Discovery of Karst Features. In the event Karst Features are discovered within the Project ROW or a Replacement Utility Property Interest, DB Contractor shall comply with and shall cause all Persons performing Work or Utility Adjustment Work to comply with Item 12 of the Design-Build Specifications and the RID entitled “Karst Feature Discovery and Mitigation” with respect to the relevant Karst Features. DB Contractor shall be deemed to have waived the right to collect any and all costs incurred in connection with any Unknown Karst Features and any right to obtain an extension of a Completion Deadline in connection with any Unknown Karst Features if TxDOT is not provided written notice of the discovery of the Unknown Karst Feature and afforded the opportunity to inspect sites containing the Unknown Karst Feature before any action is taken that would inhibit TxDOT’s ability to ascertain, based on a site inspection, the nature and extent of the mitigation work required for such Unknown Karst Feature.
Appears in 4 contracts
Samples: Build Agreement, Build Agreement, Build Agreement
Discovery of Karst Features. In the event Karst Features are discovered within the Project ROW or a Replacement Utility Property Interest, DB Contractor shall comply with and shall cause all Persons performing Work or Utility Adjustment Work to comply with Item 12 of the Design-Build Specifications and the RID entitled “Karst Feature Discovery and Mitigation” with respect to the relevant Karst Features. DB Contractor shall be deemed to have waived the right to collect any and all costs incurred in connection with any Unknown Karst Features and any right to obtain an extension of a Completion Deadline in connection with any Unknown Karst Features if TxDOT is not provided written notice of the discovery of the Unknown Karst Feature and afforded the opportunity to inspect sites containing the Unknown Karst Feature before any action is taken that would inhibit TxDOT’s ability to ascertain, based on a site inspection, the nature and extent of the mitigation work required for such Unknown Karst Feature.
Appears in 2 contracts
Samples: Design Build Agreement, Build Agreement
Discovery of Karst Features. In the event Karst Features are discovered within the Project ROW or a Replacement Utility Property InterestROW, DB Contractor shall comply with and shall cause all Persons performing Work or Utility Adjustment Work to comply with Item 12 of the Design-Build Specifications and the RID entitled titled “Karst Feature Discovery and Mitigation.” with respect to the relevant Karst Features. DB Contractor shall be deemed to have waived the right to collect any and all costs incurred in connection with any Unknown Karst Features and any right to obtain an extension of a Completion Deadline in connection with any Unknown Karst Features if TxDOT is not provided written notice of the discovery of the Unknown Karst Feature and afforded the opportunity to inspect sites containing the Unknown Karst Feature before any action is taken that would inhibit TxDOT’s ability to ascertain, based on a site inspection, the nature and extent of the mitigation work required for such Unknown Karst Feature.
Appears in 1 contract
Samples: Build Agreement
Discovery of Karst Features. [In the event Karst Features are discovered within the Project ROW or a Replacement Utility Property Interest, DB Contractor shall comply with and shall cause all Persons performing Work or Utility Adjustment Work to comply with Item 12 of the Design-Build Specifications and the RID entitled “Karst Feature Discovery and Mitigation” with respect to the relevant Karst Features. DB Contractor shall be deemed to have waived the right to collect any and all costs incurred in connection with any Unknown Karst Features and any right to obtain an extension of a Completion Deadline in connection with any Unknown Karst Features if TxDOT is not provided written notice of the discovery of the Unknown Karst Feature and afforded the opportunity to inspect sites containing the Unknown Karst Feature before any action is taken that would inhibit TxDOT’s ability to ascertain, based on a site inspection, the nature and extent of the mitigation work required for such Unknown Karst Feature.]
Appears in 1 contract
Samples: Professional Services Agreement