Exclusion from further participation in this Agreement. If the Non-Defaulting Participants exclude the Defaulting Participant from further participation in the performance of this Agreement by notice under clause 13.3(c)(ii): (a) the other Participants may employ and pay other persons to replace the Defaulting Participant in the performance of the Alliance Works and may use all Design Documentation, Temporary Works and Construction Plant provided by the Defaulting Participant and necessary to perform the Alliance Works; (b) the Defaulting Participant will promptly, if required by the Non-Defaulting Participants, assign to RTA without payment the benefit of any agreements for the performance of any part of the Alliance Works; (c) as and when required by the ALT (and not before), the Defaulting Participant will remove from the Site any Temporary Works, Construction Plant and other property provided by the Defaulting Participant and if it fails to do so, not less than 10 Business Days after written notice of the Non-Defaulting Participants' intention to do so (but without being responsible for any loss or damage), the Non-Defaulting Participants may remove and/or sell any such Temporary Works, Construction Plant or other property; (d) the Defaulting Participant and its Representatives will no longer be entitled to be represented on the ALT or otherwise participate in the Project; and (e) the Non-Defaulting Participants may execute all deeds and documents and do all such things on behalf of the Defaulting Participant as is necessary for the performance of the Alliance Works and the Defaulting Participant irrevocably authorises any directors or managers of the Non-Defaulting Participants to act as its attorneys for the purpose of executing such deeds and documents and doing those things.
Appears in 3 contracts
Samples: Project Alliance Agreement, Project Alliance Agreement, Project Alliance Agreement
Exclusion from further participation in this Agreement. If the Non-Defaulting Participants exclude the Defaulting Participant from further participation in the performance of this Agreement by notice under clause 13.3(c)(ii):
(a) the other Participants may employ and pay other persons to replace the Defaulting Participant in the performance of the Alliance Works and may use all Design Documentation, Temporary Works and Construction Plant provided by the Defaulting Participant and necessary to perform the Alliance Works;
(b) the Defaulting Participant will promptly, if required by the Non-Defaulting Participants, assign to RTA RMS without payment the benefit of any agreements for the performance of any part of the Alliance Works;
(c) as and when required by the ALT (and not before), the Defaulting Participant will remove from the Site any Temporary Works, Construction Plant and other property provided by the Defaulting Participant and if it fails to do so, not less than 10 Business Days after written notice of the Non-Defaulting Participants' intention to do so (but without being responsible for any loss or damage), the Non-Defaulting Participants may remove and/or sell any such Temporary Works, Construction Plant or other property;
(d) the Defaulting Participant and its Representatives will no longer be entitled to be represented on the ALT or otherwise participate in the Project; and
(e) the Non-Defaulting Participants may execute all deeds and documents and do all such things on behalf of the Defaulting Participant as is necessary for the performance of the Alliance Works and the Defaulting Participant irrevocably authorises any directors or managers of the Non-Defaulting Participants to act as its attorneys for the purpose of executing such deeds and documents and doing those things.
Appears in 1 contract
Samples: Project Alliance Agreement