Contractor Submission of Change Request. Contractor may also submit a Change Request to the Department to propose changes that should be made within the scope of this Contract. Any such Change Request must include a price summary and Schedule impacts. The Department will attempt to respond to such Change Requests from Contractor within 20 days of receipt. If the parties reach an agreement on a Change Order in writing, and the Change Order is executed by authorized representatives of the Parties, the terms of this Contract will be modified accordingly through an amendment as provided for in Section 24.21. If the parties are unable to reach an agreement in writing on a Change Request submitted by Contractor, the Department’s Project Manager will be deemed to have rejected the requested Change Request. Upon rejection by the Department of a Contractor request for a change order, Contractor is obligated to continue performance in accordance with this Contract.