Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and, to this end, shall carry out the Project through NTSC, with due diligence and efficiency and in conformity with appropriate administrative, management, financial, engineering and traffic management practices, and sound environmental and social standards acceptable to the Association; and shall provide, promptly as needed, the funds, facilities, services and other resources required for the Project.
(b) Without limitation upon the provisions of paragraph (a) of this Section and except as the Borrower and the Association shall otherwise agree, the Borrower shall carry out, and cause to be carried out, the Project in accordance with the Implementation Program set forth in Schedule 4 to this Agreement.
(a) Except as the Association shall otherwise agree, procurement of the goods, works and consultants’ services required for the Project and to be financed out of the proceeds of the Credit shall be governed by the provisions of Schedule 3 to this Agreement, as said provisions may be further elaborated in the Procurement Plan.
(b) The Borrower shall update the Procurement Plan in accordance with guidelines acceptable to the Association and furnish such update to the Association not later than twelve (12) months after the date of the preceding Procurement Plan, for the Association’s approval.
Section 3.03. For the purposes of Section 9.06 of the General Conditions and without limitation thereto, the Borrower shall:
(a) prepare, on the basis of guidelines acceptable to the Association, and furnish to the Association not later than six (6) months after the Closing Date or such later date as may be agreed for this purpose between the Borrower and the Association, a plan designed to ensure the continued achievement of the objectives of the Project; and
(b) afford the Association a reasonable opportunity to exchange views with the Borrower on said plan.
Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and to this end shall cause: (i) SDR to coordinate (at the federal level) and issue guidelines related to the carrying out of the Program, to propose annual budgets for such Program and to take all actions necessary to ensure the availability of the counterpart funds for the carrying out of such Program in a timely manner; (ii) SUDENE to coordinate (at the regional level), supervise and monitor the Program; (iii) the Participating Banks, through Participating Agreements, to carry out the credit program included in Parts D and I of the Project; and (iv) EMBRAPA to carry out Part H of the Project, all with due diligence and efficiency, in accordance with appropriate administrative, financial and agricultural practices.
(b) Without any limitation or restriction upon any of its other obligations under the Loan Agreement, the Borrower shall cause the State, under contractual arrangements satisfactory to the Bank, to perform in accordance with the provisions of the Project Agreement, all the respective obligations of the State therein set forth, shall take or cause to be taken all action, including the provision of funds, facilities, services and other resources, necessary or appropriate to enable the State to perform its obligations, and shall not take or permit to be taken any action which would prevent or interfere with such performance.
(c) Without limitation to its obligations under paragraph (a) above, the Borrower shall: (i) take all action as shall be required to regulate, in a manner satisfactory to the Bank, the funding procedures which will ensure that the Executing Entities shall have the funds required for carrying out the Project available to them in a timely manner; and (ii) provide or cause SUDENE to provide advances in Cruzeiros into: (A) an account opened and operated by EMBRAPA; and (B) an account opened and operated by the State, as referred to in Section 2.01 (h) of the Project Agreement; all in a timely manner and in sufficient amounts for the purpose of financing the activities under Part H of the Project and under the State Project, respectively, as provided in each POA.
(d) The Borrower shall make the proceeds of the Loan allocated respectively:
(i) for purposes of the State Project available to the State; and (ii) for Part H of the Project available to EMBRAPA; under arrangements satisfactory to the Bank.
(e) The Borro...
Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and to this end: (i) shall carry out Part B of the Project through MINAGRA with due diligence and efficiency and in conformity with appropriate administrative, technical, scientific and financial practices, and shall provide, promptly as needed, the funds, facilities, services and other resources required for the Project; and (ii) shall, without any limitation or restriction upon any of its other obligations under this agreement, cause ANADER to perform in accordance with the provisions of the Project Agreement all the obligations of ANADER therein set forth, shall take and cause to be taken all action, including the provision of funds, facilities, services and other resources, necessary or appropriate to enable ANADER to perform such obligations, and shall not take or permit to be taken any action which would prevent or interfere with such performance.
(b) The Borrower shall make part of the proceeds of the Credit available to ANADER under a financing agreement to be entered into between the Borrower and ANADER, under terms and conditions which shall have been approved by the Association.
