Documentation In Support Of Claims. Upon discovering an event or condition forming the basis of a claim for an increase in the Contract Price or an extension of the Contract Time, Design/Builder shall, until the claim is resolved, commence to maintain separate records evidencing all costs and delays incurred in connection with the event or condition forming the basis for the claim.

Appears in 4 contracts

Samples: Design and Construction Agreement, Guaranteed Maximum Price Design and Construction Agreement, Design and Construction Agreement

AutoNDA by SimpleDocs

Documentation In Support Of Claims. Upon discovering an event or condition forming the basis of a claim for an increase in the Contract Guaranteed Maximum Price or an extension of the Contract Time, Design/Builder Firm shall, until the claim is resolved, commence to maintain separate records evidencing all costs and delays incurred in connection with the event or condition forming the basis for the claim.

Appears in 1 contract

Samples: Professional Services

AutoNDA by SimpleDocs