Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”): (i) If prior to the Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement. (ii) If during the Delivery Term: (A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to Seller of such failure; provided that, if Seller within forty-five (45) days of receipt of Notice from Buyer, presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by Xxxxx’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that Seller diligently pursues such mitigation plan throughout the mitigation period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or (B) the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that Seller shall have up to ninety (90) days following such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced no later than twenty-four (24) months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreement.
Appears in 10 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”)::
(i) If prior to if after the Initial Energy Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity (as may be adjusted pursuant to Sections 3.1(e)(ii) or 3.9(d)) to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to Seller of such failure(“Force Majeure Project Failure”); provided that: (A) if the Project may be capable of resuming normal production, then Seller shall be entitled to an additional period of time (not to exceed six (6) months) to remedy the Force Majeure if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer that a Force Majeure Project Failure has occurred, Seller presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that and Seller diligently pursues such mitigation plan throughout the mitigation said additional period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
or (B) if the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that , upon Buyer’s written request to Seller, Seller shall have up to not more than ninety (90) days following such Force Majeure event to obtain a report from retain an independent, third third-party engineer stating to determine whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer.
(ii) if prior to the Commercial Operation Date Seller is unable, due solely to a Force Majeure event, to place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, as set forth Section 3.9(c)(i) and Section 3.9(c)(ii)(C)(a “Force Majeure Development Failure”); provided further that if such engineerin the event of a Force Majeure caused by a catastrophic natural disaster, upon Buyer’s report concludes that written request to Seller, Seller shall have not more than ninety (90) days to retain an independent, third-party engineer to determine whether the Project is capable of being repaired or replaced within such twenty-four (24) month period additional months and Seller undertakes and continues such repair or replacement with due diligence, then provide Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration a copy of the period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months)report, after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreementat no cost to Buyer.]
Appears in 6 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”):
(i) If prior to if after the Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity (as may be adjusted pursuant to Sections 3.1(e)(ii) or 3.9(d)) to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to Seller of such failure(“Force Majeure Project Failure”); provided that: if the Project may be capable of resuming normal production, then Seller shall be entitled to an additional period of time (not to exceed six (6) months) to remedy the Force Majeure if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer that a Force Majeure Project Failure has occurred, Seller presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that and Seller diligently pursues such mitigation plan throughout the mitigation said additional period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
(B) or if the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that , upon Buyer’s written request to Seller, Seller shall have up to not more than ninety (90) days following such Force Majeure event to obtain a report from retain an independent, third party engineer stating to determine whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer. if prior to the Construction Start Date or Commercial Operation Date, as applicable, Seller is unable, due solely to a Force Majeure event, to achieve the Construction Start Date or place the Project into Commercial Operation by either of the Guaranteed Milestones, after applicable extensions or cure periods have run, as set forth in Sections 3.9(c)(iii) and (iv) (in either case a “Force Majeure Development Failure”); provided further that if such engineerin the event of a Force Majeure caused by a catastrophic natural disaster, upon Buyer’s report concludes that written request to Seller, Seller shall have not more than ninety (90) days to retain an independent, third party engineer to determine whether the Project is capable of being repaired or replaced within such twenty-four (24) month period additional months and Seller undertakes and continues such repair or replacement with due diligence, then provide Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration a copy of the period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months)report, after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreementat no cost to Buyer.
Appears in 4 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”):
(i) If prior to the Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to Seller of such failure; provided that, if Seller within forty-five (45) days of receipt of Notice from Buyer, presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that Seller diligently pursues such mitigation plan throughout the mitigation period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
(B) the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that Seller shall have up to ninety (90) days following such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced no later than twenty-four (24) months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreement.
Appears in 4 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”)::
(i) If prior to the Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve if after the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term,:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project (“Force Majeure Project Failure”) and Buyer has provided Notice to notified Seller of such failure; provided that, that if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer regarding the Force Majeure Project Failure, presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a11.2(a) until the expiration of the mitigation additional period deemed necessary by Seller to repair the Project (which shall not to exceed six (6) months); provided that Seller diligently pursues such mitigation plan throughout the mitigation said additional period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its performance obligations under this Agreement; or
(B) the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that Seller shall have up to ninety (90) days following such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months or less from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a11.2(a) until the expiration of the period deemed necessary by the engineer’s report (which shall not to exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all its performance obligations under this Agreement;
(ii) if prior to the Construction Start Date or Commercial Operation Date, as applicable, Seller is unable, due solely to a Force Majeure event, to achieve the Construction Start Date or place the Project into Commercial Operation by either of the Guaranteed Milestones, after applicable extensions or cure periods have run, as set forth in Sections 3.9(c)(iii) and (iv) (in either case a “Force Majeure Development Failure”); provided that in the event of a Force Majeure caused by a catastrophic natural disaster, upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within twenty-four (24) additional months and provide Buyer a copy of the engineer’s report, at no cost to Buyer provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.2(a) until the expiration of the period deemed necessary by the engineer’s report (not to exceed twenty-four (24) months), after which time, Buyer may terminate unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying its performance obligations under this Agreement.