(c) The Borrower shall exercise its rights under the Financing Agreement in such manner as to protect the interests of the Borrower and the Association and to accomplish the purposes of the Credit, and except as the Association shall otherwise agree, the Borrower shall not assign, amend, abrogate or waive the Financing Agreement or any provision thereof.
(d) Without limitation upon the provisions of paragraph (a) of this Section and except as the Borrower and the Association shall otherwise agree, the Borrower shall carry out Part B of the Project in accordance with the Implementation Program set forth in Schedule 4 to this Agreement.
Section 3.02. Without limitation upon any of its obligations under Section 3.01 of this Agreement, the Borrower shall:
(a) establish and maintain, for the purposes of Part A of the Project, a Project Account (hereinafter referred to as Project Account A) in CAA on terms and conditions satisfactory to the Association to be used exclusively for the purposes of meeting expenditures incurred under Part A of the Project, which are not externally financed;
(b) establish and maintain, for the purposes of Part B of the Project, a Project Account (hereinafter referred to as Project Account B) in CAA on terms and conditions satisfac...
Execution of the Project. (a) The Recipient, through DEAT and DOT, declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement and, to this end, without any limitation or restriction upon any of its other obligations under this Agreement, the Recipient, through DEAT and DOT, shall, as provided, inter alia, in the Tripartite Agreement referred to in paragraph (c) of this Section, cause SAMSA, in respect of Parts A, D (1), and D (4) of the Project, and IOC, in respect of Parts B, C, D (2), D (3), and D (4) of the Project, to perform in accordance with the provisions of the Project Agreement all its obligations therein set forth take and cause to be taken all action including the provision of funds, facilities, services and other resources necessary or appropriate to enable SAMSA and IOC, respectively, to perform such obligations, and shall not take or permit to be taken any action which would prevent or interfere with such performance.
(b) Without limitation upon the provisions of paragraph (a) of this Section and except as the Recipient and the Bank shall otherwise agree, the Recipient shall, through DEAT and DOT, cause the Project to be carried out in accordance with the Implementation Program set forth in Schedule 4 to this Agreement.
(c) The Recipient shall, through DOT, enter into an agreement under terms and conditions consistent with the provisions of this Agreement and acceptable to the Bank (the Tripartite Arrangement) with SAMSA and IOC.
(d) The Recipient shall, through DOT, exercise its rights under the Tripartite Arrangement in such manner as to protect the interests of the Recipient and the Bank and to accomplish the purposes of the Grant, and, except as the Bank shall otherwise agree, the Recipient shall not assign, amend, abrogate or waive the Tripartite Arrangement or any provision thereof.
(a) Except as the Bank shall otherwise agree, procurement of the goods, works and services required for the Project and to be financed out of the proceeds of the GEF Trust Fund Grant shall be governed by the provisions of Schedule 3 to this Agreement, as said provisions may be further elaborated in the Procurement Plan.
(b) The Recipient, through DEAT and DOT, shall have the Procurement Plan updated in accordance with guidelines acceptable to the Bank, and furnish such update to the Bank not later than 12 months after the date of the preceding Procurement Plan, for the Bank’s approval.
Section 3.03. For the purposes of Section 9.08 of the G...
Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and, to this end, shall carry out the Project with due diligence and efficiency and in conformity with appropriate administrative, financial, technical, engineering and environmental standards and practices, and shall provide, promptly as needed, the funds, facilities, services and other resources required for the Project.
(b) Without limitation upon the provisions of paragraph (a) of this Section and except as the Borrower and the Association shall otherwise agree, the Borrower shall carry out the Project in accordance with the Implementation Program set forth in Schedule 4 to this Agreement and the provisions of the Environmental Management Plan.
Section 3.02. Except as the Association shall otherwise agree, procurement of the goods, works and consultants’ services required for the Project and to be financed out of the proceeds of the Credit shall be governed by the provisions of Schedule 3 to this Agreement.
Section 3.03. For the purposes of Section 9.06 of the General Conditions and without limitation thereto, the Borrower shall:
(a) prepare, on the basis of guidelines acceptable to the Association and furnish to the Association not later than six (6) months after the Closing Date or such later date as may be agreed for this purpose between the Borrower and the Association, a plan for the continued achievement of the objectives of the Project; and
(b) afford the Association a reasonable opportunity to exchange views with the Borrower on said plan.
