F3 Variation. F3.1 Subject to the provisions of this clause F3, the Client may request a variation to the Specification provided that such variation does not amount to a material change to the Specification. Such a change is hereinafter called a “Variation”.
Appears in 81 contracts
Samples: trn-prd-cdn-01.azureedge.net, trn-prd-cdn-01.azureedge.net, trn-prd-cdn-01.azureedge.net
F3 Variation. F3.1 Subject to the provisions of this clause F3, the Client Authority may request a variation to the Specification provided that such variation does not amount to a material change to the Specification. Such a change is hereinafter called a “Variation”.
Appears in 8 contracts
F3 Variation. F3.1 Subject to the provisions of this clause F3, the Client may request a variation to the Specification provided that such variation does not amount to a material change to the Specification. Such a change is hereinafter thereinafter called a “Variation”.
Appears in 3 contracts
Samples: trn-prd-cdn-01.azureedge.net, trn-prd-cdn-01.azureedge.net, trn-prd-cdn-01.azureedge.net
F3 Variation. F3.1 Subject to the provisions of this clause Clause F3, the Client AUTHORITY/Contracting AUTHORITY may request a variation to the Specification provided that such variation does not amount to a material change to the Specification. Such a change is hereinafter called a “Variation”.
Appears in 3 contracts
Samples: Merchant Acquirer Framework Agreement, Merchant Acquirer Framework Agreement, Framework Contract
F3 Variation. F3.1 Subject to the provisions of this clause F3, the Client may request a variation to the Specification Services provided that such variation does not amount to a material change to the SpecificationServices. Such a change is hereinafter called a “Variation”.
Appears in 1 contract
Samples: www.stockporthomes.org
F3 Variation. F3.1 Subject to the provisions of this clause F3, the Client Authority may request a variation to the Specification provided that such variation does not amount to a material change to the Specification. Such a change is hereinafter thereinafter called a “Variation”.
Appears in 1 contract
Samples: data.gov.uk
F3 Variation. F3.1 Subject to the provisions of this clause F3, the Client may request a variation to the Specification provided that such a variation does not amount to a material change to the Specification. Such a change is hereinafter called a “Variation”. F3.2 the Client may request a Variation by notifying the Contractor in writing of the “Variation” and by giving the Contractor sufficient information to assess the extent of the Variation and to consider whether any change to the Contract Price is required in order to implement the Variation.
Appears in 1 contract
Samples: data.gov.uk
F3 Variation. F3.1 Subject to the provisions of this clause F3, the Client may request a variation to the Specification provided that Client and Contractor mutually agree that such variation does not amount to a material change to the Specification. Such a change is hereinafter called a “Variation”.
Appears in 1 contract
Samples: data.gov.uk
F3 Variation. F3.1 Subject to the provisions of this clause F3, the Client may request a variation to the Specification provided that such variation does not amount to a material change to the Specification. Such a change is hereinafter called a ““ Variation”.
Appears in 1 contract
Samples: data.gov.uk