Elbridge Substation. National Grid shall be responsible for and shall make improvements to the Elbridge Substation to receive and accommodate the Proposed Line, Relocated Line 15, and Bused Line 5. • February 2016: Article VII Certificate Order Issued • April 2016: Submission of EM&CP Requesting Approval • April 2016: Submission of USACOE Permit Application • 4 months after EM&CP submission: Issuance of EM&CP Approval Order • 4 months after USACOE application submission: Issuance of USACOE Permit • 5 months after Submission of EM&CP: Commence Construction (Phase 1) (If EM&CP is approved by that time) • 6 months after Phase 1 Construction Start: Complete Construction (Phase 1) • 6 months after Phase 1 Construction Start: In-Service Date (Phase 1) • 2 month after Phase 1 Construction Start: Commence Construction (Phase 2) • 7 months after Phase 2 Construction Start: Complete Construction (Phase 2) • 7 months after Phase 2 Construction Start: In-Service Date (Phase 2) Note: This schedule does not reflect potential federal permit or PSC Certificate conditions that may restrict the ability to begin construction as noted. The dates above represent the Parties’ preliminary schedule, which is subject to adjustment, alteration, and extension. Neither Party shall be liable for failure to meet the above Estimated Milestone Schedule, any milestone, any in-service date, or any other projected or preliminary schedule in connection with this Agreement, the Work or the ATP. National Grid does not and cannot guarantee or covenant that any outage necessary in connection with the Work will occur when presently scheduled, or on any other particular date or dates, and shall have no liability arising from any change in the date or dates of such outages. Insurance Requirements In accordance with Section 13 of the Commercial Agreement relating to the ATP Project, National Grid and NYSEG have elected to self-insure to the level of their respective self-insured retention limits of any single loss and maintain excess insurance coverage above this level and in accordance with amounts set forth below: Workers Compensation and Employers Liability Insurance as required by the State of New York. If required, coverage shall include the U.S. Xxxxxxxxx and Harbor Workers' Compensation Act and the Xxxxx Act. Commercial General Liability (Including Contractual Liability), covering all activities and operations to be performed by it under this Agreement, with the following minimum limits: (A) Bodily Injury - $1,000,000/$1,000,000 Property Damage - $1,000,000/$1,000,000 OR (B) Combined Single Limit - $1,000,000 OR (C) Bodily Injury and Property Damage per Occurrence - $1,000,000 General Aggregate & Product Aggregate - $2,000,000 each Umbrella or Excess Liability, coverage with a minimum limit of $10,000,000. 1. Upon request, either Party shall promptly provide the requesting Party with either evidence of insurance or certificates of insurance evidencing the insurance coverage above. NYSEG shall provide such certificates or evidence of insurance to National Grid at the following address: To: National Grid c/o NIAGARA MOHAWK POWER CORPORATION Attention: Risk & Insurance A-4 000 Xxxx Xxxxxxxxx Xxxx Xxxxxxxx, XX 00000 National Grid shall provide such certificates or evidence of insurance to NYSEG at the following address: To: NYSEG
Appears in 5 contracts
Samples: Commercial Agreement, Commercial Agreement, Commercial Agreement
Elbridge Substation. National Grid shall be responsible for and shall make improvements to the Elbridge Substation to receive and accommodate the Proposed Line, Relocated Line 15, and Bused Line 5. • February 2016: Article VII Certificate Order Issued • April 2016: Submission of EM&CP Requesting Approval • April 2016: Submission of USACOE Permit Application • 4 months after EM&CP submission: Issuance of EM&CP Approval Order • 4 months after USACOE application submission: Issuance of USACOE Permit • 5 months after Submission of EM&CP: Commence Construction (Phase 1) (If EM&CP is approved by that time) • 6 months after Phase 1 Construction Start: Complete Construction (Phase 1) • 6 months after Phase 1 Construction Start: In-Service Date (Phase 1) • 2 month after Phase 1 Construction Start: Commence Construction (Phase 2) • 7 months after Phase 2 Construction Start: Complete Construction (Phase 2) • 7 months after Phase 2 Construction Start: In-Service Date (Phase 2) Note: This schedule does not reflect potential federal permit or PSC Certificate conditions that may restrict the ability to begin construction as noted. The dates above represent the Parties’ preliminary schedule, which is subject to adjustment, alteration, and extension. Neither Party shall be liable for failure to meet the above Estimated Milestone Schedule, any milestone, any in-service date, or any other projected or preliminary schedule in connection with this Agreement, the Work or the ATP. National Grid does not and cannot guarantee or covenant that any outage necessary in connection with the Work will occur when presently scheduled, or on any other particular date or dates, and shall have no liability arising from any change in the date or dates of such outages. Insurance Requirements In accordance with Section 13 of the Commercial Agreement relating to the ATP Project, National Grid and NYSEG have elected to self-insure to the level of their respective self-insured retention limits of any single loss and maintain excess insurance coverage above this level and in accordance with amounts set forth below: Workers Compensation and Employers Liability Insurance as required by the State of New York. If required, coverage shall include the U.S. Xxxxxxxxx and Harbor Workers' Compensation Act and the Xxxxx Act. Commercial General Liability (Including Contractual Liability), covering all activities and operations to be performed by it under this Agreement, with the following minimum limits:
(A) Bodily Injury - $1,000,000/$1,000,000 Property Damage - $1,000,000/$1,000,000 OR
(B) Combined Single Limit - $1,000,000 OR
(C) Bodily Injury and Property Damage per Occurrence - $1,000,000 General Aggregate & Product Aggregate - $2,000,000 each Umbrella or Excess Liability, coverage with a minimum limit of $10,000,000.