Appears in 2 contracts
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”)::
(i) If prior to if after the Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project (“Force Majeure Project Failure”) and Buyer has provided Notice to notified Seller in writing of such failure; provided that, :
(A) if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer regarding the Force Majeure Project Failure, presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a11.2(a) until the expiration of the mitigation additional period deemed necessary by for Seller to repair the Project (which shall not to exceed six (6) months); provided that Seller diligently pursues such mitigation plan throughout the mitigation period, said additional period and after which time Buyer may terminate this Agreement unless the Project has been repaired, repaired and the Seller has resumed and is satisfying all of its performance obligations under this Agreement; or
(B) if the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; disaster provided that Seller shall have up to ninety (90) days following such Force Majeure event Event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer; provided provided, further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a11.2(a) until the expiration of the period deemed necessary by the engineer’s report while Seller continues such repair or replacement (which shall not to exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its performance obligations under this Agreement.; or
Appears in 2 contracts
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”)::
(i) If prior to if after the Initial Energy Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity (as may be adjusted pursuant to Sections 3.1(e)(ii) or 3.9(d)) to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to Seller of such failure(“Force Majeure Project Failure”); provided that: (A) if the Project may be capable of resuming normal production, then Seller shall be entitled to an additional period of time (not to exceed six (6) months) to remedy the Force Majeure if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer that a Force Majeure Project Failure has occurred, Seller presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that and Seller diligently pursues such mitigation plan throughout the mitigation said additional period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
or (B) if the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that , upon Buyer’s written request to Seller, Seller shall have up to not more than ninety (90) days following such Force Majeure event to obtain a report from retain an independent, third third-party engineer stating to determine whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer.
(ii) if prior to the Commercial Operation Date Seller is unable, due solely to a Force Majeure event, to place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, as set forth Section 3.9(c)(i) and Section 3.9(c)(ii)(C)(a “Force Majeure Development Failure”); provided further that if such engineerin the event of a Force Majeure caused by a catastrophic natural disaster, upon Buyer’s report concludes that written request to Seller, Seller shall have not more than ninety (90) days to retain an independent, third-party engineer to determine whether the Project is capable of being repaired or replaced within such twenty-four (24) month period additional months and Seller undertakes and continues such repair or replacement with due diligence, then provide Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration a copy of the period deemed necessary by the engineer’s report report, at no cost to Buyer.] [(which ii) if prior to the Expected Initial Energy Delivery Date, Seller is unable, due solely to a Force Majeure event, to achieve the Initial Energy Delivery Date on or prior to the Expected Initial Energy Delivery Date (a “Force Majeure Development Failure”); provided that in the event of a Force Majeure caused by a catastrophic natural disaster, upon Buyer’s written request to Seller, Seller shall have not exceed more than ninety (90) days to retain an independent, third-party engineer to determine whether the Project is capable of being repaired or replaced within twenty-four (24) months)additional months and provide Buyer a copy of the engineer’s report, after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreementat no cost to Buyer.]
Appears in 2 contracts
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”):
(i) If prior to the Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to Seller of such failure; provided that, if Seller within forty-five (45) days of receipt of Notice from Buyer, presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by Xxxxx’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that Seller diligently pursues such mitigation plan throughout the mitigation period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
(B) the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that Seller shall have up to ninety (90) days following such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced no later than twenty-four (24) months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreement.
Appears in 2 contracts
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”)::
(i) If prior to if after the Initial Energy Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity (as may be adjusted pursuant to Sections 3.1(e)(ii) or 3.9(d)) to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to Seller of such failure(“Force Majeure Project Failure”); provided that:
(A) if the Project may be capable of resuming normal production, then Seller shall be entitled to an additional period of time (not to exceed six (6) months) to remedy the Force Majeure if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer that a Force Majeure Project Failure has occurred, Seller presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that and Seller diligently pursues such mitigation plan throughout the mitigation said additional period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
(B) if the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that , upon Buyer’s written request to Seller, Seller shall have up to not more than ninety (90) days following such Force Majeure event to obtain a report from retain an independent, third third-party engineer stating to determine whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer.