Execution of the Project. Section 3.01. The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and, to this end, shall carry out the Project with due diligence and efficiency and in conformity with appropriate administrative, financial, engineering, and public utility practices and shall provide, promptly as needed, the funds, facilities, services and other resources required for the Project.
Section 3.02. Except as the Bank shall otherwise agree, procurement of the goods required for the Project and to be financed out of the proceeds of the Loan shall be governed by the provisions of Schedule 4 to this Agreement.
Section 3.03. For the purposes of Section 9.08 of the General Conditions and without any limitation thereto, the Borrower shall:
(a) prepare, on the basis of guidelines acceptable to the Bank, and furnish to the Bank not later than six (6) months after the Closing Date or such later date as may be agreed for this purpose between the Bank and the Borrower, a plan for the future operation of the Project; and
(b) afford the Bank a reasonable opportunity to exchange views with the Borrower on said plan.
Section 3.04. The Borrower shall:
(a) maintain policies and procedures adequate to enable it to monitor and evaluate on an ongoing basis, in accordance with indicators agreed with the Bank, the carrying out of the Project and the achievement of the objectives thereof;
(b) prepare, under terms of reference satisfactory to the Bank, and furnish to the Bank, on or about January 30, 1998 a report integrating the results of the monitoring and evaluation activities performed pursuant to paragraph (a) of this Section, on the progress achieved in the carrying out of the Project during the period preceding the date of said report and setting out the measures recommended to ensure the efficient carrying out of the Project and the achievement of the objectives thereof during the period following such date; and
(c) review with the Bank, by March 31, 1998, or such later date as the Bank shall request, the report referred to in paragraph (b) of this Section, and, thereafter, take all measures required to ensure the efficient completion of the Project and the achievement of the objectives thereof, based on the conclusions and recommendations of the said report and the Bank views on the matter.
Execution of the Project. (a) DAWASA declares its commitment to the objectives of the Project as set forth in Schedule 2 to the Development Credit Agreement, and, to this end, shall:
(i) carry out the Project with due diligence and efficiency and in conformity with appropriate administrative, financial, engineering, environmental, water, sewerage and resettlement practices, and shall provide, or cause to be provided, promptly as needed, the funds, facilities, services and other resources required for the Project;
(ii) duly and punctually perform in accordance with the provisions of the Development Contract, Lease Contract and the DAWASA Subloan Agreement all its obligations therein set forth and shall exercise its rights thereunder in such manner as to protect the interests of the Borrower and the Association and accomplish the purposes of the Credit; and
(iii) cause the Operator to carry out its obligations under the Project, Lease Contract and DAWASA Subloan Agreement with due diligence and efficiency and in conformity with appropriate administrative, financial, engineering, environmental, water, sewerage and resettlement practices.
(b) Without limitation upon the provisions of paragraph (a) of this Section and except as the Association and DAWASA shall otherwise agree, DAWASA shall carry out the Project in accordance with the Implementation Program set forth in Schedule 2 to this Agreement.
Section 2.02. Except as the Association shall otherwise agree, procurement of the goods, works and consultants’ services required for the Project and to be financed out of the proceeds of the Credit shall be governed by the provisions of Schedule 1 to this Agreement.
(a) DAWASA shall carry out or cause to be carried out, the obligations set forth in Sections 9.03, 9.04, 9.05, 9.06, 9.07 and 9.08 of the General Conditions (relating to insurance, use of goods and services, plans and schedules, records and reports, maintenance and land acquisition, respectively) in respect of this Agreement.
(b) For the purposes of Section 9.06 of the General Conditions and without limitation thereto, DAWASA shall, in conjunction with the Borrower:
(i) prepare, on the basis of guidelines acceptable to the Association and furnish to the Association not later than six (6) months after the Closing Date or such later date as may be agreed for this purpose among the Association, the Borrower and DAWASA, a plan for the future operation of the Project designed to ensure its sustainability; and
(ii) afford the Associati...
Execution of the Project. (a) The Borrower declares its commitment to the objective of the Project, and, to this end, shall carry out the Project with due diligence and efficiency and in conformity with appropriate administrative, financial, environmental, social, engineering, public utility and technical practices (including for dam safety), and shall provide, promptly as needed, the funds, facilities, services and other resources required for the Project.