1. Upon request, either Party shall promptly provide the requesting Party with either evidence of insurance or certificates of insurance evidencing the insurance coverage above. NYSEG shall provide such certificates or evidence of insurance to National Grid at the following address: To: National Grid c/o NIAGARA MOHAWK POWER CORPORATION Attention: Risk & Insurance A-4 000 Xxxx Xxxxxxxxx Xxxx Xxxxxxxx, XX 00000 National Grid shall provide such certificates or evidence of insurance to NYSEG at the following address: To: NYSEGNYSEG 00 Xxxx Xxxxx Xxxxxxxxxx, XX 00000
2. Should any of the above-described policies be cancelled before the expiration date thereof, notice will be delivered in accordance with the policy provisions.
3. If a party fails to secure or maintain any insurance coverage, or any insurance coverage is canceled before the completion of all services provided under this Agreement, and such party fails immediately to procure such insurance as specified herein, then the non-defaulting party has the right but not the obligation to procure such insurance and, at its option, either xxxx the cost thereof to the defaulting party or deduct the cost thereof from any sum due the defaulting party under this Agreement.
4. To the extent requested, both Parties shall furnish to each other copies of any accidents report(s) sent to the Party's insurance carriers covering accidents or incidents occurring in connection with or as a result of the performance of the Work for the Project under this Agreement.
5. Each Party shall comply with any governmental and/or site-specific insurance requirements even if not stated herein.
6. By the date that such coverage is required, each Party represents to the other that it will have full policy limits available and shall notify each other in writing when coverages required herein have been reduced as a result of claim payments, expenses, or both.
Appears in 3 contracts
Samples: Commercial Agreement, Commercial Agreement, Commercial Agreement
Elbridge Substation. National Grid shall be responsible for and shall make improvements to the Elbridge Substation to receive and accommodate the Proposed Line, Relocated Line 15, and Bused Line 5. • February 2016: Article VII Certificate Order Issued • April 2016: Submission of EM&CP Requesting Approval • April 2016: Submission of USACOE Permit Application • 4 months after EM&CP submission: Issuance of EM&CP Approval Order • 4 months after USACOE application submission: Issuance of USACOE Permit • 5 months after Submission of EM&CP: Commence Construction (Phase 1) (If EM&CP is approved by that time) • 6 months after Phase 1 Construction Start: Complete Construction (Phase 1) • 6 months after Phase 1 Construction Start: In-Service Date (Phase 1) • 2 month after Phase 1 Construction Start: Commence Construction (Phase 2) • 7 months after Phase 2 Construction Start: Complete Construction (Phase 2) • 7 months after Phase 2 Construction Start: In-Service Date (Phase 2) Note: This schedule does not reflect potential federal permit or PSC Certificate conditions that may restrict the ability to begin construction as noted. The dates above represent the Parties’ preliminary schedule, which is subject to adjustment, alteration, and extension. Neither Party shall be liable for failure to meet the above Estimated Milestone Schedule, any milestone, any in-service date, or any other projected or preliminary schedule in connection with this Agreement, the Work or the ATP. National Grid does not and cannot guarantee or covenant that any outage necessary in connection with the Work will occur when presently scheduled, or on any other particular date or dates, and shall have no liability arising from any change in the date or dates of such outages. Insurance Requirements In accordance with Section 13 of the Commercial Agreement relating to the ATP Project, National Grid and NYSEG have elected to self-insure to the level of their respective self-insured retention limits of any single loss and maintain excess insurance coverage above this level and in accordance with amounts set forth below: Workers Compensation and Employers Liability Insurance as required by the State of New York. If required, coverage shall include the U.S. Xxxxxxxxx and Harbor Workers' Compensation Act and the Xxxxx Act. Commercial General Liability (Including Contractual Liability), covering all activities and operations to be performed by it under this Agreement, with the following minimum limits:
(A) Bodily Injury - $1,000,000/$1,000,000 Property Damage - $1,000,000/$1,000,000 OR
(B) Combined Single Limit - $1,000,000 OR
(C) Bodily Injury and Property Damage per Occurrence - $1,000,000 General Aggregate & Product Aggregate - $2,000,000 each Umbrella or Excess Liability, coverage with a minimum limit of $10,000,000.
1. Upon request, either Party shall promptly provide the requesting Party with either evidence of insurance or certificates of insurance evidencing the insurance coverage above. NYSEG shall provide such certificates or evidence of insurance to National Grid at the following address: To: National Grid c/o NIAGARA MOHAWK POWER CORPORATION Attention: Risk & Insurance A-4 000 Xxxx Xxxxxxxxx Xxxx XxxxxxxxSyracuse, XX 00000 NY 13202 National Grid shall provide such certificates or evidence of insurance to NYSEG at the following address: To: NYSEG
Appears in 2 contracts
Samples: Commercial Agreement, Commercial Agreement
Elbridge Substation. National Grid shall be responsible for and shall make improvements to the Elbridge Substation to receive and accommodate the Proposed Line, Relocated Line 15, and Bused Line 5. • February 2016: Article VII Certificate Order Issued • April 2016: Submission of EM&CP Requesting Approval • April 2016: Submission of USACOE Permit Application • 4 months after EM&CP submission: Issuance of EM&CP Approval Order • 4 months after USACOE application submission: Issuance of USACOE Permit • 5 months after Submission of EM&CP: Commence Construction (Phase 1) (If EM&CP is approved by that time) • 6 months after Phase 1 Construction Start: Complete Construction (Phase 1) • 6 months after Phase 1 Construction Start: In-Service Date (Phase 1) • 2 month after Phase 1 Construction Start: Commence Construction (Phase 2) • 7 months after Phase 2 Construction Start: Complete Construction (Phase 2) • 7 months after Phase 2 Construction Start: In-Service Date (Phase 2) Note: This schedule does not reflect potential federal permit or PSC Certificate conditions that may restrict the ability to begin construction as noted. The dates above represent the Parties’ preliminary schedule, which is subject to adjustment, alteration, and extension. Neither Party shall be liable for failure to meet the above Estimated Milestone Schedule, any milestone, any in-service date, or any other projected or preliminary schedule in connection with this Agreement, the Work or the ATP. National Grid does not and cannot guarantee or covenant that any outage necessary in connection with the Work will occur when presently scheduled, or on any other particular date or dates, and shall have no liability arising from any change in the date or dates of such outages. Insurance Requirements In accordance with Section 13 of the Commercial Agreement relating to the ATP Project, National Grid and NYSEG have elected to self-insure to the level of their respective self-insured retention limits of any single loss and maintain excess insurance coverage above this level and in accordance with amounts set forth below: • Workers Compensation and Employers Liability Insurance as required by the State of New York. If required, coverage shall include the U.S. Xxxxxxxxx and Harbor Workers' Compensation Act and the Xxxxx Act. • Commercial General Liability (Including Contractual Liability), covering all activities and operations to be performed by it under this Agreement, with the following minimum limits:
(A) Bodily Injury - $1,000,000/$1,000,000 Property Damage - $1,000,000/$1,000,000 OR
(B) Combined Single Limit - $1,000,000 OR
(C) Bodily Injury and Property Damage per Occurrence - $1,000,000 General Aggregate & Product Aggregate - $2,000,000 each • Umbrella or Excess Liability, coverage with a minimum limit of $10,000,000.
