Covered Or Concealed Work. If a portion of the Work has been covered, the Contractor shall, if notified to do so by the Owner’s Project Representative or a Professional, uncover the designated portion for observation and then replace it. 8.2.1 If the designated portion of the Work was covered contrary to the request of the Owner’s Project Representative or the Professional, or to requirements specifically expressed in the Construction Documents, the Contractor shall receive no additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule. 8.2.2 If the designated portion of the Work was covered prior to a specific request by the Owner’s Project Representative or the Professional that it remain uncovered, the Contractor shall receive additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule(s) only if the designated portion of the Work was in conformance with the Construction Documents.
Appears in 2 contracts
Samples: Construction Agreement, Construction Agreement
Covered Or Concealed Work. If a portion of the Work has been covered, the General Contractor shall, if notified to do so by the Owner’s Project Representative or a Design Professional, uncover the designated portion for observation and then replace it.
8.2.1 If the designated portion of the Work was covered contrary to the request of the Owner’s Project Representative or the Design Professional, or to requirements specifically expressed in the Construction Documents, the General Contractor shall receive no additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule.
8.2.2 If the designated portion of the Work was covered prior to a specific request by the Owner’s Project Representative or the Design Professional that it remain uncovered, the General Contractor shall receive additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule(s) only if the designated portion of the Work was in conformance with the Construction Documents.
Appears in 1 contract
Samples: Construction Agreement
Covered Or Concealed Work. If a portion of the Work has been covered, the General Contractor shall, if notified to do so by the Owner’s Project Representative or a Professional, uncover the designated portion for observation and then replace it.
8.2.1 If the designated portion of the Work was covered contrary to the request of the Owner’s Project Representative or the Professional, or to requirements specifically expressed in the Construction Documents, the General Contractor shall receive no additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule.
8.2.2 If the designated portion of the Work was covered prior to a specific request by the Owner’s Project Representative or the Professional that it remain uncovered, the General Contractor shall receive additional compensation for the costs of uncovering and replacement or modification of the Construction Schedule(s) only if the designated portion of the Work was in conformance with the Construction Documents.
Appears in 1 contract
Samples: Construction Agreement