EXTENSION OF CONTRACT TIME. A. The Contractor expressly covenants and agrees that in undertaking to complete the Work within the Contract Time, he has taken into consideration and made allowances for all delays and hindrances incidental to such Work, whether growing out of delays in securing Materials and Equipment or workmen, normal inclement weather, or otherwise.
B. If the Contractor is delayed at any time in the progress of the Work by an act or omission of the Owner, or its designated representative, any separate contractor employed by the Owner, or by Changed or Extra Work, industry-wide labor strikes, fire, epidemics, quarantine restrictions, freight embargoes, unavoidable casualties, abnormal weather conditions, any causes beyond the Contractor's control, or by any other cause which the Owner determines may justify the delay, then the Contract Time shall be extended for such reasonable time as the Owner may determine based on the timing and submittal requirements of this Section provided, however, that such delay could not have been avoided by the exercise of due diligence by the Contractor.
C. No extension of the Contract Time will be granted for:
1. Variations between original Contract quantities and actual quantities which cannot be predetermined and which variance (plus or minus) is less than twenty five (25) percent of the Contract quantities.
2. Rain, snow, wind, flood, or natural phenomena of normal intensity for the locality where the Work is performed.
3. Acts or omissions of the Contractor or its Subcontractors.
4. Delays occurring concurrently (either at the same time, on the same critical path or on a concurrent critical path) with delays attributable to acts or omissions of the Contractor or its Subcontractors.
5. Delays occurring to activities which are not on the then-current critical path.
D. A Request for an Extension of the Contract Time shall be made in writing to the Owner not later than seven (7) Days after the commencement of the delay. In the case of a continuing delay for the same cause only one request is necessary. The Contractor shall support its Request for an Extension of the Contract Time with a supplemental submittal, which shall be filed with the Owner within fourteen (14) Days of making the Request. The Contractor’s supplemental submittal shall include:
1. A description of the activities that were delayed, the reasons for the delay, an explanation of how they were delayed and a detailed factual statement relative to all relevant dates, locatio...
EXTENSION OF CONTRACT TIME. A delay beyond the contractor's control occasioned by an Act of God or act of omission on the part of the owner or by strikes, lockouts, fire, etc., may entitle the contractor to an extension of time in which to complete the work as determined by the Engineer, provided, however, that the contractor shall give immediate notice to the Engineer of the cause of such delay. For any single delay in the project in excess of 2 calendar days, the Contractor shall provide the Engineer written notice of such delay and reasons for said delay within 7 days of the occurrence of the delay.
EXTENSION OF CONTRACT TIME. Any extension of the Contract Time requested by Design/Builder for performance of any change in the Design Services or the Work ordered by Owner may be granted by mutual agreement and then set forth in the Change Order. Otherwise, extensions of the Contract Time must be requested by Design/Builder pursuant to the terms and conditions of Article 16 of this Agreement. The failure of Design/Builder to provide notice in writing to Owner in accordance with Article 16 of this Agreement of any request for extension of the Contract Time shall constitute a waiver by Design/Builder of any entitlement to an extension of the Contract Time.
EXTENSION OF CONTRACT TIME. 6.01 Should the amount of additional work of any kind or other special circumstances of any kind whatsoever occur such as to fairly entitle the CONTRACTOR to an extension of contract time, PPA shall determine the amount of such extension; provided that PPA is not bound to take into account any claim for an extension of time unless the contractor has prior to the expiration of time and within thirty (30) calendar days after such work has been commenced or after the circumstances leading to such claims have arisen, delivered to PPA notices in order that it could have investigated them at that time. Failure to provide such notice shall constitute a waiver by the CONTRACTOR of any claim. Upon receipt of full and detailed particulars, PPA shall examine the facts and extent of the delay and shall extend the contract time for completing the contract work when, in PPA’s opinion, the findings of facts justify an extension.
6.02 No extension of contract time shall be granted the CONTRACTOR due to (a) ordinary unfavorable weather conditions (b) inexcusable failure or negligence of CONTRACTOR to provide the required equipment, supplied or materials, or (c) other causes for which the Government is not directly responsible.
