Force Majeure Events. a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following: i) acts of God; ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities; iii) acts of war (whether declared or undeclared), invasion or civil unrest; iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG or of any Law or any of their respective obligations under this Agreement); v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals; vi) earthquakes, explosions, accidents, landslides; fire; vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality; viii) chemical or radioactive contamination or ionizing radiation; or ix) damage to or breakdown of transmission facilities of GETCO/ DISCOMs; x) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.
Appears in 27 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Force Majeure Events. a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
i) acts of God;
ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
iii) acts of war (whether declared or undeclared), invasion or civil unrest;
iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG Power Producer or DISCOM of any Law or any of their respective obligations under this Agreement);
v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
vi) earthquakes, explosions, accidents, landslides; fire;
vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
viii) chemical or radioactive contamination or ionizing radiation; or
ix) damage to or breakdown of transmission facilities of GETCO/ DISCOMs;
x) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.
Appears in 10 contracts
Samples: Power Purchase Agreement (Ppa), Power Purchase Agreement, Power Purchase Agreement (Ppa)
Force Majeure Events. a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
i) acts of God;
ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
iii) acts of war (whether declared or undeclared), invasion or civil unrest;
iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG or PGVCL of any Law or any of their respective obligations under this Agreement);
v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
vi) earthquakes, explosions, accidents, landslides; fire;
vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
viii) chemical or radioactive contamination or ionizing radiation; or
ix) damage to or breakdown of transmission facilities of GETCO/ DISCOMs;
x) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.
Appears in 9 contracts
Samples: Power Purchase Agreement (Ppa), Power Purchase Agreement (Ppa), Power Purchase Agreement
Force Majeure Events. a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
i) acts of God;
ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
iii) acts of war (whether declared or undeclared), invasion or civil unrest;
iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG Power Producer or GUVNL of any Law or any of their respective obligations under this Agreement);
v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
vi) earthquakes, explosions, accidents, landslides; fire;
vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
viii) chemical or radioactive contamination or ionizing radiation; or
ix) damage to or breakdown of transmission facilities of GETCO/ DISCOMs;
x) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.
Appears in 8 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement (Ppa)
Force Majeure Events. a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
i) acts of God;
ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
iii) acts of war (whether declared or undeclared), invasion or civil unrest;
iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG Power Producer or GUVNL of any Law or any of their respective obligations under this Agreement);
v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
vi) earthquakes, explosions, accidents, landslides; fire;
vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
viii) chemical or radioactive contamination or ionizing radiation; or
ix) damage to or breakdown of transmission facilities of GETCO/ GETCO / DISCOMs;
x) Exceptionally adverse weather condition conditions which are in excess of the statistical measure of the last hundred (100) years.
xi) non-fulfillment of obligations under Land Lease Agreement and Implementation & Support Agreement attributable to GPCL leading to delay in commissioning of the project
Appears in 7 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement (Ppa), Power Purchase Agreement (Ppa)
Force Majeure Events. a) 8.1.1. Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
i) i. acts of God;
ii) . typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
iii) . acts of war (whether declared or undeclared), invasion or civil unrest;
iv) . any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG Hybrid Power Developer or MSEDCL of any Law or any of their respective obligations under this Agreement);
v) v. inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
vi) . earthquakes, explosions, accidents, landslides; fire;
vii) . expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
viii) . chemical or radioactive contamination or ionizing radiation; or
ix) . An event of force majeure affecting the concerned STU/MSEDCL, as the case may be, thereby affecting the evacuation of power from the delivery points by MSEDCL.
x. damage to or breakdown of transmission facilities of GETCO/ DISCOMsSTU/MSEDCL;
x) xi. Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.
Appears in 3 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Force Majeure Events. a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
i) i. acts of God;
ii) . typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
iii) . acts of war (whether declared or undeclared), invasion or civil unrest;
iv) . any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG Power Producer or APDCL of any Law or any of their respective obligations under this Agreement);
v) v. inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
vi) . earthquakes, explosions, accidents, landslides; fire;
vii) . expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
viii) . chemical or radioactive contamination or ionizing radiation; or
ix) . damage to or breakdown of transmission facilities of GETCO/ DISCOMsCTU/STU/DISCOM;
x) x. Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.
Appears in 2 contracts
Force Majeure Events. a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
i) acts of God;
ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
iii) acts of war (whether declared or undeclared), invasion or civil unrest;
iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG or UGVCL of any Law or any of their respective obligations under this Agreement);
v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
vi) earthquakes, explosions, accidents, landslides; fire;
vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
viii) chemical or radioactive contamination or ionizing radiation; or
ix) damage to or breakdown of transmission facilities of GETCO/ DISCOMs;
x) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.
