Costs and Schedule Relief for Contractor-Caused Suspension. Notwithstanding anything to the contrary, Contractor shall bear its own costs incurred due to a suspension by Owner pursuant to Section 19.2 and Section 19.3 where such suspension is necessitated by a breach of this Agreement by Contractor due to any act or omission by any Contractor Party or Subcontractor and shall not be entitled to a change to the Construction Schedule or an extension of time to the Guaranteed Block Substantial Completion Dates, Guaranteed Facility Substantial Completion Date or Guaranteed Final Completion Date.
Appears in 4 contracts
Samples: Procurement and Construction Agreement (Sunpower Corp), Procurement and Construction Agreement (Sunpower Corp), Engineering, Procurement and Construction Agreement (Sunpower Corp)
Costs and Schedule Relief for Contractor-Caused Suspension. Notwithstanding anything to the contrary, Contractor shall bear its own costs and delays incurred due to a suspension by Owner pursuant to Section 19.2 and Section 19.3 19.1 where such suspension is necessitated by due to a breach of this Agreement by Contractor due to Contractor, any act or omission by any Contractor Party or Subcontractor Subcontractor, an Emergency or as otherwise required by Applicable Law, and Contractor shall not be entitled to a change to the Construction Schedule or an extension of time to the Guaranteed Block Substantial Completion Dates, Guaranteed Facility Substantial Completion Date or Guaranteed Final Completion DateDates in any of such cases.
Appears in 1 contract
Costs and Schedule Relief for Contractor-Caused Suspension. Notwithstanding anything to the contrary, Contractor shall bear its own costs and delays incurred due to a suspension by Owner pursuant to Section 19.2 and Section 19.3 11.1 where such suspension is necessitated by due to a breach of this Agreement by Contractor due to Contractor, any act or omission by any Contractor Party or Subcontractor Subcontractor, an Emergency or as otherwise required by Applicable Law, and Contractor shall not be entitled to a change to the Construction Schedule or an extension of time to the Guaranteed Block Substantial Completion Dates, Guaranteed Facility Substantial Completion Date or Guaranteed Final Completion Date.Dates in any of such cases. HAZARDOUS MATERIALS
Appears in 1 contract
Samples: Engineering, Procurement and Construction Agreement