EVACUATION FACILITIES. 4.4.1 Not later than 30 days prior to the scheduled commercial operation date of the Generation Facility, the generator under supervision of MSEDCL/MSETCL shall ensure that the construction and operation of the transmission line is completed to commence the supply of power to the Generation Facilities. MSEDCL/MSETCL when requested by the Generator shall supply power to the Generator during the following periods: a) The construction of the Generation Facility; (from separate feeder) b) The start-up and commissioning of the Generation Facility through import – export ( ABT Special Energy Meter); c) During scheduled maintenance of the Generation Facility; and d) During Forced Outages. 4.4.2 Generator can avail the Start-up power during the time of commissioning of the project at the MSEDCL’s prevailing HT Industrial Tariff rate in force from time to time and Generator shall pay for this electricity (Fixed Demand (kVA) & variable power in kWh) at that rate
Appears in 4 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement