Cutover / Completion of Project. 6.6.1. SCE will own, operate, and maintain all of the “To-the-Meter” electric distribution and service systems within the MHP. Upon completion of the conversion, the facilities will be managed under and subject to Rule 15, Rule 16, and other utility tariffs. 6.6.2. Existing MHP residents within the MHP will be converted to direct SCE service and will be served under existing SCE’s tariffs. At the time of the initial service cut-over, fees associated with new customer credit checks and service deposits will be waived. However, as with other residential customers, MHP residents will still be subject to discontinuance of service provisions per the Utilities’ Discontinuance and Restoration of Service Rule (Rule 11). After the service cutover is completed and MHP residents have established their SCE accounts, all new MHP residents will be subject to all existing credit requirements and deposits applicable to all SCE residential customers. 6.6.3. Existing MHP residents who participate in the CARE and/or the Family Electric Rate Assistance (FERA) programs through the MHP master-metered/submetered distribution system and become a customer of SCE through the MHP Program will be deemed grandfathered into the respective program without having to re-certify or reapply as long as the name of the customer for the new service account matches the name of the CARE/FERA participant. This will be a one-time exception to the respective CARE/FERA Rules at the time of the service conversion. 6.6.4. Existing MHP residents who receive medical baseline allowances through the MHP master-metered/submetered distribution system and become a customer of SCE through the MHP Program will be deemed grandfathered and will continue to receive the same medical baseline allowances without having to re-certify or reapply as long as the participant who is receiving the medical baseline allowance still lives at the residence. This will be a one-time exception to the Medical Baseline Rules at the time of the service conversion. 6.6.5.
Appears in 1 contract
Cutover / Completion of Project. 6.6.1. SCE SOCALGAS will own, operate, and maintain all of the “To-the-Meter” electric distribution and service systems within the MHP. Upon completion of the conversion, the facilities will be managed under and subject to Rule 15, No. 20 and Rule 16, No. 21 and other utility Utility tariffs.
6.6.2. Existing MHP residents within the MHP will be converted to direct SCE SOCALGAS service and will be served under existing SCE’s SOCALGAS’ tariffs. At the time of the initial service cut-over, fees associated with new customer credit checks and service deposits will be waived. However, as with other residential customers, MHP residents will still be subject to discontinuance of service provisions per the Utilities’ Discontinuance and Restoration of Service Rule (Rule 11No. 44). After the service cutover is completed and MHP residents have established their SCE SOCALGAS accounts, all new MHP residents will be subject to all existing credit requirements and deposits applicable to all SCE SOCALGAS residential customers.
6.6.3. Existing MHP residents who participate in the CARE and/or the Family Electric Rate Assistance (FERA) programs through the MHP master-metered/submetered metered distribution system and become a customer of SCE SOCALGAS through the MHP Program will be deemed grandfathered into the respective program without having to re-certify or reapply as long as the name of the customer for the new service account matches the name of the CARE/FERA participant. This will be a one-time exception to the respective CARE/FERA Rules at the time of the service conversion.
6.6.4. Existing MHP residents who receive medical baseline allowances through the MHP master-metered/submetered metered distribution system and become a customer of SCE SOCALGAS through the MHP Program will be deemed grandfathered and will continue to receive the same medical baseline allowances without having to re-certify or reapply as long as the participant who is receiving the medical baseline allowance still lives at the residence. This will be a one-time exception to the Medical Baseline Rules at the time of the service conversion.
6.6.5. 6.6.5SOCALGAS or its Contractor shall purge the gas Legacy System of unpressurized gas to ensure safety of the disconnected system.
Appears in 1 contract
Samples: Mobilehome Park Utility Conversion Program Agreement
Cutover / Completion of Project. 6.6.1. SCE will own, operate, and maintain all of the “To-the-Meter” electric distribution and service systems within the MHP. Upon completion of the conversion, the facilities will be managed under and subject to Rule 15, Rule 16, and other utility tariffs.
