Delay in Interconnection Sample Clauses

Delay in Interconnection. Purchaser shall cause OUC to complete the OUC Interconnection Facilities and ensure that the Grid is capable of providing and receiving Energy by the date that is eight (8) months prior to the anticipated Commercial Operation Date, but in no event earlier than January 15, 2003. By the date that Seller has completed the collector bus and the 230 kv line to the OUC Interconnection Facilities, but no earlier than the date that is eleven (11) months prior to the anticipated Commercial Operation Date, OUC shall provide service to the Facility for the purposes of engineering and testing the collector bus and other systems by either providing 230 kv service at the 230 kv Interconnection Point or by providing service to the 4160 kv SWGR bus. If for any reason, other than the fault of Seller, OUC fails to complete the OUC Interconnection Facilities and/or if the Grid is not capable of providing and receiving Energy (as determined by OUC and as supported by reasonable documentation) in accordance with the preceding sentence and, as a result, OUC cannot accommodate Seller's start-up and testing of the Facility (such a delay, an "IF/Grid Delay"), then the Scheduled Commencement Date shall be extended by that period of time equal to the IF/Grid Delay; provided, however, that Purchaser shall make the Capacity Payments as provided in Section 5.1.3(b); provided, further, that if Seller would not have been capable of delivering Energy from the Facility to the OUC Interconnection Facilities, even in the absence of an IF/Grid Delay, on the original anticipated Commercial Operating Date ("Seller's Delay"), then extension of the Scheduled Commencement Date and the date on which Purchaser is obligated to make Capacity Payments shall be adjusted by the period of time of Seller's Delay.
AutoNDA by SimpleDocs
Delay in Interconnection. 8.2.1 If for any reason by September 2, 2002: (i) Buyer fails to complete the Interconnection Facilities necessary to interconnect the Unit to the Transmission System; or (ii) the Transmission System is not capable of providing or receiving energy to accommodate Seller's start up and testing activities for the Unit, the Required Commercial Operation Date shall, subject to Section 8.2.2, be changed to a date that is [redacted] after the date such conditions are satisfied. If the Required Commercial Operation Date is so changed, the Monthly Capacity Payments shall commence [redacted] as if such change had not occurred. The receipt of such capacity payments shall be Seller's sole and exclusive remedy for Buyer's failure to complete the Interconnection Facilities by the stated deadline. 8.2.2 The Required Commercial Operation Date shall change pursuant to Section 8.2.1 only to the extent that Seller, despite due diligence, is rendered unable to meet the original Required Commercial Operation Date as a consequence of Buyer's delay in the completion of the Interconnection Facilities.

Related to Delay in Interconnection

  • Interconnection 2.1 This section applies to linking with suppliers providing public telecommunications transport networks or services in order to allow the users of one supplier to communicate with users of another supplier and to access services provided by another supplier, where specific commitments are undertaken.

  • Initiating Interconnection 4.1 If ENT determines to offer Telephone Exchange Services and to interconnect with Verizon in any LATA in which Verizon also offers Telephone Exchange Services and in which the Parties are not already interconnected pursuant to this Agreement, ENT shall provide written notice to Verizon of the need to establish Interconnection in such LATA pursuant to this Agreement. 4.2 The notice provided in Section 4.1 of this Attachment shall include (a) the initial Routing Point(s); (b) the applicable technically feasible Point(s) of Interconnection on Verizon’s network to be established in the relevant LATA in accordance with this Agreement; (c) ENT’s intended Interconnection activation date; (d) a forecast of ENT’s trunking requirements conforming to Section 14.2 of this Attachment; and (e) such other information as Verizon shall reasonably request in order to facilitate Interconnection. 4.3 The interconnection activation date in the new LATA shall be mutually agreed to by the Parties after receipt by Verizon of all necessary information as indicated above. Within ten (10) Business Days of Verizon’s receipt of ENT’s notice provided for in Section 4.1of this Attachment, Verizon and ENT shall confirm the technically feasible Point of Interconnection on Verizon’s network in the new LATA and the mutually agreed upon Interconnection activation date for the new LATA.