6.03 Extension of contract time may be granted only when the affected activities fall within the critical path of the PERT/CPM network.
6.04 No extension of contract time shall be granted when the reason given to support the request for extension was already considered in the determination of the original contract time during the conduct of detailed engineering and in the preparation of the contract documents as agreed upon by the parties before contract perfection.
6.05 Extension of contract time shall be granted for rainy/unworkable days considered unfavorable for the prosecution of the works at the site, based on the actual conditions obtained at the site, for such period in excess of the number of rainy/unworkable days predetermined by the PPA and/or for the equivalent period of delay due to major calamities such as exceptionally destructive typhoons, floods and earthquakes, and epidemics, and for causes such as non- delivery on time of materials, working drawings, or written information to be furnished by the PPA, non-acquisition of permit to enter private properties within the right of way resulting in complete paralization of construction activities, and other meritorious causes as determined by the PPA’s authorized Engineer and approved by th...
EXTENSION OF CONTRACT TIME. If the Work is not completed within the Contract Time and any previously authorized extensions thereof, RMWD may extend the Contract Time at his discretion
EXTENSION OF CONTRACT TIME. If the Changes in the Work relate solely to quantities, payment for that part of the Work will be made according to the conditions specified in clause GC 8.01.03,
EXTENSION OF CONTRACT TIME. The DISTRICT shall review the request for extension and respond to the CONTRACTOR within three (3) working days upon the receipt of such request. The extension of contract time shall be determined by the DISTRICT and approved by the Fire Chief. It is the CONTRACTOR’s responsibility to submit the request of extension. No extension shall be granted after the end of completion date.
EXTENSION OF CONTRACT TIME. .01 An application for an extension of Contract Time or any interim dates shall be made in writing by the Contractor to the Contract Administrator, as soon as the need for such extension becomes evident and at least 15 Days prior to the expiration of the Contract Time or interim date in question. The application for an extension of Contract Time or an interim date shall enumerate the reasons and impact on the critical path schedule, and state the length of extension required.
.02 Circumstances suitable for consideration of an extension of Contract Time or any interim date include the following:
a) Delays: See clause GC 3.07 (Delays).
b) Changes in the Work: See clause GC 3.10.01 (Changes in the Work).
c) Extra Work: See clause GC 3.10.02 (Extra Work).
EXTENSION OF CONTRACT TIME. If CopperBrook is delayed at any time in progress of the Work by changes ordered by Customer, by acts of the Customer, or for any other reason, including without limitation labor disputes, fire, a delay in deliveries, unavoidable casualties or other causes beyond CopperBrook’s control, the time for CopperBrook’s completion of the Work in the Proposal shall be extended and the Price shall be equitably increased by a change order for such reasonable time and amount as the Customer and CopperBrook shall mutual agree, which consent shall not be unreasonably withheld.
EXTENSION OF CONTRACT TIME. 6.01 Should the amount of additional work of any kind or other special circumstances of any kind whatsoever occur such as to fairly entitle the CONTRACTOR to an extension of contract time, PPA shall determine the length of such extension; provided that PPA is not bound to take into account any claim for an extension of time unless the contractor has prior to the expiration of the contract time and within thirty (30) calendar days after such work has been commenced or after the circumstances leading to such claim have arisen, delivered to PPA notices in order that it could have investigated them at that time. Failure to provide such notice shall constitute a waiver by the CONTRACTOR of any claim. Upon receipt of full and detailed particulars, PPA shall examine the facts and extent of the delay and shall extend the contract time for completing the contract work when, in PPA’s opinion, the findings of facts justify an extension.
6.02 No extension of contract time shall be granted the CONTRACTOR due to (a) ordinary unfavorable weather conditions; and (b) inexcusable failure or negligence of CONTRACTOR to provide the required equipment, supplies or materials.
6.03 No extension of contract time shall be granted when the reason given to support the request for extension was already considered in the determination of the original contract time.