6.6.2. Existing MHP residents within the MHP will be converted to direct SCE service and will be served under existing SCE’s tariffs. At the time of the initial service cut-over, fees associated with new customer credit checks and service deposits will be waived. However, as with other residential customers, MHP residents will still be subject to discontinuance of service provisions per the Utilities’ Discontinuance and Restoration of Service Rule (Rule 11). After the service cutover is completed and MHP residents have established their SCE accounts, all new MHP residents will be subject to all existing credit requirements and deposits applicable to all SCE residential customers.
6.6.3. Existing MHP residents who participate in the CARE and/or the Family Electric Rate Assistance (FERA) programs through the MHP master-metered/submetered distribution system and become a customer of SCE through the MHP Program will be deemed grandfathered into the respective program without having to re-certify or reapply as long as the name of the customer for the new service account matches the name of the CARE/FERA participant. This will be a one-time exception to the respective CARE/FERA Rules at the time of the service conversion.
6.6.4. Existing MHP residents who receive medical baseline allowances through the MHP master-metered/submetered distribution system and become a customer of SCE through the MHP Program will be deemed grandfathered and will continue to receive the same medical baseline allowances without having to re-certify or reapply as long as the participant who is receiving the medical baseline allowance still lives at the residence. This will be a one-time exception to the Medical Baseline Rules at the time of the service conversion. 6.6.5.
Appears in 1 contract
Cutover / Completion of Project. 6.6.1. SCE SOCALGAS will own, operate, and maintain all of the “To-the-Meter” electric gas distribution and service systems within the MHP. Upon completion of the conversion, the facilities will be managed under and subject to Rule 15, No. 20 and Rule 16, No. 21 and other utility Utility tariffs.
6.6.2. Existing MHP residents within the MHP will be converted to direct SCE SOCALGAS service and will be served under existing SCE’s SOCALGAS’ tariffs. At the time of the initial service cut-over, fees associated with new customer credit checks and service deposits will be waived. However, as with other residential customers, MHP residents will still be subject to discontinuance of service provisions per the Utilities’ Discontinuance and Restoration of Service Rule (Rule 11No. 44). After the service cutover is completed and MHP residents have established their SCE SOCALGAS accounts, all new MHP residents will be subject to all existing credit requirements and deposits applicable to all SCE SOCALGAS residential customers.
6.6.3. Existing MHP residents who participate in the CARE and/or the Family Electric Rate Assistance (FERA) programs through the MHP master-metered/submetered metered distribution system and become a customer of SCE SOCALGAS through the MHP Program will be deemed grandfathered into the respective program without having to re-certify or reapply as long as the name of the customer for the new service account matches the name of the CARE/FERA participant. This will be a one-time exception to the respective CARE/FERA Rules at the time of the service conversion.
6.6.4. Existing MHP residents who receive medical baseline allowances through the MHP master-metered/submetered metered distribution system and become a customer of SCE SOCALGAS through the MHP Program will be deemed grandfathered and will continue to receive the same medical baseline allowances without having to re-certify or reapply as long as the participant who is receiving the medical baseline allowance still lives at the residence. This will be a one-time exception to the Medical Baseline Rules at the time of the service conversion.
6.6.5. 6.6.5SOCALGAS or its Contractor shall purge the gas Legacy System of unpressurized gas to ensure safety of the disconnected system.
Appears in 1 contract
Samples: Mobilehome Park Utility Conversion Program Agreement
Cutover / Completion of Project. 6.6.1. SCE Liberty Utilities will own, operate, and maintain all of the “To-the-Meter” electric distribution and service systems within the MHP. Upon completion of the conversion, the facilities will be managed under and subject to Rule 15, 15 and Rule 16, 16 and other utility applicable tariffs.
6.6.2. If necessary, Liberty Utilities will coordinate with the Contractor to jointly meet to perform joint cutover with Liberty Utilities for the individual services within the MHP.
6.6.3. Liberty Utilities will reimburse the MHP Owner/Operator for all qualifying “Beyond- the-Meter” work as summarized in Attachment C.
6.6.4. Existing MHP residents within the MHP will be converted to direct SCE Liberty Utilities’ service and will be served under existing SCE’s Liberty Utilities’ tariffs. At the time of the initial service cut-over, fees associated with new customer credit checks and service deposits will be waived. However, as with other residential customers, MHP residents will still be subject to discontinuance of service provisions per the Liberty Utilities’ Discontinuance and Restoration of Service Rule (Rule No. 11). After the service cutover is completed and MHP residents have established their SCE Liberty Utilities’ accounts, all new MHP residents will be subject to all existing credit requirements and deposits applicable to all SCE Liberty Utilities’ residential customers.
6.6.36.6.5. Existing MHP residents who participate in the CARE and/or the Family Electric Rate Assistance (FERA) programs through the MHP master-metered/submetered distribution system and become a customer of SCE Liberty Utilities through the MHP Program will be deemed grandfathered into the respective program without having to re-certify recertify or reapply as long as the name of the customer for the new service account matches the name of the CARE/FERA participant. This will be a one-time exception to the respective CARE/FERA Rules at the time of the service conversion.
6.6.46.6.6. Existing MHP residents who receive medical baseline allowances through the MHP master-metered/submetered distribution system and become a customer of SCE Liberty Utilities through the MHP Program will be deemed grandfathered and will continue to receive the same medical baseline allowances without having to re-certify recertify or reapply as long as the participant who is receiving the medical baseline allowance still lives at the residence. This will be a one-time exception to the Medical Baseline Rules at the time of the service conversion.
6.6.7. 6.6.5Liberty Utilities or its contractor shall de-energize and disconnect the Legacy System once cutover is completed to ensure safety of the disconnected system.
Appears in 1 contract
Cutover / Completion of Project. 6.6.1. SCE [Utility] will own, operate, and maintain all of the “To-the-Meter” electric distribution and service systems within the MHP. Upon completion of the conversion, the facilities will be managed under and subject to Rule 15, Rule 16, and other [utility tariffstariff rules].
6.6.2. Existing MHP residents within the MHP will be converted to direct SCE [Utility] service and will be served under existing SCE[Utility]’s tariffs. At the time of the initial service cut-cut- over, fees associated with new customer credit checks and service deposits will be waived. However, as with other residential customers, MHP residents will still be subject to discontinuance of service provisions per the Utilities’ Discontinuance and Restoration of Service Rule (Rule 11[utility tariff rules]). After the service cutover is completed and MHP residents have established their SCE [Utility] accounts, all new MHP residents will be subject to all existing credit requirements and deposits applicable to all SCE [Utility] residential customers.
6.6.3. Existing MHP residents who participate in the CARE and/or the Family Electric Rate Assistance (FERA) programs through the MHP master-metered/submetered metered distribution system and become a customer of SCE [Utility] through the MHP Program will be deemed grandfathered into the respective program without having to re-certify or reapply as long as the name of the customer for the new service account matches the name of the CARE/FERA participant. This will be a one-time exception to the respective CARE/FERA Rules at the time of the service conversion.
6.6.4. Existing MHP residents who receive medical baseline allowances through the MHP master-metered/submetered metered distribution system and become a customer of SCE [Utility] through the MHP Program will be deemed grandfathered and will continue to receive the same medical baseline allowances without having to re-certify or reapply as long as the participant who is receiving the medical baseline allowance still lives at the residence. This will be a one-time exception to the Medical Baseline Rules at the time of the service conversion.
6.6.5. 6.6.5[Utility] or its Contractor shall purge the gas Legacy System of unpressurized gas to ensure safety of the disconnected system.
Appears in 1 contract
Samples: Mobilehome Park Utility Conversion Program Agreement