Customization Reports. For each Contract Order under this Agreement, Supplier must provide Sprint weekly a written report that includes, without limitation, (i) an updated schedule of work for each Specification, (ii) identification of all problems identified that may impact schedule, functionality or performance, (iii) proposed recovery method to meet schedule, functionality or performance requirements, (iv) a schedule of Acceptance Tests to be performed, and (v) the amount of development hours actually spent for a Specification and the hours required for completion. Supplier must separately and immediately report in writing any material errors discovered in the Supplier Services and any circumstances that may lead to a delay in the Development Milestones or affect functionality or performance of the System.