Construction Progress Update. Each monthly update shall contain a narrative description of the Project progress and a critical path method schedule in Primavera format, including any plans to correct defective or deficient work or for time lost due to delays.
Appears in 20 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management at Risk Services Agreement
Construction Progress Update. Each monthly update shall contain contain, but not limited to, a baseline schedule and schedule updates with a narrative description of the Project project progress and a demonstrating the critical path method schedule of the Project in the latest version of Primavera format, including any plans to correct defective or deficient work or for time lost due to delays.
Appears in 7 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement