Development of Punch List. Prior to submittal of the initial Project Substantial Completion Certificate, Contractor will prepare and deliver to Owner a written list setting forth all of the items that remain to be performed in order to complete the Work, provided such items of Work on such list shall only be items that are (i) minor in nature, (ii) not related to the functionality, utility, operation or restoration of Work, (iii) not related to the compliance of any such Work with any Applicable Laws or Applicable Permits, and (iv) not related to the correction of Defects. Such list shall also state the proposed time limits within which Contractor will complete each of such remaining Work items. Upon its receipt of such list, Owner will reasonably review the same and notify Contractor of any proposed revisions thereto. Owner’s Project Manager and Contractor’s Project Manager will then meet and consult in good faith to agree upon the definitive, final version of such list (including the approved time limits within which Contractor will perform such remaining Work items) (such final list, as agreed to by Owner, the “Final Punch List”).
Appears in 6 contracts
Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement
Development of Punch List. Prior to submittal of the initial Project Substantial Completion Certificate, Contractor Company will prepare and deliver to Owner and Owner’s Engineer a written list setting forth all of the items that remain to be performed in order to complete the Work, provided such items of Work on such list shall only be items that are (i) minor in nature, (ii) not related to the functionality, utility, operation or restoration of Work, and (iii) not related to the compliance of any such Work with any Applicable Laws or Applicable Permits, and (iv) not related to the correction of Defects. Such list shall also state the proposed time limits within which Contractor Company will complete each such item of such remaining Work itemsWork. Upon its No later than ten (10) Business Days after receipt of such list, Owner or Owner’s Project Manager will reasonably review the same and notify Contractor Company of any proposed revisions theretothereto and comments thereon. Owner’s Project Manager and ContractorCompany’s Project Manager will then meet and consult in good faith to agree upon the definitive, final version of such list (including the approved time limits within which Contractor Company will perform such remaining Work items) (such final list, as agreed to in writing by Owner, the “Final Punch List”).
Appears in 1 contract
Samples: Commercial Scale Demonstration Agreement (Heliogen, Inc.)