(ii) if prior to the Commercial Operation Date Seller is unable, due solely to a Force Majeure event, to place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, as set forth Section 3.9(c)(iii) (a “Force Majeure Development Failure”); provided further that if such engineerin the event of a Force Majeure caused by a catastrophic natural disaster, upon Buyer’s report concludes that written request to Seller, Seller shall have not more than ninety (90) days to retain an independent, third-party engineer to determine whether the Project is capable of being repaired or replaced within such twenty-four (24) month period additional months and Seller undertakes and continues such repair or replacement with due diligence, then provide Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration a copy of the period deemed necessary by the engineer’s report report, at no cost to Buyer.] [(which ii) if prior to the Expected Initial Energy Delivery Date, Seller is unable, due solely to a Force Majeure event, to achieve the Initial Energy Delivery Date on or prior to the Expected Initial Energy Delivery Date (a “Force Majeure Development Failure”); provided that in the event of a Force Majeure caused by a catastrophic natural disaster, upon Buyer’s written request to Seller, Seller shall have not exceed more than ninety (90) days to retain an independent, third-party engineer to determine whether the Project is capable of being repaired or replaced within twenty-four (24) months)additional months and provide Buyer a copy of the engineer’s report, after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreementat no cost to Buyer.]
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”)::
(i) If prior to if after the Initial Energy Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity (as may be adjusted pursuant to Sections 3.1(e)(ii) or 3.9(d)) to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to Seller of such failure(“Force Majeure Project Failure”); provided that:
(A) if the Project may be capable of resuming normal production, then Seller shall be entitled to an additional period of time (not to exceed six (6) months) to remedy the Force Majeure if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer that a Force Majeure Project Failure has occurred, Seller presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that and Seller diligently pursues such mitigation plan throughout the mitigation said additional period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
(B) if the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that , upon Buyer’s written request to Seller, Seller shall have up to not more than ninety (90) days following such Force Majeure event to obtain a report from retain an independent, third third-party engineer stating to determine whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer.
(ii) if prior to the Commercial Operation Date Seller is unable, due solely to a Force Majeure event, to place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, as set forth Section 3.9(c)(iii) (a “Force Majeure Development Failure”); provided further that if such engineerin the event of a Force Majeure caused by a catastrophic natural disaster, upon Buyer’s report concludes that written request to Seller, Seller shall have not more than ninety (90) days to retain an independent, third-party engineer to determine whether the Project is capable of being repaired or replaced within such twenty-four (24) month period additional months and Seller undertakes and continues such repair or replacement with due diligence, then provide Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration a copy of the period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months)report, after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreementat no cost to Buyer.]
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”)::
(i) If prior to if after the Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to Seller of such failure(“Force Majeure Project Failure”); provided that:
(A) if the Project may be capable of resuming normal production, then Seller shall be entitled to an additional period of time (not to exceed six (6) months) to remedy the Force Majeure if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer that a Force Majeure Project Failure has occurred, Seller presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by Xxxxx’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that and Seller diligently pursues such mitigation plan throughout the mitigation said additional period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
(B) if the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that , upon Xxxxx’s written request to Seller, Seller shall have up to not more than ninety (90) days following such Force Majeure event to obtain a report from retain an independent, third party engineer stating to determine whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months from the date and provide Buyer a copy of the report engineer’s report, at no cost to Buyer.
(ii) if prior to the Construction Start Date or Commercial Operation Date, as applicable, Seller is unable, due solely to a Force Majeure event, to achieve the Construction Start Date or place the Project into Commercial Operation by either of the Guaranteed Milestones, after applicable extensions or cure periods have run, as set forth in Sections 3.9(c)(iii) and (iv) (in either case a “Force Majeure Development Failure”); provided that in the event of a Force Majeure caused by a catastrophic natural disaster, upon Xxxxx’s written request to Seller, Seller shall have not more than ninety (90) days to retain an independent, third party engineer to determine whether the Project is capable of being repaired or replaced within twenty-four (24) additional months and provide Buyer with a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four [Short Term Existing: Seller to delete this subsection (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) monthsii), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreement.]
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: following (each constituting a “Force Majeure Failure”):
(i) If prior to the Delivery TermConstruction Start Date or Commercial Operation Date, as applicable, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Construction Start Date or place the Project into Commercial Operation by either of the Guaranteed Commercial Operation DateProject Milestones, after applicable extensions or cure periods have run, as set forth in Section 3.9(cSections 3.9(c)(iii) and (iv); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period months from the date of the engineer’s report and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If after the Commercial Operation Date but prior to the start of the Delivery Term:
(A) Seller is unable, due solely to a Force Majeure event that was not caused by a catastrophic natural disaster, to achieve the Guaranteed Initial Energy Delivery Date, as may be extended on a day for day basis equal to the number of days allowed for (A) any Permitted Extension and any Project Cure Period, as authorized under and exercised in accordance with Section 3.9(c)(iii)(A)(II) and Section 3.9(c)(iv), respectively, and (B) any Initial Extension and any Additional Extension that is accepted, as authorized under and exercised in accordance with Section 3.1(c)(ii); provided that Seller Notices Buyer as soon as practicable after the Force Majeure event and presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by Buyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that Seller diligently pursues such mitigation plan throughout the mitigation period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
(B) Seller is unable, due solely to a Force Majeure event that was caused by a catastrophic natural disaster, to achieve the Guaranteed Initial Energy Delivery Date, as may be extended on a day for day basis equal to the number of days allowed for (A) any Permitted Extension and any Project Cure Period, as authorized under and exercised in accordance with Section 3.9(c)(iii)(A)(II) and Section 3.9(c)(iv), respectively, and (B) any Initial Extension and any Additional Extension that is accepted, as authorized under and exercised in accordance with Section 3.1(c)(ii), provided that Seller Notices Buyer as soon as practicable after the Force Majeure event, then upon Buyer’s written request to Seller, Seller shall obtain within ninety (90) days from the date of such Force Majeure event, a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the engineer’s report and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying all of its obligations under this Agreement. For the avoidance of doubt, the Delivery Term cannot commence until the Project is repaired or replaced, as applicable, and Seller is satisfying all of its obligations under this Agreement, including the obligations set forth in 3.1(c)(i) that Seller must demonstrate to achieve the Intial Energy Delivery Date.
(iii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to notified Seller of such failure; provided that, if Seller within forty-five (45) days of receipt of Notice from Buyer, presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that Seller diligently pursues such mitigation plan throughout the mitigation period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
(B) the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that Seller shall have up to ninety (90) days following such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced no later than twenty-four (24) months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreement.
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”)::
(i) If prior to if after the Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to Seller after the commencement of such failureForce Majeure event (“Force Majeure Project Failure”); provided that:
(A) if the Project may be capable of resuming normal production, then Seller shall be entitled to an additional period of time (not to exceed six (6) months) to remedy the Force Majeure if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer that a Force Majeure Project Failure has occurred, Seller presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and reasonably satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that and Seller diligently pursues such mitigation plan throughout the mitigation said additional period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
(B) if the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that , upon Buyer’s written request to Seller, Seller shall have up to not more than ninety (90) days following such Force Majeure event to obtain a report from retain an independent, third party engineer stating to determine whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer.
(ii) if prior to the Construction Start Date or Commercial Operation Date, as applicable, Seller is unable, due solely to a Force Majeure event, to achieve the Construction Start Date or place the Project into Commercial Operation by either of the Guaranteed Milestones, after applicable Permitted Extensions or cure periods have run, as set forth in Sections 3.9(c)(iii) and (iv) (in either case a “Force Majeure Development Failure”); provided further that if such engineerin the event of a Force Majeure caused by a catastrophic natural disaster, upon Buyer’s report concludes that written request to Seller, Seller shall have not more than ninety (90) days to retain an independent, third party engineer to determine whether the Project is capable of being repaired or replaced within such twenty-four (24) month period additional months and Seller undertakes and continues such repair or replacement with due diligence, then provide Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration a copy of the period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months)report, after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreementat no cost to Buyer.