1. Upon request, either Party shall promptly provide the requesting Party with either evidence of insurance or certificates of insurance evidencing the insurance coverage above. NYSEG shall provide such certificates or evidence of insurance to National Grid at the following address: To: National Grid c/o NIAGARA MOHAWK POWER CORPORATION Attention: Risk & Insurance A-4 000 Xxxx Xxxxxxxxx Xxxx Xxxxxxxx, XX 00000 National Grid shall provide such certificates or evidence of insurance to NYSEG at the following address: To: NYSEGNYSEG 00 Xxxx Xxxxx Binghamton, NY 13902
2. Should any of the above-described policies be cancelled before the expiration date thereof, notice will be delivered in accordance with the policy provisions.
3. If a party fails to secure or maintain any insurance coverage, or any insurance coverage is canceled before the completion of all services provided under this Agreement, and such party fails immediately to procure such insurance as specified herein, then the non-defaulting party has the right but not the obligation to procure such insurance and, at its option, either bill the cost thereof to the defaulting party or deduct the cost thereof from any sum due the defaulting party under this Agreement.
4. To the extent requested, both Parties shall furnish to each other copies of any accidents report(s) sent to the Party's insurance carriers covering accidents or incidents occurring in connection with or as a result of the performance of the Work for the Project under this Agreement.
5. Each Party shall comply with any governmental and/or site-specific insurance requirements even if not stated herein.
6. By the date that such coverage is required, each Party represents to the other that it will have full policy limits available and shall notify each other in writing when coverages required herein have been reduced as a result of claim payments, expenses, or both.
Appears in 1 contract
Samples: Commercial Agreement
Elbridge Substation. National Grid shall be responsible for and shall make improvements to the Elbridge Substation to receive and accommodate the Proposed Line, Relocated Line 15, and Bused Line 5. • February 2016: Article VII Certificate Order Issued • April 2016: Submission of EM&CP Requesting Approval • April 2016: Submission of USACOE Permit Application • 4 months after EM&CP submission: Issuance of EM&CP Approval Order • 4 months after USACOE application submission: Issuance of USACOE Permit • 5 months after Submission of EM&CP: Commence Construction (Phase 1) (If EM&CP is approved by that time) • 6 months after Phase 1 Construction Start: Complete Construction (Phase 1) • 6 months after Phase 1 Construction Start: In-Service Date (Phase 1) • 2 month after Phase 1 Construction Start: Commence Construction (Phase 2) • 7 months after Phase 2 Construction Start: Complete Construction (Phase 2) • 7 months after Phase 2 Construction Start: In-Service Date (Phase 2) Note: This schedule does not reflect potential federal permit or PSC Certificate conditions that may restrict the ability to begin construction as noted. The dates above represent the Parties’ preliminary schedule, which is subject to adjustment, alteration, and extension. Neither Party shall be liable for failure to meet the above Estimated Milestone Schedule, any milestone, any in-service date, or any other projected or preliminary schedule in connection with this Agreement, the Work or the ATP. National Grid does not and cannot guarantee or covenant that any outage necessary in connection with the Work will occur when presently scheduled, or on any other particular date or dates, and shall have no liability arising from any change in the date or dates of such outages. Insurance Requirements In accordance with Section 13 of the Commercial Agreement relating to the ATP Project, National Grid and NYSEG have elected to self-insure to the level of their respective self-insured retention limits of any single loss and maintain excess insurance coverage above this level and in accordance with amounts set forth below: • Workers Compensation and Employers Liability Insurance as required by the State of New York. If required, coverage shall include the U.S. Xxxxxxxxx and Harbor Workers' Compensation Act and the Xxxxx Act. • Commercial General Liability (Including Contractual Liability), covering all activities and operations to be performed by it under this Agreement, with the following minimum limits:
(A) Bodily Injury - $1,000,000/$1,000,000 Property Damage - $1,000,000/$1,000,000 OR
(B) Combined Single Limit - $1,000,000 OR
(C) Bodily Injury and Property Damage per Occurrence - $1,000,000 General Aggregate & Product Aggregate - $2,000,000 each • Umbrella or Excess Liability, coverage with a minimum limit of $10,000,000.
