Execution of Tests Sample Clauses
Execution of Tests. Execution of tests involves the actual performance of the testing, including both system and integration testing. Supplier shall perform the execution of test Services, which include the following based on the test phase or test plan:
(i) Preparing test environment for the test phase;
(ii) Defining business test cycles for each test phase (i.e., a logical grouping of test conditions defined with consideration for repeatability and reuse, as well as functional area);
(iii) Defining business test scripts for each test phase (i.e., a definition of the steps necessary to perform a given business function test), including identifying additional test scripts associated with the integration of various application group components, which may not have been addressed by the individual teams and as applicable, combining test scripts for projects affecting multiple application groups;
(iv) Defining business test environment requirements for each test phase (i.e., a detailed description of the components and configurations needed for the business test environment);
(v) Defining system test scripts, including scripts used to test existing interfaces to business applications as well as scripts used to test new interfaces to applications (including as applicable for adaptive development work);
(vi) Delivering the test plan, test cases and test scripts to Health Net for review and approval;
(vii) Working out the detailed setup regarding coding components and test data to be tested with the test team during design;
(viii) Developing necessary test data based on test cases and business scenarios that are in accordance with Health Net’s standard methodologies (e.g., project development) as made available to Supplier, except where Supplier is only responsible for assisting Health Net in performing the testing, in which case Supplier will provide necessary inputs (e.g. information on table, fields, key fields, index fields, views etc.) to the Health Net project team to develop such test data;
(ix) Creating and managing all test data and the test data management process. Supplier will condition all test data and cases as needed to fulfill testing all requirements;
(x) Adequately conditioning test accounts so that such information may be accessed, as necessary, during the testing process;
(xi) Conducting each test phase other than UAT; coordinating and supporting Health Net in Health Net’s UAT efforts;
(xii) Leveraging technology to automate scripts to improve quality and through...
Execution of Tests. The tests shall be executed in accordance with the following rules:
a) The Head of Testing shall lead and supervise the tests and report on their status. Also, he/she will be in charge of all measurements, the calculation of results and the final report preparation. His/her decision will be determinant with respect to any questions concerning the test or its execution. The tests shall be carried out in compliance with the procedures and instructions of COES. The testing of the fiber optic system shall follow the technical specifications set out in Annex No. 5, Telecommunications, of this Contract.
b) The Concession Holder shall provide all reasonable facilities to the Inspector to obtain real, complete and acceptable data with respect to all the parts of the equipment associated with the project’s electric power transmission. Also, the Inspector shall have physical access to all the components associated with the project’s electromechanical equipment.
c) The main constituent components of the project shall be subjected to inspection, upon the Inpsector’s request, before the beginning of the tests.
d) Upon completion of each test, and in case it is within the acceptance levels, the corresponding certificate for that test shall be issued; with this the test will be finalized. Each certificate shall contain: i) the list of personnel of the Parties, OSINERGMIN’s representatives, and Inspector that participated in the tests, ii) the protocol of the tests carried out indicating the results obtained, iii) the list of tests not carried out with the corresponding waiver; and, iv) additional information deemed appropriate by the Concession Holder, OSINERGMIN and/or the Inspector.
Execution of Tests. The tests shall be executed in accordance with the following rules:
a) The Testing Supervisor shall lead and supervise the tests and report on their status. Also, he/she will be in charge of all measurements, the calculation of results and the final report preparation. His/her decision will be determinant with respect to any questions concerning the test or its execution. The tests shall be carried out in compliance with the procedures and instructions of the COES. The testing of the fiber optic system shall follow the technical specifications set out in Annex 5, Telecommunications, of this Contract. The Testing Supervisor shall be a licensed electrical or mechanical engineer, or an engineer in related branches. He/she shall have extensive experience as a Testing and/or Start-Up Supervisor for power transmission projects.
b) The CONCESSIONAIRE shall provide all reasonable facilities to the Inspector to obtain real, complete and acceptable data with respect to all the parts of the equipment associated with the Project’s electric power transmission. Also, the Inspector shall have physical access to all the components associated with the Project’s electromechanical equipment.
c) The main constituent components of the Project shall be subjected to inspection, upon the Inspector’s request, before the beginning of the tests.
d) Upon completion of each test, and in case it is within the acceptance levels, the corresponding certificate for that test shall be issued; with this the test will be finalized. Each certificate shall contain: i) the list of personnel of the Parties, OSINERGMIN’s representatives, and the Inspector that participated in the tests, ii) the protocol of the tests carried out indicating the results obtained, iii) the list of tests not carried out with the corresponding disclaimer; and, iv) additional information deemed appropriate by the CONCESSIONAIRE, the OSINERGMIN and/or the Inspector.
e) In the event that the Inspector and/or the OSINERGMIN considers that the result is unsatisfactory, as determined in the test certificates, the CONCESSIONAIRE (Testing Supervisor) shall proceed with the corresponding rectifications. The new test shall be executed only in the point or points that delivered unsatisfactory results. The GRANTOR and/or the OSINERGMIN cannot request new tests or inspections, nor observe or reject their results, if their representatives were not present during such tests or inspections.
f) Upon completion of the tests, the Testing ...
Execution of Tests. The execution of tests shall be subject to the following rules:
a) The Head of Tests shall conduct and supervise the tests and shall inform about the conditions of the same. He shall be also responsible of all the measurements, the calculation of the results and the preparation of the final report. His decision shall be determinant before any question regarding the test or its execution. The tests shall be made according to the procedures and instructions of the COES. The test of the optical fiber system shall follow the technical specifications established in Annex N° 5, Telecommunications, of this Contract.
b) The Concessionaire shall provide all the reasonable facilities to the Inspector to obtain real data, complete and acceptable regarding all the parts of the equipment related to the transmission of electric energy in the Power Line. Likewise, the Inspector shall have access to all the mechanisms related to the electro mechanic equipment of the Power Line ) The main constitutive components of the Power Line will be submitted to inspection upon requirement of the Inspector before the start of the test.