Common use of Construction Completion Deadline Clause in Contracts

Construction Completion Deadline. If Commercial Operation of the SEF does not occur on or before [ ] (the “Guaranteed Commercial Operation Date”), subject to extension due to delays arising out of any Force Maujer events, any Buyer Acts, any Governmental Approvals or approvals from Client Agency’s Serving Utility (including the Interconnection Agreement), Client Agency shall have the right to terminate this Site Specific PPA by providing written notice to Seller at any time prior to the date upon which Commercial Operation is achieved.

Appears in 2 contracts

Samples: Master Power Purchase Agreement, Master Power Purchase Agreement

AutoNDA by SimpleDocs

Construction Completion Deadline. If Commercial Operation of the SEF does not occur on or before [ [____] (the “Guaranteed Commercial Operation Date”), subject to extension due to delays arising out of any Force Maujer Majeur events, any Buyer Acts, any Governmental Approvals or approvals from Client Agency’s Serving Utility (including the Interconnection Agreement), Client Agency shall have the right to terminate this Site Specific PPA by providing written notice to Seller at any time prior to the date upon which Commercial Operation is achieved.

Appears in 2 contracts

Samples: Master Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs