Damage to the works. The contractor shall, from the commencement date of the works until the date of the certificate of practical completion, bear the full risk of and hereby indemnifies and hold harmless the employer against any damage to and/or destruction of the works consequent upon a catastrophic ground movement as mentioned above. The contractor shall take such precautions and security measures and other steps for the protection of the works as he may deem necessary. When so instructed to do so by the principal agent, the contractor shall proceed immediately to remove and/or dispose of any debris arising from damage to or destruction of the works and to rebuild, replace and/or repair the works, at the contractor’s own costs. 10.
Appears in 17 contracts
Samples: Bid Agreement, Tender Agreement, Tender Agreement
Damage to the works. The contractor shall, from the commencement date of the works until the date of the certificate of practical completion, bear the full risk of and hereby indemnifies and hold harmless the employer against any damage to and/or destruction of the works consequent upon a catastrophic ground movement as mentioned above. The contractor shall take such precautions and security measures and other steps for the protection of the works as he may deem necessary. When so instructed to do so by the principal agent, the contractor shall proceed immediately to remove and/or dispose of any debris arising from damage to or destruction of the works and to rebuild, replace and/or repair the works, at the contractor’s own costs. 10.
Appears in 10 contracts
Samples: Bid Agreement, Bid Agreement, Bid Agreement
Damage to the works. The contractor shall, from the commencement date of possession of the works site until the date of the certificate of practical completion, bear the full risk of and hereby indemnifies and hold holds harmless the employer against any damage to and/or destruction of the works consequent upon a catastrophic ground movement as mentioned above. The contractor shall take such precautions and security measures and other steps for the protection of the works as he may deem necessary. necessary When so instructed to do so by the principal agent, the contractor shall proceed immediately to remove and/or dispose of any debris arising from damage to or destruction of the works and to rebuild, restore, replace and/or repair the works, at the contractor’s own costs. 10.
Appears in 7 contracts
Samples: Term Contract for General Building Maintenance and Repairs, Tender Agreement, Contract for Minor Building Repairs
Damage to the works. The contractor shall, from the commencement date of the works until the date of the certificate of practical completion, completion bear the full risk of and hereby indemnifies and hold holds harmless the employer against any damage to and/or destruction of the works consequent upon a catastrophic ground movement as mentioned above. The contractor shall take such precautions and security measures and other steps for the protection of the works as he may deem necessary. necessary When so instructed to do so by the principal agent, the contractor shall proceed immediately to remove and/or dispose of any debris arising from damage to or destruction of the works and to rebuild, restore, replace and/or repair the works, at the contractor’s 's own costs. 10.
Appears in 7 contracts
Samples: Contract, Principal Building Agreement, Principal Building Agreement
Damage to the works. The contractor shall, from the commencement date of the works until the date of the certificate of practical completion, completion bear the full risk of and hereby indemnifies and hold holds harmless the employer against any damage to and/or destruction of the works consequent upon a catastrophic ground movement as mentioned above. The contractor shall take such precautions and security measures and other steps for the protection of the works as he may deem necessary. necessary When so instructed to do so by the principal agent, the contractor shall proceed immediately to remove and/or dispose of any debris arising from damage to or destruction of the works and to rebuild, restore, replace and/or repair the works, at the contractor’s own costs. 10.
Appears in 6 contracts
Samples: Principal Building Agreement, Principal Building Agreement, Principal Building Agreement
Damage to the works. The contractor shall, from the commencement date of the works until the date of the certificate of practical completion, completion bear the full risk of and hereby indemnifies and hold holds harmless the employer against any damage to and/or destruction of the works consequent upon a catastrophic ground movement as mentioned above. The contractor shall take such precautions and security measures and other steps for the protection of the works as he may deem necessary. necessary When so instructed to do so by the principal agent, the contractor shall proceed immediately to remove and/or dispose of any debris arising from damage to or destruction of the works and to rebuild, restore, replace and/or repair the works, at the contractor’s own costs. 10.
Appears in 1 contract
Samples: Bill of Quantities