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”)::
(i) If prior to the Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve if after the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term,:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project (“Force Majeure Project Failure”) and Buyer has provided Notice to notified Seller of such failure; provided that, that if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer regarding the Force Majeure Project Failure, presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a11.2(a) until the expiration of the mitigation additional period deemed necessary by Seller to repair the Project (which shall not to exceed six (6) months); provided that Seller diligently pursues such mitigation plan throughout the mitigation said additional period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its performance obligations under this Agreement; or
(B) the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that Seller shall have up to ninety (90) days following such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months or less from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a11.2(a) until the expiration of the period deemed necessary by the engineer’s report (which shall not to exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all its performance obligations under this Agreement;
(ii) if prior to the Construction Start Date or Commercial Operation Date, as applicable, Seller is unable, due solely to a Force Majeure event, to achieve the Construction Start Date or place the Project into Commercial Operation by either of the Guaranteed Milestones, after applicable extensions or cure periods have run, as set forth in Sections 3.9(c)(iii) and (iv) (in either case a “Force Majeure Development Failure”); provided that in the event of a Force Majeure caused by a catastrophic natural disaster, upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within twenty-four (24) additional months and provide Buyer a copy of the engineer’s report, at no cost to Buyer provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.2(a) until the expiration of the period deemed necessary by the engineer’s report (not to exceed twenty-four (24) months), after which time, Buyer may terminate unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its performance obligations under this Agreement.
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”)::
(i) If prior to the Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve if after the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project (“Force Majeure Project Failure”) and Buyer has provided Notice to notified Seller of such failure; provided that, that if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer regarding the Force Majeure Project Failure, presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by Xxxxx’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation additional period deemed necessary by Seller to repair the Project (which shall not to exceed six (6) months); provided that Seller diligently pursues such mitigation plan throughout the mitigation said additional period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its performance obligations under this Agreement; or
(B) the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that Seller shall have up to ninety (90) days following such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months or less from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the period deemed necessary by the engineer’s report (which shall not to exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all its performance obligations under this Agreement;
(ii) if prior to the Construction Start Date or Commercial Operation Date, as applicable, Seller is unable, due solely to a Force Majeure event, to achieve the Construction Start Date or place the Project into Commercial Operation by either of the Guaranteed Milestones, after applicable extensions or cure periods have run, as set forth in Sections 3.9(c)(iii) and (iv) (in either case a “Force Majeure Development Failure”); provided that in the event of a Force Majeure caused by a catastrophic natural disaster, upon Xxxxx’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within twenty-four (24) additional months and provide Buyer a copy of the engineer’s report, at no cost to Buyer provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the period deemed necessary by the engineer’s report (not to exceed twenty-four (24) months), after which time, Buyer may terminate unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its performance obligations under this Agreement.
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”)::
(i) If prior to if after the Initial Energy Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) in cases where the following paragraph (B) does not apply (it being agreed that paragraph (B) shall prevail over this paragraph (A) when both paragraphs may be applicable), the Project fails to deliver at least forty percent (40%) of the Contract Quantity to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project (“Force Majeure Project Failure”) and Buyer has provided Notice to notified Seller of such failure; provided that, that if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer regarding the Force Majeure Project Failure, presents Buyer with a plan for mitigation of the effect of the Force Majeure with the mitigation to be completed within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation additional period deemed necessary by Seller to repair the Project (which shall not to exceed six (6) months); provided that Seller diligently pursues such mitigation plan throughout the mitigation said additional period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its performance obligations under this Agreement; or
(B) the Project is destroyed or a material portion thereof is rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; , provided that Seller shall have up to ninety (90) days following such Force Majeure event to obtain a report from an independent, third party engineer Licensed Professional Engineer stating whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months or less from the date of the report and Seller shall provide Buyer with a copy of the engineerLicensed Professional Engineer’s report, at no cost to Buyer; provided further that if such engineerLicensed Professional Engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the period deemed necessary by the engineerLicensed Professional Engineer’s report (which shall not to exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its performance obligations under this Agreement;
(ii) if prior to the Construction Start Date or Commercial Operation Date, as applicable, Seller is unable, due solely to a Force Majeure event, to achieve the Construction Start Date or place the Project into Commercial Operation by either of the Guaranteed Milestones, after applicable extensions or cure periods have run, as set forth in Sections 3.9(c)(iii) and 3.9(c)(iv) and 3.1(g)(iii)(A)(III) (in either case a “Force Majeure Development Failure”); provided that in the event of a Force Majeure caused by a catastrophic natural disaster, upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party Licensed Professional Engineer stating whether the Project is capable of being repaired or replaced within twenty-four (24) additional months and provide Buyer a copy of the Licensed Professional Engineer’s report, at no cost to Buyer provided further that if such Licensed Professional Engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the period deemed necessary by the Licensed Professional Engineer’s report (not to exceed twenty-four (24) months), after which time, Buyer may terminate unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its performance obligations under this Agreement. If Buyer terminates this Agreement pursuant to this Section 11.1(a)(ii) due to a Force Majeure Development Failure caused by Seller’s failure to achieve the Guaranteed Commercial Operation Date, then Seller shall also pay Buyer the Force Majeure Payment. Any termination of this Agreement pursuant to this Section 11.1(a) shall be treated as a “no-fault” termination, shall not give rise to any Event of Default and all Performance Assurance shall be returned according to Section 8.4.
