditions precedent to a Service Period are: i. NAFC receiving from the Contractor a copy of an applicable and valid AOC; and ii. NAFC receiving from the Contractor a copy of all relevant documentation iii. NAFC receiving from the Contractor the performance bond where required; and iv. confirmation from a Member that the requirements of this Contract for the Services have been met; and v. the Contractor receiving written notice from NAFC or a Member requesting that a Service Period is to commence at a specified time and date. vi. the Contractor accepting a request from NAFC or a Member to commence a Service Period at a specified time and date. c. The satisfaction of a condition precedent to the Service Period can only be waived by written notice from NAFC to the Contractor. d. Where a Contractor fails to commence a Service Period at an agreed date and time then the Service will be considered Not Serviceable.
Appears in 2 contracts
Samples: Contract for Call When Needed Services, Contract for Call When Needed Services
Conditions Precedent to a Service Period.
a. A Service Period does not commence unless and until each of the conditions set out in this clause have been satisfied in accordance with clause 6.3(b) or waived in accordance with clause 6.3(c).
b. The conditions precedent to a Service Period are:
i. NAFC receiving from the Contractor a copy of an applicable and valid AOC; and
ii. NAFC receiving from the Contractor a copy of all relevant documentationdocumentation evidencing the Contractor’s insurance and its currency; and
iii. NAFC receiving from the Contractor the performance bond Performance Bond where required; and
iv. confirmation from acceptance by a Member that the requirements of this Contract for the Services have been met; and
v. the Contractor receiving written notice from NAFC or a Member requesting that a advising the date on which the Service Period is to commence at a specified time and date.
vi. in accordance with the Contractor accepting a request from NAFC or a Member to commence a Service Period at a specified time and dateNotice Period.
c. The satisfaction of a condition precedent to the Service Period can only be waived by written notice from NAFC to the Contractor.
d. Where a Contractor fails to commence a Service Period at an agreed date and time then the Service will be considered Not Serviceable.
Appears in 1 contract
Samples: Contract for Services
Conditions Precedent to a Service Period. a. A Service Period does not commence unless and until each of the conditions set out in this clause have been satisfied in accordance with clause 6.3(b) or waived in accordance with clause 6.3(c).
b. The conditions precedent to a Service Period are:
i. NAFC receiving from the Contractor a copy of an applicable and valid AOC; and
ii. NAFC receiving from the Contractor a copy of all relevant documentationdocumentation evidencing the Contractor’s insurance and its currency; and
iii. NAFC receiving from the Contractor the performance bond Performance Bond where required; and
iv. confirmation from acceptance by a Member that the requirements of this Contract for the Services have been met; and
v. the Contractor receiving written notice from NAFC or a Member requesting that a advising the date on which the Service Period is to commence at a specified time and date.
vi. in accordance with the Contractor accepting a request from NAFC or a Member to commence a Service Period at a specified time and dateNotice Period.
c. The satisfaction of a condition precedent to the Service Period can only be waived by written notice from NAFC to the Contractor.
d. Where a Contractor fails to commence a Service Period at an agreed date and time then the Service will be considered Not Serviceable.
Appears in 1 contract
Samples: Contract for Services
Conditions Precedent to a Service Period. a. A Service Period does not commence unless and until each of the conditions set out in this clause have been satisfied in accordance with clause 6.3(b) or waived in accordance with clause 6.3(c).
b. The conditions precedent to a Service Period are:
i. NAFC receiving from the Contractor a copy of an applicable and valid AOC; and
ii. NAFC receiving from the Contractor a copy of all relevant documentation
iii. NAFC receiving from the Contractor the performance bond where required; and
iv. confirmation from a Member that the requirements of this Contract for the Services have been met; and
v. the Contractor receiving written notice from NAFC or a Member requesting that a advising the date on which the Service Period is to commence at a specified time and date.
vi. in accordance with the Contractor accepting a request from NAFC or a Member to commence a Service Period at a specified time and dateNotice Period.
c. The satisfaction of a condition precedent to the Service Period can only be waived by written notice from NAFC to the Contractor.
d. Where a Contractor fails to commence a Service Period at an agreed date and time then the Service will be considered Not Serviceable.