Earned Value. Chart 11-1 tracks the planned costs, earned value, and actual costs for the Project. Commencing with start of Quarter 1, the Planned Cost, Earned Value, and Actual Costs, as shown in the chart, have been aligned as a starting point for tracking. Moving forward, the chart will show the Earned Value and Actual Costs incurred, relative to Planned Costs over time.
Appears in 16 contracts
Samples: Urban Flood Risk Reduction Funding Agreement, Urban Flood Risk Reduction Funding Agreement, Urban Flood Risk Reduction Funding Agreement
Earned Value. β Chart 11-1 tracks the planned costs, earned value, and actual costs for the Project. Commencing with start of Quarter 1, the Planned Cost, Earned Value, and Actual Costs, as shown in the chart, have been aligned as a starting point for tracking. Moving forward, the chart will show the Earned Value and Actual Costs incurred, relative to Planned Costs over time.
Appears in 5 contracts
Samples: Urban Flood Risk Reduction Funding Agreement, Urban Flood Risk Reduction Funding Agreement, Urban Flood Risk Reduction Funding Agreement