Common use of Fast Track/Multiple Completion Times Clause in Contracts

Fast Track/Multiple Completion Times. If the Owner elects to “fast-track” or develop the Project in multiple stages, Construction Manager shall organize and perform its services as appropriate to each stage. Each stage of the Project may have a unique schedule for completion and a specific Construction Cost Limitation, at Owner’s discretion.

Appears in 11 contracts

Samples: Construction Manager at Risk Agreement, Construction Manager Agreement, Construction Manager Agreement

AutoNDA by SimpleDocs

Fast Track/Multiple Completion Times. If the Owner elects to “fast-track” or develop the Project in multiple stages, Construction Manager shall organize and perform its services as appropriate to each stage. Each stage of the Project may have a unique schedule for completion and a specific Construction Cost Limitation, at Owner’s discretion.

Appears in 6 contracts

Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Manager at Risk Agreement

Fast Track/Multiple Completion Times. If the Owner elects to “fast-track” or develop the Project in multiple stages, Construction Manager Design/Build Contractor shall organize and perform its services as appropriate to each stage. Each stage of the Project may have a unique schedule for completion and a specific Construction Cost Limitation, at Owner’s discretion.

Appears in 6 contracts

Samples: Design/Build Agreement, Design/Build Agreement, Design/Build Agreement

Fast Track/Multiple Completion Times. If the Owner elects to “fast-track” or develop the Project in multiple stages, Construction Manager Design/Build Contractor shall organize and perform its services as appropriate to each stage. Each stage of the Project may have a unique schedule for completion and a specific Construction Cost Limitation, at Owner’s discretion.

Appears in 3 contracts

Samples: Design/Build Agreement, Design/Build Agreement, Design/Build Agreement

Fast Track/Multiple Completion Times. If the Owner elects to “fast-track” or develop the Project in multiple stages, Construction Manager shall will organize and perform its services as appropriate to each stage. Each stage of the Project may have a unique schedule for completion and a specific Construction Cost LimitationCCL, at Owner’s discretion.

Appears in 2 contracts

Samples: Construction Manager at Risk Contract, Construction Manager at Risk Contract

Fast Track/Multiple Completion Times. If the Owner elects to “fast―fast-track” track‖ or develop the Project in multiple stages, Construction Manager shall organize and perform its services as appropriate to each stage. Each stage of the Project may have a unique schedule for completion and a specific Construction Cost Limitation, at Owner’s discretion.

Appears in 1 contract

Samples: Construction Manager at Risk Agreement

AutoNDA by SimpleDocs

Fast Track/Multiple Completion Times. If the Owner elects to “fast-track” or develop the Project in multiple stages, Construction Manager the Design/Build Contractor shall cooperate fully with the Owner and organize and perform its services as to be most appropriate to and efficient for each stage. Each stage of the Project may have a unique schedule for completion and a specific Construction Cost LimitationCCL, at Owner’s discretion.

Appears in 1 contract

Samples: Design/Build Agreement

Fast Track/Multiple Completion Times. If the Owner elects to “fast-fast- track” or develop the Project in multiple stages, Construction Manager shall organize and perform its services as appropriate to each stage. Each stage of the Project may have a unique schedule for completion and a specific Construction Cost Limitationconstruction budget, at Owner’s discretion.

Appears in 1 contract

Samples: Solicitation Amendment

Fast Track/Multiple Completion Times. If the Owner elects to “fast―fast-track” track‖ or develop the Project in multiple stages, Construction Manager Design/Build Contractor shall organize and perform its services as appropriate to each stage. Each stage of the Project may have a unique schedule for completion and a specific Construction Cost Limitation, at Owner’s discretion.

Appears in 1 contract

Samples: Design/Build Agreement