  • Two-Way Interconnection Trunks 2.4.1 Where the Parties have agreed to use Two-Way Interconnection Trunks for the exchange of traffic between Verizon and PCS, PCS shall order from Verizon, and Verizon shall provide, the Two-Way Interconnection Trunks and the Entrance Facility, on which such Trunks will ride, and transport and multiplexing, in accordance with the rates, terms and conditions set forth in this Agreement and Verizon’s applicable Tariffs. 2.4.2 Prior to ordering any Two-Way Interconnection Trunks from Verizon, PCS shall meet with Verizon to conduct a joint planning meeting (“Joint Planning Meeting”). At that Joint Planning Meeting, each Party shall provide to the other Party originating Centium Call Second (Hundred Call Second) information, and the Parties shall mutually agree on the appropriate initial number of Two-Way End Office and Tandem Interconnection Trunks and the interface specifications at the Point of Interconnection (POI). Where the Parties have agreed to convert existing One-Way Interconnection Trunks to Two-Way Interconnection Trunks, at the Joint Planning Meeting, the Parties shall also mutually agree on the conversion process and project intervals for conversion of such One-Way Interconnection Trunks to Two-Way Interconnection Trunks. 2.4.3 Two-Way Interconnection Trunks shall be from a Verizon End Office or Tandem to a mutually agreed upon POI. 2.4.4 On a semi-annual basis, PCS shall submit a good faith forecast to Verizon of the number of End Office and Tandem Two-Way Interconnection Trunks that PCS anticipates Verizon will need to provide during the ensuing two (2) year period to carry traffic from PCS to Verizon and from Verizon to PCS. PCS’s trunk forecasts shall conform to the Verizon CLEC trunk forecasting guidelines as in effect at that time. 2.4.5 The Parties shall meet (telephonically or in person) from time to time, as needed, to review data on End Office and Tandem Two-Way Interconnection Trunks to determine the need for new trunk groups and to plan any necessary changes in the number of Two-Way Interconnection Trunks. 2.4.6 Two-Way Interconnection Trunks shall have SS7 Common Channel Signaling. The Parties agree to utilize B8ZS and Extended Super Frame (ESF) DS1 facilities, where available. 2.4.7 With respect to End Office Two-Way Interconnection Trunks, both Parties shall use an economic Centium Call Second (Hundred Call Second) equal to five (5). 2.4.8 Two-Way Interconnection Trunk groups that connect to a Verizon access Tandem shall be engineered using a design blocking objective of Xxxx-Xxxxxxxxx B.005 during the average time consistent busy hour. Two-Way Interconnection Trunk groups that connect to a Verizon local Tandem shall be engineered using a design blocking objective of Xxxx-Xxxxxxxxx B.01 during the average time consistent busy hour. Verizon and PCS shall engineer Two-Way Interconnection Trunks using BOC Notes on the LEC Networks SR-TSV-002275. 2.4.9 The performance standard for final Two-Way Interconnection Trunk groups shall be that no such Interconnection Trunk group will exceed its design blocking objective (B.005 or B.01, as applicable) for three

  • One-Way Interconnection Trunks 2.3.1 Where the Parties use One-Way Interconnection Trunks for the delivery of traffic from Onvoy to Frontier, Onvoy, at Xxxxx’s own expense, shall: 2.3.1.1 provide its own facilities for delivery of the traffic to the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA; and/or 2.3.1.2 obtain transport for delivery of the traffic to the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA (a) from a third party, or, (b) if Frontier offers such transport pursuant to a Frontier access Tariff, from Frontier. 2.3.2 For each Tandem or End Office One-Way Interconnection Trunk group for delivery of traffic from Onvoy to Frontier with a utilization level of less than sixty percent (60%) for final trunk groups and eighty-five percent (85%) for high usage trunk groups, unless the Parties agree otherwise, Onvoy will promptly submit ASRs to disconnect a sufficient number of Interconnection Trunks to attain a utilization level of approximately sixty percent (60%) for all final trunk groups and eighty-five percent (85%) for all high usage trunk groups. In the event Onvoy fails to submit an ASR to disconnect One-Way Interconnection Trunks as required by this Section, Frontier may disconnect the excess Interconnection Trunks or bill (and Onvoy shall pay) for the excess Interconnection Trunks at the rates set forth in the Pricing Attachment. 2.3.3 Where the Parties use One-Way Interconnection Trunks for the delivery of traffic from Frontier to Onvoy, Frontier, at Frontier’s own expense, shall provide its own facilities for delivery of the traffic to the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA.

  • Network Interconnection Architecture Each Party will plan, design, construct and maintain the facilities within their respective systems as are necessary and proper for the provision of traffic covered by this Agreement. These facilities include but are not limited to, a sufficient number of trunks to the point of interconnection with the tandem company, and sufficient interoffice and interexchange facilities and trunks between its own central offices to adequately handle traffic between all central offices within the service areas at a P.01 grade of service or better. The provisioning and engineering of such services and facilities will comply with generally accepted industry methods and practices, and will observe the rules and regulations of the lawfully established tariffs applicable to the services provided.

  • Interconnection Service Interconnection Service allows the Interconnection Customer to connect the Large Generating Facility to the Participating TO’s Transmission System and be eligible to deliver the Large Generating Facility’s output using the available capacity of the CAISO Controlled Grid. To the extent the Interconnection Customer wants to receive Interconnection Service, the Participating TO shall construct facilities identified in Appendices A and C that the Participating TO is responsible to construct.

  • Interconnection Facilities 4.1.1 The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 of this Agreement. The NYISO, in consultation with the Connecting Transmission Owner, shall provide a best estimate cost, including overheads, for the purchase and construction of its Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, the NYISO, and the Connecting Transmission Owner. 4.1.2 The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with (1) owning, operating, maintaining, repairing, and replacing its own Interconnection Facilities, and

  • Interconnection Customer’s Interconnection Facilities The Interconnection Customer shall design, procure, construct, install, own and/or control the Interconnection Customer’s Interconnection Facilities described in Appendix A at its sole expense.

  • Participating TO’s Interconnection Facilities The Participating TO shall design, procure, construct, install, own and/or control the Participating TO’s Interconnection Facilities described in Appendix A at the sole expense of the Interconnection Customer. Unless the Participating TO elects to fund the capital for the Participating TO’s Interconnection Facilities, they shall be solely funded by the Interconnection Customer.

  • Interconnection Customer (1) Interconnection Customer shall construct and, unless otherwise indicated, shall own, the following Interconnection Facilities: None (2) In the event that, in accordance with the Interconnection Construction Service Agreement, Interconnection Customer has exercised the Option to Build, it is hereby permitted to build in accordance with and subject to the conditions and limitations set forth in that Section, the following portions of the Transmission Owner Interconnection Facilities which constitute or are part of the Customer Facility: None Ownership of the facilities built by Interconnection Customer pursuant to the Option to Build shall be as provided in the Interconnection Construction Service Agreement.