Feasibility Studies and Abortive works Clause Samples

Feasibility Studies and Abortive works. 6.1 Cambs HIA reserves the right to charge a fee up to the maximum for any work completed by the agency where work does not proceed to a grant. This should be proportionate to the time and resources deployed o the individual project. 6.2 Cambs HIA will seek agreement in advance, for each occasion, with the relevant GVO or PSHO for feasibility studies when funding is being sought for feasibility of proposed works by the engagement of third parties e.g. structural engineer's report. 6.3 Cambs HIA shall seek agreement, on each occasion, for any payment or for abortive works e.g. architectural design completed but grant does not go ahead where the payment sought is for the architectural design element alone.