Appears in 2 contracts
Samples: Power Purchase Agreement (Ppa), Power Purchase Agreement
Force Majeure Events. a) 8.1.1 Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
(i) acts of God;
(ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
(iii) acts of war (whether declared or undeclared), invasion or civil unrest;
(iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG Biomass Power Developer or MSEDCL of any Law or any of their respective obligations under this Agreement);
(v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
(vi) earthquakes, explosions, accidents, landslides; fire;
(vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
(viii) chemical or radioactive contamination or ionizing radiation; or
(ix) An event of force majeure affecting the concerned STU/MSEDCL, as the case may be, thereby affecting the evacuation of power from the delivery points by MSEDCL.
(x) damage to or breakdown of transmission facilities of GETCO/ DISCOMsSTU/MSEDCL;
x(xi) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Events. a) 12.2.1 Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events Events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "βForce Majeure Event"β) beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
ia) acts Acts of God;
iib) typhoonsTyphoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
iiic) acts Acts of war (whether declared or undeclared), invasion or civil unrest;
ivd) any Any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG Power Producer or GRIDCO of any Law or any of their respective obligations under this Agreement);
ve) inability Inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvalslegal approvals;
vif) earthquakesEarthquakes, explosions, accidents, landslides; fire;
viig) expropriation and/or Expropriation and/ or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
viiih) chemical Chemical or radioactive contamination or ionizing radiation; or;
ixi) damage Damage to or breakdown of transmission facilities of GETCO/ DISCOMsGRIDCO/ CTU;
xj) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred 100 (100hundred) years.
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Events. a) 8.1.1 Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
(i) acts of God;
(ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
(iii) acts of war (whether declared or undeclared), invasion or civil unrest;
(iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG Floating Solar Power Developer or MSEDCL of any Law or any of their respective obligations under this Agreement);
(v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
(vi) earthquakes, explosions, accidents, landslides; fire;
(vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
(viii) chemical or radioactive contamination or ionizing radiation; or
(ix) An event of force majeure affecting the concerned STU/MSEDCL, as the case may be, thereby affecting the evacuation of power from the delivery points by MSEDCL.
(x) damage to or breakdown of transmission facilities of GETCO/ DISCOMsSTU/MSEDCL;
x(xi) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Events. a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
i) acts of God;
ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
iii) acts of war (whether declared or undeclared), invasion or civil unrest;
iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG Power Producer or GUVNL of any Law or any of their respective obligations under this Agreement);
v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
vi) earthquakes, explosions, accidents, landslides; fire;
vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
viii) chemical or radioactive contamination or ionizing radiation; or
ix) damage to or breakdown of transmission facilities of GETCO/ DISCOMs;
x) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Events. a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
i) acts of God;
ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
iii) acts of war (whether declared or undeclared), invasion or civil unrest;
iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG Power Producer or GUVNL of any Law or any of their respective obligations under this Agreement);
v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
vi) earthquakes, explosions, accidents, landslides; fire;
vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
viii) chemical or radioactive contamination or ionizing radiation; or
ix) damage to or breakdown of transmission facilities of GETCO/ DISCOMs;
x) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.
Appears in 1 contract
Samples: Power Purchase Agreement (Ppa)
Force Majeure Events. a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (( "a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
i) acts of God;
ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
iii) acts of war (whether declared or undeclared), invasion or civil unrest;
iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG Power Producer or GUVNL of any Law or any of their respective obligations under this Agreement);
v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
vi) earthquakes, explosions, accidents, landslides; fire;
vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
viii) chemical or radioactive contamination or ionizing radiation; or
ix) damage to or breakdown of transmission facilities of GETCO/ DISCOMs;
x) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Events. a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:
i) acts of God;
ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities;
iii) acts of war (whether declared or undeclared), invasion or civil unrest;
iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG Power Producer or GUVNL of any Law or any of their respective obligations under this Agreement);
v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals;
vi) earthquakes, explosions, accidents, landslides; fire;
vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality;
viii) chemical or radioactive contamination or ionizing radiation; or
ix) damage to or breakdown of transmission facilities of CTU / GETCO/ DISCOMs;
x) Exceptionally adverse weather condition conditions which are in excess of the statistical measure of the last hundred (100) years.
Appears in 1 contract
Samples: Power Purchase Agreement