DETAILED WORK SCHEDULE Sample Clauses
The DETAILED WORK SCHEDULE clause sets out a comprehensive timeline for the completion of specific tasks or milestones within a project. It typically outlines start and end dates for each phase of work, assigns responsibilities to parties involved, and may include provisions for monitoring progress or adjusting deadlines as needed. By clearly defining the sequence and timing of activities, this clause helps ensure that all parties are aligned on expectations and deadlines, reducing the risk of delays and misunderstandings during project execution.
DETAILED WORK SCHEDULE. D15.1 The Contractor shall provide the Contract Administrator with a detailed work schedule (Form L: tailed Work Schedule) at least two (2) Business Days prior to the commencement of any Work on the Site but in no event later than the date specified in the General Conditions for the return of the executed Contract.
D15.2 The detailed work schedule shall consist of the following:
(a) a ▇▇▇▇▇ chart for the Work, and
(b) a daily manpower schedule for the Work all acceptable to the Contract Administrator.
DETAILED WORK SCHEDULE. D13.1 The Contractor shall provide the Contract Administrator with a detailed work schedule at least two (2) Business Days prior to the commencement of any Work on the Site but in no event later than the date specified in C4.1 for the return of the executed Contract.
D13.2 The detailed work schedule shall consist of the following:
(a) a critical path method (C.P.M.) schedule for the Work; and
(b) a ▇▇▇▇▇ chart for the Work based on the C.P.M. schedule; all acceptable to the Contract Administrator. D13.3 Further to D13.2(a), the C.P.M. schedule shall clearly identify the start and completion dates of all of the following activities/tasks making up the Work as well as showing those activities/tasks on the critical path:
(a) Commencement Date.
(b) Installation of Land Drainage Sewers on a street by street basis.
(c) Surface restoration.
(d) Substantial Performance.
(e) Total Performance.
DETAILED WORK SCHEDULE. D13.1 The Contractor shall provide the Contract Administrator with a detailed work schedule at least two (2) Business Days prior to the commencement of any Work on the Site but in no event later than the date specified in C4.1 for the return of the executed Contract.
D13.2 The detailed work schedule shall consist of the following:
(a) a critical path method (C.P.M.) schedule for the Work; and
(b) a ▇▇▇▇▇ chart for the Work based on the C.P.M. schedule;
(c) all acceptable to the Contract Administrator. D13.3 Further to D13.2(a), the C.P.M. schedule shall clearly identify the start and completion dates of all of the following activities/tasks making up the Work as well as showing those activities/tasks on the critical path:
(a) Commencement Date (b) Major shaft construction
DETAILED WORK SCHEDULE. D13.1 The Contractor shall provide the Contract Administrator with a detailed work schedule at least two (2) Business Days prior to the commencement of any Work on the Site but in no event later than the date specified in the General Conditions for the return of the executed Contract.
D13.2 The detailed work schedule shall consist of the following:
(a) a critical path method (C.P.M.) schedule for the Work;
(b) a ▇▇▇▇▇ chart for the Work based on the C.P.M. schedule; all acceptable to the Contract Administrator. D13.3 Further to D13.2(a), the C.P.M. schedule shall clearly identify the start and completion dates of all of the following activities/tasks making up the Work as well as showing those activities/tasks on the critical path:
(a) Commencement Date;
(b) Storm relief sewers and appurtenances on:
(i) ▇▇▇▇▇ ▇▇▇▇▇▇ – ▇▇▇▇▇▇▇ ▇▇▇. to ▇▇▇▇ Ave.
(ii) ▇▇▇▇▇ ▇▇▇▇▇▇ – ▇▇▇▇ Ave. to ▇▇▇▇▇ Ave.
(iii) ▇▇▇▇▇ ▇▇▇▇▇▇ – ▇▇▇▇▇ Ave. to ▇▇▇▇▇ ▇▇▇.
(iv) ▇▇▇▇ Avenue
(v) Pacific Avenue
(vi) ▇▇▇▇▇ Avenue
(vii) ▇▇▇▇▇▇▇ Avenue
(viii) Alexander Avenue
(c) Surface restorations:
(i) Pavement
(ii) Sodding
(d) Substantial Performance;
(e) Total Performance.