(b) The Borrower also declares that: (i) no excavations or other types of works under Part A of the Project shall be carried out unless the use, or the process of acquisition, of land sites are carried out in a manner satisfactory to the Bank; (ii) no Resettlement shall occur under Part A of the Project; and (iii) if any temporary loss of crops, harvesting or use of land occurs under the Project, it shall cause WASCO to compensate any affected person(s) an amount equivalent to the market value of such temporary loss.
(c) Without limitation upon the provisions of paragraphs (a) and (b) of this Section and except as the Borrower and the Bank shall otherwise agree, the Borrower shall carry out the Project in accordance with the Implementation Program set forth in Schedule 5 to this Agreement.
(a) Except as the Bank shall otherwise agree, procurement of the goods, works and services required for the Project and to be financed out of the proceeds of the Loan shall be governed by the provisions of Schedule 4 to this Agreement, as said provisions may be further elaborated in the Procurement Plan.
(b) The Borrower shall update the Procurement Plan in accordance with guidelines acceptable to the Bank, and furnish such update to the Bank not later than 12 months after the date of the preceding Procurement Plan, for the Bank’s approval.
Section 3.03. For the purposes of Section 9.07 of the General Conditions and without limitation thereto, the Borrower shall:
(a) prepare, on the basis of guidelines acceptable to the Bank, and furnish to the Bank not later than six (6) months after the Closing Date or such later date as may be agreed for this purpose between the Borrower and the Bank, a plan for the future operation of the Project; and
(b) afford the Bank a reasonable opportunity to exchange views with the Borrower on said plan.
Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and, to this end, shall carry out the Project with due diligence and efficiency and in conformity with appropriate administrative, educational, and financial practices, and shall provide, promptly as needed, the funds, facilities, services and other resources required for the Project.
(b) Without limitation upon the provisions of paragraph (a) of this Section and except as the Borrower and the Bank shall otherwise agree, the Borrower shall carry out the Project in accordance with the Implementation Program set forth in Schedule 5 to this Agreement.
Section 3.02. Except as the Bank shall otherwise agree, procurement of the goods, works and consultants’ services required for the Project and to be financed out of the proceeds of the Loan shall be governed by the provisions of Schedule 4 to this Agreement.
Section 3.03. For the purposes of Section 9.08 of the General Conditions and without limitation thereto, the Borrower shall:
(a) prepare, on the basis of guidelines acceptable to the Bank, and furnish to the Bank not later than six months after the Closing Date or such later date as may be agreed for this purpose between the Borrower and the Bank, a plan designed to ensure the continued achievement of the objectives of the Project; and
(b) afford the Bank a reasonable opportunity to exchange views with the Borrower on said plan.
Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and, to this end, without any limitation or restriction upon any of its other obligations under this Agreement, shall cause Hunan to perform in accordance with the provisions of the Project Agreement all the obligations of Hunan therein set forth, shall take and cause to be taken all action, including the provision of funds, facilities, services and other resources, necessary or appropriate to enable Hunan to perform such obligations, and shall not take or permit to be taken any action which would prevent or interfere with such performance.
(b) The Borrower shall make the proceeds of the Loan available to Hunan on the following principal terms:
(i) The principal amount shall be made available in Dollars (determined on the date, or respective dates, of withdrawal from the Loan Account) of the value of the currency or currencies so withdrawn.
(ii) The following shall be recovered over a period of twenty (20) years, inclusive of a grace period of five (5) years: (A) the principal amount so made available; and (B) an amount equal to the fee paid pursuant to Section 2.04 of this Agreement.
(iii) Interest shall be charged on such principal amount withdrawn and outstanding from time to time at a rate equal to the rate of interest applicable from time to time to the Loan pursuant to the provisions of Section 2.06 of this Agreement.
(iv) A commitment fee shall be charged on such principal amount of the Loan so made available and not withdrawn from time to time at a rate equal to three fourths of one percent (3/4 of 1%) per annum.
Section 3.02. Except as the Bank shall otherwise agree procurement of goods, works and consultants’ services required for the Project and to be financed out of the proceeds of the Loan shall be governed by the provisions of Schedule 1 to the Project Agreement.
Section 3.03. The Bank and the Borrower hereby agree that the obligations set forth in Sections 9.04, 9.05, 9.06, 9.07, 9.08 and 9.09 of the General Conditions (relating to insurance, use of goods and services, plans and schedules, records and reports, maintenance and land acquisition, respectively) shall be carried out by Hunan pursuant to Section 2.03 of the Project Agreement.