EXTENSION OF CONTRACT TIME. A. The Contractor expressly covenants and agrees that in undertaking to complete the Work within the Contract Time, he has taken into consideration and made allowances for all delays and hindrances incidental to such Work, whether growing out of delays in securing Materials and Equipment or workmen, normal inclement weather, or otherwise.
EXTENSION OF CONTRACT TIME. A delay beyond the contractor's control occasioned by an Act of God or act of omission on the part of the owner or by strikes, lockouts, fire, etc., may entitle the contractor to an extension of time in which to complete the work as determined by the Engineer, provided, however, that the contractor shall give immediate notice to the Engineer of the cause of such delay. For any single delay in the project in excess of 2 calendar days, the Contractor shall provide the Engineer written notice of such delay and reasons for said delay within 7 days of the occurrence of the delay.
EXTENSION OF CONTRACT TIME. 6.01 Should the amount of additional work of any kind or other special circumstances of any kind whatsoever occur such as to fairly entitle the CONTRACTOR to an extension of contract time, PPA shall determine the amount of such extension; provided that PPA is not bound to take into account any claim for an extension of time unless the contractor has prior to the expiration of time and within thirty (30) calendar days after such work has been commenced or after the circumstances leading to such claims have arisen, delivered to PPA notices in order that it could have investigated them at that time. Failure to provide such notice shall constitute a waiver by the CONTRACTOR of any claim. Upon receipt of full and detailed particulars, PPA shall examine the facts and extent of the delay and shall extend the contract time for completing the contract work when, in PPA’s opinion, the findings of facts justify an extension.
EXTENSION OF CONTRACT TIME. Any extension of the Contract Time requested by Design/Builder for performance of any change in the Design Services or the Work ordered by Owner may be granted by mutual agreement and then set forth in the Change Order. Otherwise, extensions of the Contract Time must be requested by Design/Builder pursuant to the terms and conditions of Article 16 of this Agreement. The failure of Design/Builder to provide notice in writing to Owner in accordance with Article 16 of this Agreement of any request for extension of the Contract Time shall constitute a waiver by Design/Builder of any entitlement to an extension of the Contract Time.
EXTENSION OF CONTRACT TIME. If the Work is not completed within the Contract Time and any previously authorized extensions thereof, RMWD may extend the Contract Time at his discretion
EXTENSION OF CONTRACT TIME. .03 If the Extra Work relates solely to quantities, payment for the work will be made according to the conditions in clause GC 8.01.03,
EXTENSION OF CONTRACT TIME. .01 An application for an extension of Contract Time shall be made in writing by the Contractor to the Contract Administrator as soon as the need for such extension becomes evident and at least 15 Days prior to the expiration of the Contract Time. The application for an extension of Contract Time shall enumerate the reasons, and state the length of extension required.
EXTENSION OF CONTRACT TIME. (CHANGE ORDER) A delay beyond the Contractor's control occasioned by an Act of God, by act or omission on the part of the Owner or by strikes, lockouts, fire, etc. may entitle the Contractor to an extension of time in which to complete the work, provided, however, that the Contractor shall immediately give written notice to the Owner of the cause of such delay.
EXTENSION OF CONTRACT TIME. .02 If the Work is delayed by labour disputes, strikes or lock-outs - including lock-outs decreed or recommended to its members by a recognized contractor's association, of which the Contractor is a member or to which the Contractor is otherwise bound - which are beyond the Contractor's control, then the Contract Time shall be extended in accordance with subsection GC 3.07,
EXTENSION OF CONTRACT TIME. .1 The time for completion of the Work under the Contract may be extended in the event of one (1) or more of the following: