FORCE MAJEURE EVENTS OR ACTS OF GOD. 10.1 The construction stage, which runs from the Closing Date to the Commercial Start-Up, shall be subject to the provisions established in Clauses 10.2 to 10.8. Starting with the Project’s integration into the SEIN declared by the COES up to the expiration of the Contract term, the research, assignment of responsibilities, determination and payment of compensations, review or challenge, request for force majeure or acts of God for issues involving the interruption of the supply, as well as any other matters related to the NTCSE, as supplemented, shall follow the provisions established in said standards, as supplemented or amended, and the Applicable Laws and Provisions.
Appears in 4 contracts
Samples: STS Concession Contract, STS Concession Contract, STS Concession Contract
FORCE MAJEURE EVENTS OR ACTS OF GOD. 10.1 10.1. The construction stage, which runs from the Closing Date to the Startup of Commercial Start-UpOperation, shall be subject to the provisions established in Clauses 10.2 to 10.8. Starting with the Project’s integration into the SEIN declared by the COES up to the expiration of the Contract termSEIN, the research, assignment of responsibilities, determination and payment of compensations, review or challenge, request for force majeure or acts of God for issues involving the interruption of the supply, as well as any other matters related to the NTCSETechnical Quality Standards for Electrical Services, as supplemented, shall follow the provisions established in said standards, as supplemented or amended, and the Applicable Laws and Provisions.
Appears in 3 contracts
Samples: SGT Concession Contract, SGT Concession Contract, SGT Concession Contract