1. Upon request, either Party shall promptly provide the requesting Party with either evidence of insurance or certificates of insurance evidencing the insurance coverage above. NYSEG shall provide such certificates or evidence of insurance to National Grid at the following address: To: National Grid c/o NIAGARA MOHAWK POWER CORPORATION Attention: Risk & Insurance A-4 000 Xxxx Xxxxxxxxx Xxxx Xxxxxxxx, XX 00000 National Grid shall provide such certificates or evidence of insurance to NYSEG at the following address: To: NYSEGNYSEG 00 Xxxx Xxxxx Xxxxxxxxxx, XX 00000
2. Should any of the above-described policies be cancelled before the expiration date thereof, notice will be delivered in accordance with the policy provisions.
3. If a party fails to secure or maintain any insurance coverage, or any insurance coverage is canceled before the completion of all services provided under this Agreement, and such party fails immediately to procure such insurance as specified herein, then the non-defaulting party has the right but not the obligation to procure such insurance and, at its option, either xxxx the cost thereof to the defaulting party or deduct the cost thereof from any sum due the defaulting party under this Agreement.
4. To the extent requested, both Parties shall furnish to each other copies of any accidents report(s) sent to the Party's insurance carriers covering accidents or incidents occurring in connection with or as a result of the performance of the Work for the Project under this Agreement.
5. Each Party shall comply with any governmental and/or site-specific insurance requirements even if not stated herein.
6. By the date that such coverage is required, each Party represents to the other that it will have full policy limits available and shall notify each other in writing when coverages required herein have been reduced as a result of claim payments, expenses, or both.
Appears in 1 contract
Samples: Commercial Agreement
Elbridge Substation. National Grid shall be responsible for and shall make improvements to the Elbridge Substation to receive and accommodate the Proposed Line, Relocated Line 15, and Bused Line 5. • February 2016: Article VII Certificate Order Issued • April 2016: Submission of EM&CP Requesting Approval • April 2016: Submission of USACOE Permit Application • 4 months after EM&CP submission: Issuance of EM&CP Approval Order • 4 months after USACOE application submission: Issuance of USACOE Permit XXXXXX Xxxxxx • 5 months after Submission of EM&CP: Commence Construction (Phase 1) (If EM&CP is approved by that time) • 6 months after Phase 1 Construction Start: Complete Construction (Phase 1) • 6 months after Phase 1 Construction Start: In-Service Date (Phase 1) • 2 month after Phase 1 Construction Start: Commence Construction (Phase 2) • 7 months after Phase 2 Construction Start: Complete Construction (Phase 2) • 7 months after Phase 2 Construction Start: In-Service Date (Phase 2) Note: This schedule does not reflect potential federal permit or PSC Certificate conditions that may restrict the ability to begin construction as noted. The dates above represent the Parties’ preliminary schedule, which is subject to adjustment, alteration, and extension. Neither Party shall be liable for failure to meet the above Estimated Milestone Schedule, any milestone, any in-service date, or any other projected or preliminary schedule in connection with this Agreement, the Work or the ATP. National Grid does not and cannot guarantee or covenant that any outage necessary in connection with the Work will occur when presently scheduled, or on any other particular date or dates, and shall have no liability arising from any change in the date or dates of such outages. Insurance Requirements In accordance with Section 13 of the Commercial Agreement relating to the ATP Project, National Grid and NYSEG have elected to self-insure to the level of their respective self-insured retention limits of any single loss and maintain excess insurance coverage above this level and in accordance with amounts set forth below: Workers Compensation and Employers Liability Insurance as required by the State of New York. If required, coverage shall include the U.S. Xxxxxxxxx and Harbor Workers' Compensation Act and the Xxxxx Act. Commercial General Liability (Including Contractual Liability), covering all activities and operations to be performed by it under this Agreement, with the following minimum limits:
(A) Bodily Injury - $1,000,000/$1,000,000 Property Damage - $1,000,000/$1,000,000 OR
(B) Combined Single Limit - $1,000,000 OR
(C) Bodily Injury and Property Damage per Occurrence - $1,000,000 General Aggregate & Product Aggregate - $2,000,000 each Umbrella or Excess Liability, coverage with a minimum limit of $10,000,000.
