Final Completion Certificate. The Principal must issue a Final Completion Certificate in the form at Appendix 8 at the end of the Defects Notification Period, or once the Contractor has remedied all defects in the Works, or obtained a CCC, whichever is the later.
Appears in 4 contracts
Samples: Medium Works Contract, Medium Works Contract, Medium Works Contract
Final Completion Certificate. The Principal must issue a Final Completion Certificate in the form at Appendix 8 9 at the end of the Defects Notification Period, or once the Contractor has remedied all defects in the Works, or obtained a CCC, whichever is the later.
Appears in 3 contracts
Samples: Medium Works Contract, Medium Works Contract, Medium Works Contract