Common use of Contract Penalty Clause in Contracts

Contract Penalty. The CONSULTANT shall pay to the CITY the amount of $ 100.00 Dollars per calendar day for unexcused delay in completion of the project past the date of completion.

Appears in 14 contracts

Samples: General Professional Services Agreement, General Professional Services Agreement, General Professional Services Agreement

AutoNDA by SimpleDocs

Contract Penalty. The CONSULTANT CONTRACTOR shall pay to the CITY the amount of $ $_100.00 Dollars per calendar day for unexcused delay in completion of the project past the date of completion.

Appears in 4 contracts

Samples: Parks and Recreation Department General Construction Agreement, Parks and Recreation Department General Construction Agreement, Parks and Recreation Department General Construction Agreement

Contract Penalty. The CONSULTANT CONTRACTOR shall pay to the CITY the amount of $ $100.00 Dollars per calendar day for unexcused delay in completion of the project past the date of completion.

Appears in 3 contracts

Samples: Deployment Professional Service Agreement, Deployment Professional Service Agreement, Deployment Professional Service Agreement

Contract Penalty. The CONSULTANT shall pay to the CITY the amount of $ $100.00 Dollars per calendar day for unexcused delay in completion of the project past the date of completion.

Appears in 3 contracts

Samples: General Professional Services Agreement, General Professional Services Agreement, General Professional Services Agreement

Contract Penalty. The CONSULTANT shall pay to the CITY the amount of $ 100.00 Dollars per calendar day for unexcused delay in completion of the project past the date of completion. CONSULTANT shall be excused for any delays which are out of their control.

Appears in 1 contract

Samples: General Professional Services Agreement

Contract Penalty. The CONSULTANT CONTRACTOR shall pay to the CITY the amount of $ 100.00 Dollars per calendar day for unexcused delay in completion of the project past the date of completion.

Appears in 1 contract

Samples: General Construction Agreement

Contract Penalty. The CONSULTANT CONTRACTOR shall pay to the CITY the amount of $ 100.00 $250.00 Dollars per calendar day for unexcused delay in completion of the project past the date of completion.

Appears in 1 contract

Samples: Cupola Repairs General Construction Agreement

AutoNDA by SimpleDocs

Contract Penalty. The CONSULTANT CONTRACTOR shall pay to the CITY the amount of $ 100.00 100 Dollars per calendar day for unexcused delay in completion of the project past the date of completion.

Appears in 1 contract

Samples: General Construction Agreement

Contract Penalty. The CONSULTANT shall pay to the CITY the amount of $ 100.00 0.00 Dollars per calendar day for unexcused delay in completion of the project past the date of completion.

Appears in 1 contract

Samples: General Professional Services Agreement

Contract Penalty. The CONSULTANT shall pay to the CITY the amount of $ $_100.00 Dollars per calendar day for unexcused delay in completion of the project past the date of completion.

Appears in 1 contract

Samples: General Professional Services Agreement