Common use of Contractor’s Delivery of Estimate Clause in Contracts

Contractor’s Delivery of Estimate. As soon as practicable and in any event not more than 15 Business Days after receipt of a Change Order Enquiry, or such longer period as the parties, acting reasonably, mutually agree, the Contractor shall deliver to the Province an Estimate prepared in accordance with and meeting the requirements of Section 3.3.

Appears in 3 contracts

Samples: Change Orders, Change Order Agreement, Change Orders

AutoNDA by SimpleDocs

Contractor’s Delivery of Estimate. As soon as practicable and in any event not more than 15 Business Days after receipt of a Change Order Enquiry, or such longer period as the parties, parties acting reasonably, reasonably mutually agree, the Contractor shall deliver to the Province an Estimate prepared in accordance with and meeting the requirements of Section 3.3.

Appears in 1 contract

Samples: Change Order Agreement

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!