Common use of Effectiveness; Continued Performance Pending Resolution of Disputes Clause in Contracts

Effectiveness; Continued Performance Pending Resolution of Disputes. If a Change in the Work is initiated under this Article 8, then the Change Order and the modifications made pursuant to such Change Order shall be effective upon Company’s issuance of a Change Order with respect thereto. Notwithstanding a dispute regarding any proposed or requested Change Order, or any adjustment of one or more of the Contract Price, the Schedule (including the Guaranteed Substantial Completion Date and the Guaranteed Final Completion Date), or any other such part of this Contract as may be affected with respect to a Change Order, Contractor shall proceed with the performance of such Change Order promptly following Company’s execution of the corresponding Change Order.

Appears in 2 contracts

Samples: Engineering, Procurement and Construction Contract (Us Geothermal Inc), Engineering, Procurement and Construction Contract (Us Geothermal Inc)

AutoNDA by SimpleDocs

Effectiveness; Continued Performance Pending Resolution of Disputes. If a Change in the Work is initiated under this Article 8ARTICLE 7, then the Change Order and the modifications made pursuant to such Change Order shall be effective upon CompanyOwner’s issuance of a Change Order with respect thereto. Notwithstanding a dispute regarding any proposed or requested Change Order, or any adjustment of one or more of the Contract Price, the Schedule (including the Guaranteed Substantial Completion Date and the Guaranteed Final Completion Date)Schedule, or any other such part of this Contract as may be affected with respect to a Change Order, Contractor shall proceed with the performance of such Change Order promptly following CompanyOwner’s execution of the corresponding Change Order.

Appears in 2 contracts

Samples: Procurement and Construction Contract, Procurement and Construction Contract (Clean Coal Technologies Inc.)

AutoNDA by SimpleDocs

Effectiveness; Continued Performance Pending Resolution of Disputes. If a Change in the Work is initiated under this Article 8, then the Change Order and the modifications made pursuant to such Change Order shall be effective upon Company’s issuance of a Change Order with respect thereto. Notwithstanding a dispute regarding any proposed or requested Change Order, or any adjustment of one or more of the Contract Price, the Schedule (including the Guaranteed Substantial Completion Date and the Guaranteed Final Completion Date), or any other such part of this Contract as may be affected with respect to a Change Order, Contractor shall proceed with the performance of such Change Order promptly following Company’s execution of the corresponding Change Order.

Appears in 2 contracts

Samples: Construction Contract (Us Geothermal Inc), Construction Contract (Us Geothermal Inc)