Constructability and Plan Reviews Clause Samples
Constructability and Plan Reviews. 4.4.1. The Construction Manager must conduct constructability reviews and site verifications of the Project at the following times:
4.4.1.1. At the end of the Preliminary Plans / Design Development Phase
4.4.1.2. At 50% through the Working Drawings Phase (NYA)
4.4.1.3. At 90% through the Working Drawings Phase (NYA)
4.4.1.4. When Working Drawings are 100% complete (NYA)
4.4.2. The Construction Manager must review the design documents for code compliance, clarity, consistency, constructability and coordination. The results of the review must be provided in writing and in electronic database or spreadsheet format and as notations on the documents to the Project Manager. The Construction Manager must also make recommendations to the Project Manager with respect to constructability, construction cost sequence of construction, construction duration and separation of the contracts for various projects into categories of the work and separate Bid trade packages. However, the Construction Manager is not responsible for providing, nor does the Construction Manager control, the Project design or the contents of the design documents.
4.4.3. Construction Manager’s actions in reviewing the Project design and the design documents and in making recommendations as provided herein are advisory only to the Council. The Design Team members are not third party beneficiaries of the Construction Manager’s work described in this paragraph and the Design Team members remain solely responsible for the contents of design drawings and design documents.
Constructability and Plan Reviews. 4.3.1. The Construction Manager shall conduct constructability reviews and site verifications of the Project at the following times:
4.3.1.1. At the end of the Preliminary Plans / Design Development Phase
4.3.1.2. At 50% through the Working Drawings Phase
4.3.1.3. At 75% through the Working Drawings Phase
4.3.1.4. When Working Drawings are 100% complete
4.3.2. The Construction Manager shall review the design documents for code compliance, clarity, consistency, constructability and coordination. The results of the review shall be provided in writing and as notations on the documents to the Project Manager. The Construction Manager shall also make recommendations to the Project Manager with respect to constructability, construction cost sequence of construction, construction duration and separation of the contracts for various projects into categories of the work and separate bid trade packages. However, the Construction Manager is not responsible for providing, nor does the Construction Manager control, the Project design or the contents of the design documents.
Constructability and Plan Reviews. 2.24.1 If requested for an Assigned Project, the Consultant must review the design documents for code compliance, clarity, consistency, constructability and coordination. The results of the review must be provided in writing and in electronic database or spreadsheet format and as notations on the documents to the Manager. The Consultant must also make recommendations to the Manager with respect to constructability, construction cost sequence of construction, construction duration and separation of the contracts for various projects into categories of the work and separate Bid trade packages. However, the Consultant is not responsible for providing, nor does the Consultant control, the Assigned Project design or the contents of the design documents.
Constructability and Plan Reviews. The Construction Manager shall conduct constructability reviews and site verifications of the Project at the following times: At the end of the Preliminary Plans / Design Development Phase At 50% through the Working Drawings Phase At 75% through the Working Drawings Phase When Working Drawings are 100% complete The Construction Manager shall review the design documents for code compliance, clarity, consistency, constructability and coordination. The results of the review shall be provided in writing and as notations on the documents to the Project Manager. The Construction Manager shall also make recommendations to the Project Manager with respect to constructability, construction cost sequence of construction, construction duration and separation of the contracts for various projects into categories of the work and separate bid trade packages. However, the Construction Manager is not responsible for providing, nor does the Construction Manager control, the Project design or the contents of the design documents. Construction Manager’s actions in reviewing the Project design and the design documents and in making recommendations as provided herein are advisory only to the Council. The Design Team members are not third party beneficiaries of the Construction Manager’s work described in this paragraph and the Design Team members remain solely responsible for the contents of design drawings and design documents.
Constructability and Plan Reviews. 3.3.1 The Construction Manager must conduct constructability reviews and site verifications of the Project when Working Drawings are 100% complete and as bid packages are being prepared by CMR and approved by the Council.
3.3.1. The Construction Manager must review the design documents for code compliance, clarity, consistency, constructability and coordination. The results of the review must be provided in writing and in electronic database or spreadsheet format and as notations on the documents to the Project Manager. The Construction Manager must also make recommendations to the Project Manager with respect to constructability, construction cost sequence of construction, construction duration and separation of the contracts for various projects into categories of the work and separate Bid trade packages. However, the Construction Manager is not responsible for providing, nor does the Construction Manager control, the Project design or the contents of the design documents.