Duration of relief for force majeure. The right of an Affected Party to relief under Clause 17.2 shall cease on the earlier of: (a) the date on which its performance of the Relevant Obligations is no longer prevented or materially impeded by the Relevant Force Majeure Event; and (b) the date on which such performance would no longer have been prevented or materially impeded if the Affected Party had complied with its obligations under Clause 17.6.
Appears in 103 contracts
Samples: Track Access Contract, Track Access Contract, Track Access Contract (Freight Services)
Duration of relief for force majeure. The right of an Affected Party to relief under Clause clause 17.2 shall cease on the earlier of:
(a) the date on which its performance of the Relevant Obligations is no longer prevented or materially impeded by the Relevant Force Majeure Event; and
(b) the date on which such performance would no longer have been prevented or materially impeded if the Affected Party had complied with its obligations under Clause clause 17.6.
Appears in 44 contracts
Samples: Track Access Contract (Passenger Services), Track Access Contract (Passenger Services), Track Access Contract (Passenger Services)
Duration of relief for force majeure. The right of an Affected Party to relief under Clause 17.2 17.1 shall cease on the earlier of:
(a) the date on which its performance of the Relevant Obligations is no longer prevented or materially impeded by the Relevant Force Majeure Event; and
(b) the date on which such performance would no longer have been prevented or materially impeded if the Affected Party had complied with its obligations under Clause 17.617.5.
Appears in 19 contracts
Samples: Model Connection Contract, Model Connection Contract, Model Connection Contract
Duration of relief for force majeure. The right of an Affected Party to relief under Clause 17.2 shall cease on the earlier of:
(a) : the date on which its performance of the Relevant Obligations is no longer prevented or materially impeded by the Relevant Force Majeure Event; and
(b) and the date on which such performance would no longer have been prevented or materially impeded if the Affected Party had complied with its obligations under Clause 17.6.
Appears in 10 contracts
Samples: Freight Customer Track Access Contract, Track Access Contract, Freight Customer Track Access Contract
Duration of relief for force majeure. The right of an Affected Party to relief under Clause clause 17.2 shall cease on the earlier of:
(a) : the date on which its performance of the Relevant Obligations is no longer prevented or materially impeded by the Relevant Force Majeure Event; and
(b) and the date on which such performance would no longer have been prevented or materially impeded if the Affected Party had complied with its obligations under Clause clause 17.6.
Appears in 3 contracts
Samples: Track Access Contract, Track Access Contract (Passenger Services), Track Access Contract
Duration of relief for force majeure. The right of an Affected Party to relief under Clause 17.2 shall cease on the earlier of:
(a) the date on which its performance of the Relevant Obligations is no longer prevented or materially impeded by the Relevant Force Majeure Event; andand
(b) the date on which such performance would no longer have been prevented or materially impeded if the Affected Party had complied with its obligations under Clause 17.6.17.6.
Appears in 2 contracts
Samples: Track Access Contract, Track Access Contract
Duration of relief for force majeure. The right of an Affected Party to relief under Clause 17.2 shall cease on the earlier of:
(a) the date on which its performance of the Relevant Obligations is no longer prevented or materially impeded by the Relevant Force Majeure Event; and
(b) the date on which such performance would no longer have been prevented or materially impeded if the Affected Party had complied with its obligations under Clause 17.6.
Appears in 1 contract
Duration of relief for force majeure. The right of an Affected Party to relief under Clause 17.2 shall cease on the earlier of:
(a) the date on which its performance of the Relevant Obligations is no longer prevented or materially impeded by the Relevant Force Majeure Event; and
(b) the date on which such performance would no longer have been prevented or materially impeded if the Affected Party had complied with its obligations under Clause 17.6.
Appears in 1 contract
Duration of relief for force majeure. The right of an Affected Party to relief under Clause clause 17.2 shall cease on the earlier of:
(a) the date on which its performance of the Relevant Obligations is no longer prevented or materially impeded by the Relevant Force Majeure Event; andand
(b) the date on which such performance would no longer have been prevented or materially impeded if the Affected Party had complied with its obligations under Clause 17.6.clause 17.6.
Appears in 1 contract
Samples: Track Access Contract
Duration of relief for force majeure. The right of an Affected Party to relief under Clause 17.2 17.1 shall cease on the earlier of:
(a) the date on which its performance of the Relevant Obligations is no longer prevented or materially impeded by the Relevant Force Majeure Event; and
(b) the date on which such performance would no longer have been prevented or materially impeded if the Affected Party had complied with its obligations under Clause 17.617.5.
Appears in 1 contract
Samples: Connection Contract
Duration of relief for force majeure. The right of an Affected Party to relief under Clause 17.2 14.2 shall cease on the earlier of:
(a) the date on which its performance of the Relevant Obligations is no longer prevented or materially impeded by the Relevant Force Majeure Event; and
(b) the date on which such performance would no longer have been prevented or materially impeded if the Affected Party had complied with its obligations under Clause 17.614.6.
Appears in 1 contract
Samples: Track Access Contract
Duration of relief for force majeure. The right of an Affected Party to relief under Clause 17.2 shall cease on the earlier of:
(a) the date on which its performance of the Relevant Obligations is no longer prevented or materially impeded by the Relevant Force Majeure Event; and
(b) the date on which such performance would no longer have been prevented or materially impeded if the Affected Party had complied with its obligations under Clause 17.6.
Appears in 1 contract
Samples: Track Access Contract