1. Upon request, either Party shall promptly provide the requesting Party with either evidence of insurance or certificates of insurance evidencing the insurance coverage above. NYSEG shall provide such certificates or evidence of insurance to National Grid at the following address: To: National Grid c/o NIAGARA MOHAWK POWER CORPORATION Attention: Risk & Insurance A-4 000 Xxxx Xxxxxxxxx Xxxx Xxxxxxxx, XX 00000 National Grid shall provide such certificates or evidence of insurance to NYSEG at the following address: To: NYSEG
Appears in 1 contract
Samples: Commercial Agreement
Elbridge Substation. National Grid shall be responsible for and shall make improvements to the Elbridge Substation to receive and accommodate the Proposed Line, Relocated Line 15, and Bused Line 5. • February 2016: Article VII Certificate Order Issued • April 2016: Submission of EM&CP Requesting Approval • April 2016: Submission of USACOE Permit Application • 4 months after EM&CP submission: Issuance of EM&CP Approval Order • 4 months after USACOE application submission: Issuance of USACOE Permit XXXXXX Xxxxxx • 5 months after Submission of EM&CP: Commence Construction (Phase 1) (If EM&CP is approved by that time) • 6 months after Phase 1 Construction Start: Complete Construction (Phase 1) • 6 months after Phase 1 Construction Start: In-Service Date (Phase 1) • 2 month after Phase 1 Construction Start: Commence Construction (Phase 2) • 7 months after Phase 2 Construction Start: Complete Construction (Phase 2) • 7 months after Phase 2 Construction Start: In-Service Date (Phase 2) Note: This schedule does not reflect potential federal permit or PSC Certificate conditions that may restrict the ability to begin construction as noted. The dates above represent the Parties’ preliminary schedule, which is subject to adjustment, alteration, and extension. Neither Party shall be liable for failure to meet the above Estimated Milestone Schedule, any milestone, any in-service date, or any other projected or preliminary schedule in connection with this Agreement, the Work or the ATP. National Grid does not and cannot guarantee or covenant that any outage necessary in connection with the Work will occur when presently scheduled, or on any other particular date or dates, and shall have no liability arising from any change in the date or dates of such outages. Insurance Requirements In accordance with Section 13 of the Commercial Agreement relating to the ATP Project, National Grid and NYSEG have elected to self-insure to the level of their respective self-insured retention limits of any single loss and maintain excess insurance coverage above this level and in accordance with amounts set forth below: • Workers Compensation and Employers Liability Insurance as required by the State of New York. If required, coverage shall include the U.S. Xxxxxxxxx and Harbor Workers' Compensation Act and the Xxxxx Act. • Commercial General Liability (Including Contractual Liability), covering all activities and operations to be performed by it under this Agreement, with the following minimum limits:
(A) Bodily Injury - $1,000,000/$1,000,000 Property Damage - $1,000,000/$1,000,000 OR
(B) Combined Single Limit - $1,000,000 OR
(C) Bodily Injury and Property Damage per Occurrence - $1,000,000 General Aggregate & Product Aggregate - $2,000,000 each • Umbrella or Excess Liability, coverage with a minimum limit of $10,000,000.
1. Upon request, either Party shall promptly provide the requesting Party with either evidence of insurance or certificates of insurance evidencing the insurance coverage above. NYSEG shall provide such certificates or evidence of insurance to National Grid at the following address: To: National Grid c/o NIAGARA MOHAWK POWER CORPORATION Attention: Risk & Insurance A-4 000 Xxxx Xxxxxxxxx Xxxx Xxxxxxxx, XX 00000 National Grid shall provide such certificates or evidence of insurance to NYSEG at the following address: To: NYSEGNYSEG 00 Xxxx Xxxxx Xxxxxxxxxx, XX 00000
2. Should any of the above-described policies be cancelled before the expiration date thereof, notice will be delivered in accordance with the policy provisions.
3. If a party fails to secure or maintain any insurance coverage, or any insurance coverage is canceled before the completion of all services provided under this Agreement, and such party fails immediately to procure such insurance as specified herein, then the non-defaulting party has the right but not the obligation to procure such insurance and, at its option, either bill the cost thereof to the defaulting party or deduct the cost thereof from any sum due the defaulting party under this Agreement.
4. To the extent requested, both Parties shall furnish to each other copies of any accidents report(s) sent to the Party's insurance carriers covering accidents or incidents occurring in connection with or as a result of the performance of the Work for the Project under this Agreement.
5. Each Party shall comply with any governmental and/or site-specific insurance requirements even if not stated herein.
6. By the date that such coverage is required, each Party represents to the other that it will have full policy limits available and shall notify each other in writing when coverages required herein have been reduced as a result of claim payments, expenses, or both.
Appears in 1 contract
Samples: Commercial Agreement