Common use of DELAYS AND DAMAGES Clause in Contracts

DELAYS AND DAMAGES. In the event Contractor is delayed in the prosecution and completion of the Work or achievement of any Contract Times because of any delays caused by City or Engineer, Contractor shall have no claim against City or Engineer for damages or contract adjustment other than an extension of the Contract Times as provided herein and the waiving of liquidated damages during the period occasioned by the delay.

Appears in 18 contracts

Samples: Construction Contract, Construction Agreement, Contract Agreement