Contractor Response to Changes and Change Requests. Contractor must respond in writing within 10 days of receiving a Change Request, advising the Department of any cost and Schedule impacts. When there is a cost impact, i.e., increase or decrease in Charges, Contractor must advise the Department in writing of the increase or decrease involved, including a breakdown of the number of Staff hours by level of Contractor and the Department personnel needed to effect this change.
Appears in 5 contracts
Contractor Response to Changes and Change Requests. Contractor must respond in writing within 10 days of receiving a Change Request, advising the Department of any cost and Schedule impacts. When there is a cost impact, i.e., increase or decrease in Charges, Contractor must advise the Department in writing of the increase or decrease involved, including a breakdown of the number of Staff hours by level level, of Contractor and the Department personnel personnel, needed to effect this change.