Critical Path Schedule Updates. If there is any change in the Schedule covered by a Change Order, or based on a Change Order notice, Contractor shall provide Company with an updated version of Contractor’s Exhibit B Schedule showing the critical path schedule reflecting the change attributable to the Change Order or event(s) giving rise to the request for adjustment.
Appears in 2 contracts
Sources: Construction Contract (Us Geothermal Inc), Construction Contract (Us Geothermal Inc)
Critical Path Schedule Updates. If there is any change in the Schedule covered by a Change Order, or based on a Change Order notice, Contractor shall provide Company with an updated version of Contractor’s Exhibit B Schedule showing the critical path schedule reflecting the change attributable to the Change Order or event(s) giving rise to the request for adjustment.
Appears in 2 contracts
Sources: Engineering, Procurement and Construction Contract (Us Geothermal Inc), Engineering, Procurement and Construction Contract (Us Geothermal Inc)
Critical Path Schedule Updates. If there is any change in the Schedule covered by a Change Order, or based on a Change Order notice, Contractor shall provide Company Owner with an updated version of Contractor’s Exhibit B Schedule showing the critical path schedule reflecting the change attributable to the Change Order or event(s) giving rise to the request for adjustment.
Appears in 2 contracts
Sources: Engineering, Procurement and Construction Contract, Engineering, Procurement and Construction Contract (Clean Coal Technologies Inc.)