Contractor’s Design Development Stage Submission Sample Clauses
The Contractor’s Design Development Stage Submission clause requires the contractor to provide detailed design documents and plans for review and approval at a specific stage of the project. This typically includes drawings, specifications, and calculations that demonstrate how the contractor intends to meet the project’s design requirements. By mandating this submission, the clause ensures that the client or project manager can verify the design’s compliance with contractual and regulatory standards before construction proceeds, thereby reducing the risk of costly errors or rework later in the project.
Contractor’s Design Development Stage Submission. 4.5.1 At the completion of the activities described under Section 4.4 and based on the provisional Design Development Documents, the Contractor will submit its Design Development Stage Submission.
4.5.2 If all of the Work is not subject to an executed GMP Amendment at the time of the Contractor’s Design Development Stage Submission, the Contractor will include in its Design Development Stage Submission the Contractor’s estimate of Construction Costs (“Contractor’s Design Development Estimate”).
4.5.2.1 If the Contractor’s Design Development Estimate exceeds the Construction Budget or varies from the A/E’s Design Development Estimate by more than 5 percent of that estimate, the Contracting Authority may require the A/E to immediately work with the Contractor to develop viable proposals to reconcile the estimates with each other and the Construction Budget. The Contractor will present those proposals as an addendum to its Design Development Stage Submission.
4.5.3 If a GMP Amendment has been entered into at the time of the Contractor’s Design Development Stage Submission, the Contractor shall include with the Contractor’s Design Development Stage Submission a detailed description of any change in the scope of the Work described in the provisional Design Development Documents as compared to the scope of the Work described in the GMP Documents and an estimate of the cost and time impact of each change.
Contractor’s Design Development Stage Submission. 4.6.1 At the completion of the activities described under Section 4.4.3 and based on the provisional Design Development Documents, the Contractor will submit its Design Development Stage Submission.
4.6.2 If all of the Work is not subject to an executed GMP Amendment at the time of the Contractor’s Design Development Stage Submission, the Contractor will include in its Design Development Stage Submission the Contractor’s estimate of Construction Costs (“Contractor’s Design Development Estimate”).
4.6.2.1 If the Contractor’s Design Development Estimate exceeds the Construction Budget or varies from the A/E’s Design Development Estimate by more than 5 percent of that estimate, the Contracting Authority may require the A/E to immediately work with the Contractor to develop viable proposals to reconcile the estimates with each other and the Construction Budget. The Contractor will present those proposals as an addendum to its Design Development Stage Submission.