CONSTRUCTION MOBILIZATION Clause Samples
The Construction Mobilization clause outlines the requirements and procedures for the contractor to begin work on a construction project. It typically specifies the conditions under which mobilization can start, such as receipt of a notice to proceed, and may detail the types of preparatory activities allowed, like moving equipment to the site or setting up temporary facilities. This clause ensures that both parties understand when and how the project will physically commence, helping to coordinate schedules and allocate initial responsibilities.
POPULAR SAMPLE Copied 1 times
CONSTRUCTION MOBILIZATION. The CMR’s mobilization to perform the Contract Work shall commence at the issuance of a written Notice to Proceed and shall be completed within thirty (30) days of the date of the Notice to Proceed. At a minimum, the construction mobilization phase shall include the following:
A. Submission of an acceptable detailed Schedule of Values immediately after Notice to Proceed and prior to the submission of the first request for payment, as required by Part 11.2 of these General Conditions;
B. Submission of an acceptable Startup Construction Schedule within seven (7) days of Notice to Proceed as required by Section 01 3200 of the Specifications.
C. Submission of a proposed List of Sub-contractors within ten (10) days of Notice to Proceed as required by Part 6 of these General Conditions;
D. Submission of an acceptable CMR Quality Control Plan within ten (10) days of Notice to Proceed as required by Section 01 4000 of the Specifications;
E. Submission of an acceptable Project Schedule as required by Section 01 3200 of the Specifications;
F. Submission of an acceptable Submittal Schedule as required by Submittals, Section 01 3300 of the Specifications;
G. Submission of an acceptable Erosion and Sedimentation Control Plan as required by Section 01 5000 of the Specifications;
H. Completed installation of required Phase 1 Erosion & Sediment Controls, perimeter construction fence and CMR and Owner’s Representative’s onsite construction trailers, as required by the Contract Documents; I. Submission of an acceptable Waste Management Plan as required by Section 01 7419 of the Specifications.
CONSTRUCTION MOBILIZATION. The Contractor’s mobilization to perform the Work shall commence at the issuance of a written Notice to Proceed and shall be completed within thirty (30) days of the date of the Notice to Proceed. At a minimum, the construction mobilization phase shall include the following:
1. Submission of an acceptable detailed Schedule of Values in compliance with the requirements of General Conditions Part 11 PAYMENTS AND COMPLETION Paragraph 11.2 within ten (10) Days of the date of the Notice to Proceed;
2. Submission of Contractor Certification of Criminal Conviction form, due within ten (10) days of Notice to Proceed;
3. Submission of an acceptable Startup Construction Schedule within seven (7) Days of the date of the Notice to Proceed.
4. Submission of a proposed List of Sub-contractors within ten (10) days of Notice to Proceed as required by General Conditions Part 6 SUBCONTRACTORS Paragraph 6.2
5. Submission of an acceptable Waste Management Plan.
6. Satisfaction of all of the foregoing requirements construction mobilization requirements is a condition precedent to any obligation of Owner to accept, consider or act upon any request by Contractor for payment, or to make any payment of any kind to Contractor.
CONSTRUCTION MOBILIZATION. If Authority issues an NTP other than NTP 1 and there is no other Segment in the Construction Period prior to Final Acceptance, Contractor shall be entitled to an additional mobilization payment as set forth below. [to be provided]
CONSTRUCTION MOBILIZATION. The CMR’s mobilization to perform the Contract Work shall commence at the issuance of a written Notice to Proceed and shall be completed within thirty (30) days of the date of the Notice to Proceed. At a minimum, the construction mobilization phase shall include the following:
A. Submission of an acceptable detailed Schedule of Values immediately after Notice to Proceed and prior to the submission of the first request for payment, as required by Part 11.2 of these General Conditions;
B. Submission of an acceptable Startup Construction Schedule within seven (7) days of Notice to Proceed as required by Section 01 3200 of the Specifications.