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”)::
(i) If prior to if after the Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity (as may be adjusted pursuant to Sections 3.1(e)(ii) or 3.9(d)) to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to Seller of such failure(“Force Majeure Project Failure”); provided that:
(A) if the Project may be capable of resuming normal production, then Seller shall be entitled to an additional period of time (not to exceed six (6) months) to remedy the Force Majeure if Seller within forty-five (45) days of receipt of Notice from BuyerBuyer that a Force Majeure Project Failure has occurred, Seller presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by XxxxxBuyer’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that and Seller diligently pursues such mitigation plan throughout the mitigation said additional period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
(B) if the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that , upon Buyer’s written request to Seller, Seller shall have up to not more than ninety (90) days following such Force Majeure event to obtain a report from retain an independent, third third-party engineer stating to determine whether the Project is capable of being repaired or replaced no later than within twenty-four (24) additional months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer.
(ii) if prior to the Commercial Operation Date Seller is unable, due solely to a Force Majeure event, to place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, as set forth Section 3.9(c)(iii) (a “Force Majeure Development Failure”); provided further that if such engineerin the event of a Force Majeure caused by a catastrophic natural disaster, upon Buyer’s report concludes that written request to Seller, Seller shall have not more than ninety (90) days to retain an independent, third-party engineer to determine whether the Project is capable of being repaired or replaced within such twenty-four (24) month period additional months and Seller undertakes and continues such repair or replacement with due diligence, then provide Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration a copy of the period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months)report, after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreementat no cost to Buyer.
Appears in 1 contract
Samples: Power Purchase Agreement
Force Majeure Failure. Buyer shall have the right, but not the obligation, to terminate this Agreement after the occurrence of any of the following: (each constituting a “Force Majeure Failure”):
(i) If prior to the Delivery Term, Seller is unable, due solely to a Force Majeure event, to achieve the Commercial Operation Date or place the Project into Commercial Operation by the Guaranteed Commercial Operation Date, after applicable extensions or cure periods have run, as set forth in Section 3.9(c); provided that if a Force Majeure event is caused by a catastrophic natural disaster, then upon Buyer’s written request to Seller, Seller shall have not more than ninety (90) days from the date of such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller shall provide Buyer a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within twenty-four (24) months from the date of the Seller provides the engineer’s report to Buyer and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the repair or replacement period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and Seller has resumed and is satisfying its obligations under this Agreement.
(ii) If during the Delivery Term:
(A) the Project fails to deliver at least forty percent (40%) of the Contract Quantity to the Delivery Point for a period of twelve (12) consecutive rolling months following a Force Majeure event that materially and adversely impacts the Project and Buyer has provided Notice to Seller of such failure; provided that, if Seller within forty-five (45) days of receipt of Notice from Buyer, presents Buyer with a plan for mitigation of the effect of the Force Majeure within a period not to exceed six (6) months from the above-mentioned Notice date, which plan is commercially reasonable and satisfactory to Buyer, as evidenced by Xxxxx’s written acknowledgement of such plan, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the mitigation period deemed necessary by Seller to repair the Project (which shall not exceed six (6) months); provided that Seller diligently pursues such mitigation plan throughout the mitigation period, and after which time Buyer may terminate this Agreement unless the Project has been repaired, and the Seller has resumed and is satisfying all of its obligations under this Agreement; or
(B) the Project is destroyed or rendered inoperable by a Force Majeure event caused by a catastrophic natural disaster; provided that Seller shall have up to ninety (90) days following such Force Majeure event to obtain a report from an independent, third party engineer stating whether the Project is capable of being repaired or replaced no later than twenty-four (24) months from the date of the report and Seller shall provide Buyer with a copy of the engineer’s report, at no cost to Buyer; provided further that if such engineer’s report concludes that the Project is capable of being repaired or replaced within such twenty-four (24) month period and Seller undertakes and continues such repair or replacement with due diligence, then Buyer shall not have the right to terminate this Agreement pursuant to this Section 11.1(a) until the expiration of the period deemed necessary by the engineer’s report (which shall not exceed twenty-four (24) months), after which time, Buyer may terminate this Agreement unless the Project has been repaired or replaced, as applicable, and the Seller has resumed and is satisfying all of its obligations under this Agreement.