Dangerous Materials. When the use or storage of explosives or other dangerous materials or equipment or unusual methods are necessary for the Work, Contractor shall exercise utmost care and carry on its activities only under the supervision of properly qualified personnel. Contractor shall notify Owner's Project Director prior to bringing any explosives onto the Site.
Appears in 4 contracts
Samples: Procurement and Construction Agreement (South Carolina Electric & Gas Co), Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement
Dangerous Materials. When the use or storage of explosives or other dangerous materials or equipment or unusual methods are necessary for the Work, Contractor shall exercise utmost appropriate care and carry on carryon its activities only under the supervision of properly qualified personnel. Contractor shall notify Owner's ’s Project Director prior to bringing any explosives onto the Site.
Appears in 3 contracts
Samples: Engineering, Procurement and Construction Agreement (Duke Energy CORP), Engineering, Procurement and Construction Agreement (Duke Energy Carolinas, LLC), Engineering, Procurement and Construction Agreement (Duke Energy CORP)
Dangerous Materials. When the use or storage of explosives or other dangerous materials or equipment or unusual methods are necessary for execution of the Work, the Contractor shall exercise utmost care and carry on its such activities only under the supervision of properly qualified personnel. Contractor shall notify Owner's Project Director prior to bringing any explosives onto the Site.2.10.2.4
Appears in 2 contracts
Samples: Design Build Agreement (Isle of Capri Black Hawk Capital Corp), Design Build Agreement (Isle of Capri Black Hawk Capital Corp)
Dangerous Materials. When the use or storage of explosives or other dangerous materials or equipment or unusual methods are necessary for the Work, Contractor shall exercise utmost care and carry on its activities only under the supervision of properly qualified personnel. Contractor shall notify Owner's ’s Project Director prior to bringing any explosives onto the Site.
Appears in 1 contract
Samples: Engineering, Procurement and Construction Agreement (Scana Corp)
Dangerous Materials. When the use or storage of explosives or other dangerous materials or equipment or unusual methods are necessary for the execution of the Work, Contractor shall exercise utmost care and carry on its activities only under the supervision of properly qualified personnel. Contractor shall notify Owner's Project Director prior to bringing any explosives onto the Site.
Appears in 1 contract
Samples: And Construction Agreement (Sierra Pacific Resources /Nv/)
Dangerous Materials. When the use or storage of -------------------- explosives or other dangerous materials or equipment or unusual methods are necessary for execution of the Work, the Contractor shall exercise utmost care and carry on its such activities only under the supervision of properly qualified personnel. Contractor shall notify Owner's Project Director prior to bringing any explosives onto the Site.
Appears in 1 contract
Samples: Design Build Agreement (Isle of Capri Black Hawk Capital Corp)
Dangerous Materials. When the use or storage of explosives or other dangerous materials or equipment or unusual methods are necessary for execution of the Work, Contractor shall exercise utmost care and carry on its such activities only under the supervision of properly qualified personnel. Contractor Explosives shall notify Owner's Project Director not be used on the Job Site or the Big Stone Site, without the prior to bringing any explosives onto the Sitewritten consent of Owners.
Appears in 1 contract
Samples: General Work Construction Agreement (Otter Tail Corp)
Dangerous Materials. When the use or storage of explosives or other dangerous materials or equipment or unusual methods are necessary for the Work, Contractor shall exercise utmost care and carry on its activities only under the supervision of properly qualified personnel. Contractor shall notify Owner's ’s Project Director prior to bringing any explosives onto the SiteSite or Nearby Work Areas.
Appears in 1 contract
Dangerous Materials. When the use or storage of explosives explosives, ------------------- radioactive or other dangerous materials or equipment or unusual methods are necessary for the prosecution of the Work, Contractor shall exercise the utmost care and carry on its such activities only under the supervision of its properly qualified personnel. Contractor shall notify Owner's Project Director prior to bringing any explosives onto the Site.
Appears in 1 contract