Decommissioning The expenditure for Decommissioning will be estimated on the basis of technical studies undertaken by the Contractor, to be agreed by the National Petroleum Agency, as part of each Field Development Program and revised as necessary.
Remediation The Charter School shall provide remediation in required cases pursuant to State Board of Education Rule 160-4-5-.01 and No Child Left Behind, subject to any amendment, waiver or reauthorization thereof
Environmental Remediation Failure to remediate (or pursue the remediation process with due diligence and good faith) within the time period required by law or governmental order, (or within a reasonable time in light of the nature of the problem if no specific time period is so established), environmental problems in violation of Applicable Law related to Properties of the Borrower and/or its Subsidiaries where the estimated cost of remediation is in the aggregate in excess of Seventy-Five Million Dollars ($75,000,000), in each case after all administrative hearings and appeals have been concluded.
Hazardous Materials; Remediation (a) If any release or disposal of Hazardous Materials shall occur or shall have occurred on any real property or any other assets of any Borrower or any other Credit Party, such Borrower will cause, or direct the applicable Credit Party to cause, the prompt containment and removal of such Hazardous Materials and the remediation of such real property or other assets as is necessary to comply with all Environmental Laws and to preserve the value of such real property or other assets. Without limiting the generality of the foregoing, each Borrower shall, and shall cause each other Credit Party to, comply with each Environmental Law requiring the performance at any real property by any Borrower or any other Credit Party of activities in response to the release or threatened release of a Hazardous Material.
Environmental, Health and Safety Matters (a) The Company has complied and is in compliance with all Environmental, Health, and Safety Requirements.
Environmental and Safety Matters Except as disclosed in Schedule 4.13:
Commissioning Commissioning tests of the Interconnection Customer's installed equipment shall be performed pursuant to applicable codes and standards. If the Interconnection Customer is not proceeding under Section 2.3.2, the Utility must be given at least ten (10) Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.
Site Lands or areas indicated in the Contract Documents as being furnished by the Owner upon which the Work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by the Owner that are designated for the use of the Contractor. Also referred to as Project Site, Job Site and Premises.
Contamination The presence in, on or under land, air or water of a substance (whether a solid, liquid, gas, odour, heat, sound, vibration or radiation) at a concentration above the concentration at which the substance is normally present in, on or under land, air or water in the same locality, that presents a risk of Environmental Harm, including harm to human health or any other aspect of the Environment, or could otherwise give rise to a risk of non-compliance with any Statutory Requirement for the protection of the Environment.
Environmental, Health and Safety i. Environment, Health and Safety Performance. Seller acknowledges and accepts full and sole responsibility to maintain an environment, health and safety management system ("EMS") appropriate for its business throughout the performance of this Contract. Buyer expects that Seller’s EMS shall promote health and safety, environmental stewardship, and pollution prevention by appropriate source reduction strategies. Seller shall convey the requirement of this clause to its suppliers. Seller shall not deliver goods that contain asbestos mineral fibers.